Interior Tenders

Interior Tenders

VETERANS AFFAIRS, DEPARTMENT OF USA Tender

Electrical Cables And Wires...+1Electrical and Electronics
Corrigendum : Closing Date Modified
United States
Closing Date20 Mar 2025
Tender AmountRefer Documents 
Details: 556-23-101 Renovate B134-2c Clc July 22, 2024 Construction Statement Of Work Date: July 22, 2024 Project Number: 556-23-101 Project Name: Renovate B134-2c Clc Location: B134 C-wing 2nd Floor Clc Captain James A. Lovell Fhcc 3001 Green Bay Rd, North Chicago, Il 60064 Part 1: Project Scope Of Work Overview: Contractor Shall Provide All Tools, Materials, Labor, Quality Assurance, And Supervision For Renovations Resulting In A Complete, Compliant, And Fully-functional Clc, Including Erection Of Temporary Enclosures Preventing The Release Of Dust Outside Of The Work Area, Selective Demolition, Metal Studs, Gypsum Wall Board, Paint, Ceilings, Flooring, Electrical Power And Light, Modifications To The Fire Protection System, Telecom Cabling, Fire Alarm, And Other Work To Affect A Complete Turn-key Space Supporting Described Clinical Function(s) And Equipment. Finished Square Footage Is Approximately 12,590. The Current Hvac System And All Its Components Installed On The Roof Will Be Tied Into The New Space On The 2nd Floor. Part 2: Period Of Performance: The Following Model Presents The Summary Logic Of The Milestone Sequence Working Backward From The Delivery Date Of The Longest Lead Time In The Critical Path To Determine A Mobilization Date, And Then Forward From The Delivery Date Of The Longest Lead Time To Completion Of All Work. Notes: Durations Shown Are In Calendar Days. Actual Award And Ntp Dates Will Be Revised To Match Their Occurrence. Time Consumed For Resubmission And Review Must Be Made Up By The Gc To Ensure That All Submittals Of This Contract Are Approved Within 60 Days Of Ntp. See Section 01 32 16.15 Project Schedules With Long Lead Items (d/b/b Projects At Fhcc). Part 3: Detailed Project Requirements: Project Objectives: This Project Is Required To Renovate The Described Space As Expediently And Compliantly As Practical. Meet Or Exceed All Code, Technical, And Programmatic Requirements Adopted, Established, Revised, And Or Published By Va Or The Many Organizations Listed In The Several Specifications. Expedite The Delivery Of A Highly Functional, Complete, Compliant, And Safe Workspace For The User Service. List Of Ae Documents To Be Included In This Contract: See: 00 01 10 Table Of Contents And The Entire Project Manual See: 00 01 15 List Of Drawing Sheets And The Entire Volume Of Drawings Pre-bid Conference: Va Shall Schedule Two Pre-bid Conferences Required To Be Attended By Prospective Bidders To Observe Current Conditions Within The Work Area(s). The Ae Shall Not Attend The Pre-bid Events. No Questions Will Be Allowed During The Events. All Questions By All Prospective Contractors Shall Follow The Rfi Process Described In The Solicitation. Prospective Bidders Shall Not Attempt To Contact The Ae Or Va Facilities Engineering Staff During The Solicitation And Bidding Period. The Ae And Va Facilities Engineering Staff Are Instructed To Ignore All Such Inquiries And Report Them To The Va Contracting Officer. All Inquiries Regarding This Project Shall Be Presented As Complete And Coherent Requests For Information (rfi) Specifically Citing Design Or Specification Sections, Pages, Paragraphs, Notes, Details, Etc. To Enable Responses To Rfi S. Follow The Instructions Provided By The Contracting Officer Within The Solicitation Regarding Submission Of Rfi S. Va Will Post Responses Developed To Enable All Prospective Bidders To Receive The Same Information At The Same Time. Project Scheduling And Mobilization On Site: The Contractor Shall Not Mobilize On Site Until All Required Submittals Are Prepared, Transmitted, Reviewed, And Accepted By Va, And The Delivery Dates Of Long Lead Items Have Been Established By The Respective Manufacturers. Significant Time For This Essential Is Included In The Period Of Performance. Critical Components And Other Long Lead Items Shall Require Proof Of Purchase And An Established Delivery Date Delivered To The Contracting Officer And Cor To Complete Va Approval Of The Schedule. Approval To Mobilize Shall Be In Writing By The Contracting Officer In Consultation With The Cor And Facility Safety Manager. Prior To Beginning Work, Post And Maintain At Each Work Area All Current Emergency Contact Information, Va Infection Control Risk Assessment (icra)/permit, Interim Life Safety Measures (ilsm), And Other Information Required By Va And The Gc Project- Specific Safety Plan, At All Entry Points To The Work Area. The Target Mobilization Date Is Determined By First Establishing The Delivery Date Of The Longest Lead Time Material Or System Along The Critical Path, Which In This Project Is Predominantly Hvac Equipment, But Is Likely To Also Consider Shop-fabricated Doors And Frames, And Then Working Back Along The Critical Path Listing All Predecessor Work Activities. The Baseline Period Of Performance Is Certain To Change Between Initial Project Schedule And Acceptance Of The Final Project Schedule. The Contracting Officer, At His Or Her Discretion And Judgement, Will Issue A Contract Modification Revising The Period Of Performance End Date. As There Is No Change To The Quantity Or Quality Of The Work, The Contract Value Shall Not Change. Performance Of The Work: Erect And Maintain A Dust-tight Containment Around The Work Area Which Complies With Applicable Code Associated With Ul-rated Wall Assemblies And Maintenance Of Egress Paths. Containment Shall Enable Access To The Work, Without Obstructing Access To Adjacent Suites Or Rooms. Establish Hepa Air Purification. Review And Follow Specification 01 35 33 Infection Control Requirements As Applicable To This Location And Work. Follow Pra & Icra Plan And Permit Generated And Issued By Va. Remove Only Upon Completion Approval Of The Cor. After Establishing And Gaining Approval Of The Temporary Modular Hard Plastic Dust-tight Construction Dust Control Barrier System, Including Lockable Door. Where This Is The Sole Containment, Include Differential Pressure Monitoring For The Work Area, With Monitor Located Adjacent To The Temporary Entry Door. Where Fire Or Smoke-rated Wall Assemblies Are Planned For Alternation Even If Temporarily, Provide A Dust-tight 1-hour Rated Temporary Construction Wall With Locking Door To Isolate The Area Of Work, Finished With One Coat Of Paint On The Outside Were Indicated. The 1-hour Temporary Wall Shall Include Differential Pressure Monitoring For The Work Area, With Monitor Located Adjacent To The Temporary Entry Door. The 1-hour Temporary Wall And Differential Pressure Monitoring Must Be Complete And Approved Prior To Removal Of The (outer) Temporary Modular Wall Barrier, And Commencement Of Demolition Within The Space. Prior To Removal Of A Temporary Fire Or Smoke-rated Walls, Completely Restore Rated Wall Assemblies Required Of The Work, And Then Re-erect The Temporary Modular Hard Plastic, Dust-tight, Barrier System. In No Case Shall Any Containment Be Removed Unless And Until The Work Area, Including The Inside Of The Ventilation System, Has Been Thoroughly Cleaned And Approved For Progress Toward Activation. Immediately Prior To Turnover, Remove All Air Filters From The Ventilation System Used During Construction, And Supply And Install New Specified Filters. Supply Case Quantities Of Each Filter To Va With The System. Perform Selective Demolition And Construction As Described In The Specifications And Drawings. Special Acceptance Criteria For The Work Shall Include: Hvac System Shall Not Be Acceptable In Whole Or In Part Unless And Until Testing, Adjusting, And Balancing (tab) Is Completed And Accepted In Accordance With The Specifications, Drawings, And The Current Edition Ashrae 170 Ventilation Of Health Care Facilities (and Errata) Requirements Specific To The Room/suite Type And Purpose. Va Reserves The Right To Conduct, Or Have Conducted, Verification Testing, And Deduct Its Cost From The Contract If Noncompliant Conditions Are Found. The Contractor Shall Provide Eia/tia Testing And Certification Of All New Cat 6a Communications Cable. Restore All Finishes Damaged During The Work Match Existing. Thoroughly Clean All Surfaces Using Hepa-filtered Vacuum Cleaner And Anti-bacterial Wipes. Part 4: Meetings, Submittals, And Deliverables: Kick-off Meeting And Documentation The Contractor S Project Manager And Field Supervisor Shall Attend A Preconstruction Safety And Coordination Meeting To Discuss Project Details. Kick-off Meeting Documentation: Prepare And Submit For Review And Acceptance A Draft Critical Path Method (cpm) Baseline Schedule Reflecting Each Phase And Activity Of The Work Beginning With Mobilization, Including Each Critical Activity, And Each Essential Task Required To Optimally Meet The Objectives Of The Project. The Baseline Schedule Must Also Include All Activities To Be Performed By Va, Including Maintenance Shops Support, Safety And Infection Control, The Ae, The Commissioning Agent, Etc. It Is Expected That This Timeline Will List All Activities Of The Work Leading Up To The Delivery Of Long Lead Items, The Target Dates Of Long Lead Items, Installation Of Long Lead Items, And Each Work Activity That Follows Until All Work Is Complete, Compliant, And Ready For Acceptance. The Durations Of Each Phase Will Change Once The Gc Completes All Procurement Activities And Submit For Review And Approval The Final Baseline Schedule. To Enable Objective Assessment Of Costs And Progress, The Baseline Schedule Shall Be Cost-loaded At Each Work Activity (essentially Division 02 On), Ensuring That The Total Cost Of Each Phase And Division Of Work Match The Corresponding Schedule Of Values, And The Total Of The Construction Contract At Award. Develop The Cpm Schedule In Sufficient Detail To Enable Readers To Understand All Planned Activities, Their Predecessors, And Successors, Who Is Performing The Work, Durations, And Costs. Activity Durations Shall Not Exceed Two Calendar Weeks. Indicate Resource Sdvosb Status. The Project Manual Index Of Specifications Is A Useful Guide For Starting The Cpm Schedule And Schedule Of Values In Sufficient Detail. For Example: Simply Listing Hvac Is Unacceptable For Projects Including More Than Basic Work In This Category. The Inclusion Of Specifications For An Ahu, Controls, Ductwork, Demolition Of Each, Testing And Balancing, Etc. Also Prompt Their Inclusion As Categories Of Activities And Tasks In The Schedule. In Fact, For Larger Work Categories, Breaking Down The Cost By System/material And Installation And Testing Enables Partial Payment For Higher Cost Items Upon Delivery Into The Facility Work Area. Preparation And Processing Of Submittals Are Gc Procurement (administrative) Activities And Not Work Activities Contributing To The Compensable Work In The Field. Should The Contractor Elect To Include Submittal Planning In Their Internal Use Schedule For Their Own Purposes, Do Not Show Those Line Items In The Schedule Submitted To Va For Consideration In The Baseline Schedule. Not Less Than One Item Per Subcontractor At Any Tier. Subcontractors, By Definition, Are Contributing Work In The Field To The Project. Pass-throughs Are Not Acceptable. Include All Expected Utility System Shutdowns, Road Closures, Crane Lifts, And Off- Hours Work In The Cpm Schedule. Do Not Include Costs Associated With Non-work Administrative Activities Inherent In The Listed Work Items. The Government Cannot Pay For What It Has Not Inspected And Accepted As Compliant, Or For Activities Which Add No Value To Va Facilities. Front-loading Proposals, Bids, Schedules Of Values, And Line-item Costs Of Cost-loaded Cpm Schedules With Non-work Items Puts The Contractor, The Government, And The Bonding Company At Otherwise Avoidable Risk Associated With Paying Out More Than The Value Of Work In Place Should The Work Stop Prior To Completion. Administrative And Managerial Activities Associated With Each Work Line Item Are To Be Included In Each Line Item, Along With Prorated Overhead And Profit. The Contractor Shall Prepare And Submit Sf-1413 For Each Subcontractor To The Co, Copying The Cor. List Of All Subcontractors And Suppliers, Including Company Names, Office Address, And Main Point Of Contact Name With Telephone Number, And Sdvosb Status. As Required At 01 35 26 Safety Requirements: Develop And Submit A Project- Specific Construction Safety And Accident Prevention Plan With Project-specific Procedures, Processes, Analysis, And Details, Including But Not Limited To: Access And Use The U.s. Army Corps Of Engineers Em 385-1-1 Safety And Health Requirements And Its Appendix A Minimum Basic Outline For Accident Prevention Plans For Development Of Meaningful, Effective, And Compliant Project Safety Plans. Submission Of Generic, Non-project Specific Safety Plans Will Be Rejected, Resulting In A Contractor-caused Delay In Commencement Of The Work. Project-specific Activity Hazard Analysis (aha), Which Forms The Basis Of The Construction Safety And Accident Prevention Plan Highlighting Identified Risks Such As Isolation Of Stored Energy (lock-out*), Fall Protection, Or Confined Space Access. (*) Note That Tag-out Is Not An Acceptable Form Of Isolation, Therefore It Was Intentional Not To Use The Term Loto. Submit An Electronic Copy Of The Gc And All Subcontractor Competent Persons Osha 30-hour Construction Safety Training Certificates With Project-specific Construction Safety And Accident Prevention Plan. Submit An Electronic Copy Of All Workers Osha 30-hour Construction Safety Training Certificates Or Cards Prior To Allowing Entry To The Site. Assist The Cor In Completing Project-specific Va Infection Control Risk Assessment (icra) And Interim Life Safety Measures (ilsm) Documentation. Public Safety Compliance Requirements: The Following Applies To All Va And Navy Properties, Including Leased Facilities, Regardless Of Building Occupancy Or Current Use And Does Not Differentiate Between Medical Or Administrative Spaces As All Are Occupied By People We Are Collectively Working To Protect From Harm Including Contractor Staff. Contractors Shall Adhere To And Ensure Compliance With Federal Laws, Regulations, And Executive Orders Regarding Screening, Vaccinations, And Or Testing Designed To Protect Contractor Employee And General Public Health And Safety, As Well As All Associated Health Information And Personally Identifiable Information. All Contractor Staff Share A Common Moral Responsibility To Stay Away From The Facility When Feeling Ill. Quality Control Plan And Quality Assurance Plan: 01 40 00 Quality Requirements Is Included In Its Entirety In This Contract. This Specification Is Brief But Very Informative And Enabling To Those Who Approach It As An Opportunity. Submittal Register (aka Submittal Log) Is Described In Quality Assurance Of The Above Specification, And The Project Manual At 01 33 23. Submittal Register Must List Each Submission Listed In Each And Every Specification. Because Each Project Is Different, Do Not Recycle Submittal Logs From Other Projects. (dis)approval Of A Submittal Never Constitutes A Change To The Quantity, Quality, Cost, Or Duration Of A Contract. The General Contractor Is Solely Responsible For Submitting And Delivering Complete And Compliant Work. Defective Work Shall Be Removed And Replaced At The Contractor S Expense. The Government Has The Right And Responsibility To Withhold Funds Equivalent To The Cost For The Government To Complete The Work Should The Contractor Fail To Promptly Act In Executing The Work Or Remedying Defective Work. To Help Prevent (unfortunately) Common Shortcomings And Mistakes With Submittal Preparation And Submission, As Well As Ensure That The Installation Of Systems Is Complete And Compliant, The Gc Shall Provide The Services Of At Least One Licensed Professional Engineer To Pre-review And Certify As Compliant All Submittals And Subsequent Systems Prior To Requests For Va Or Its Ae To Review For Compliance. For Projects Requiring Alteration Or Replacement Of Mechanical Systems, The Gc Consulting Engineer Is Required To Be A Licensed Mechanical Engineer. Similarly, For Projects With Significant Electrical Scope, Retain A Licensed Electrical Engineer. The Consulting Engineer May Be A Firm. Engaging A Verified Sdvosb Firm Is Always Encouraged. The Consulting Engineer (or Firm) Cannot Be The Ae Of-record Or Part Of Their Consulting Team. Upon Issuance Of Notice To Proceed, Gc Shall Immediately Submit To Va For Review And Information The Contact Information And Credentials Of The Contracted Consulting Engineer. Construction Progress Meetings: The Contractor S Project Manager And Field Supervisor Shall Provide On-site Weekly Construction Progress Meetings With The Cor For The Entire Period Of Performance. Include Preparation Of Meeting Agendas, And Subsequent Minutes Of The Meeting For Each Event Not Later Than 1 Day (next Business Day) After Each Meeting. Construction Progress Meeting Agenda S And Minutes Shall Include No Less Than: List Of Invitees/attendees, List Of Past/ongoing And New Issues Or Concerns, Indicate Days Remaining Per The Contract, Detail Any Safety Incidents, And Include Current Updated Copies Of The Rfi Log, The Shop Drawing Log, And A Detailed 3-week Look- Ahead And Utility Shutdown Schedule. Daily Reports: The Contractor Shall Provide A Daily Report Each Day, Along With Accompanying Digital Photos And Other Supporting Documents. The Daily Report Shall Include: List Of Issues Or Concerns, Days Remaining Per The Contract, Detail Regarding Any Safety Incidents, Detail Of Daily Safety Inspections (including Items Checked And Corrective Actions Taken), Notations Regarding Any Visitors To The Work Area. Use Of Va Form 10101 Contractor Production Report (fillable Pdf At Https://www.va.gov/vaforms/va/pdf/va10101.pdf) Is Required Each Day Even On Days With No Contractor Activity, Which Is What To Report On Such Days. Contractor May And Should Provide More Information Than Shown In The Standard Form, But The Standard Form Is Required. The Report Must Be Accompanied By Relevant Time And Date-stamped Photos Of Construction Progress Of Sufficient Quantity And Detail To Enable Viewers To Clearly See The Progress Of All Work To-date, All Issues Discovered (including Those Which Become The Subject Of Rfi S). Email The Va Form 10101 Contractor Production Report And Photos To The Cor Not Later Than 9 Am The Next Working Day. No Photography On Va Premises Is Allowed Without Written Permission Of The Cor. In No Case Shall The Gc Allow Any Team Member To Take Photographs With Patients, Visitors, Or Employees In The Picture. Acceptance And Closeout: Acceptance Criteria For The Work: Schedule Demonstration Of New Equipment And Systems At Least 21 Calendar Days In Advance With The Cor. Provide Factory Startup And Certification Of All Systems. Demonstrate The Operation Of The System. Newly Installed Water Or Medical Gas Piping And Distribution System Components Shall Be Flushed And Disinfected Prior To Being Placed In Service. Include Documenting Completion/certifications. Startup And Testing Of New Systems Or Equipment, Or Moving In Va Purchased Equipment Or Furnishings, Or Their Use, Does Not Constitute Any Form Of Acceptance (or Beneficial Occupancy). The Project Is Planned Around The Complete, Complaint, And Unconditional Fulfillment Of All Requirements Of The Contract Which Enable The Work To Be Complete By Definition. Please Work With Va To Expedite This Process. Closeout Records: Provide One Full-size, And One Half-size Printed Set Of As-built Drawings, As Well As Cd-rom Or Dvd-rom Media Containing A Complete Archive Of All Project Documents And Files, Including But Not Limited To: As-built Record Drawings Of The Installed Condition As Cad And Pdf Files. Approved Shop Drawings. Operations And Maintenance Manuals. Spare Parts Lists. All Photographs. All Daily Reports. All Communications. All Pay Applications. All Communication, Change, And Cost Data. All Safety Records. A Project Warranty For Construction Written By The General Contractor, Projected To Start Upon Final Acceptance By Va (typically Within A Business Week Of Receiving A Complete And Compliant Closeout Package). Where Manufacturer S Warranties Exceed One Year, Provide All Documentation Necessary For Va To Exercise Warranty Rights Beyond The Standard Gc Warranty. Where Specified, Such As With Roofing Systems, Provide The Warranty Written By The Manufacturer To Va For The Term Specified Or Greater (typically 20 Years). Note That Moving Furnishings Or Equipment Into The Space Does Not Constitute Occupancy Or Acceptance, However, Damage To Completed Work During These Activities Shall Be The Responsibility Of Va To Correct. Lien Waivers And Other Documents Required By The Contracting Officer. Part 5: Applicable Performance Standards All Work Shall Comply With All Va And Fhcc Policies Including And Not Limited To: Va Construction Safety And Va Infection Control Policies. Codes, Standards And Executive Orders (topic 1) Found At Http://www.cfm.va.gov/til/cpro.asp 01 32 16.15 Project Schedules With Long Lead Items (d/b/b Projects At Fhcc) 01 35 26 Safety Requirements 01 35 33 Infection Control Requirements 01 40 00 Quality Requirements 01 41 00 Regulatory Requirements 01 42 16 Definitions And Abbreviations Coordinating With Va-retained Commissioning Agent (cxa) And Architect-engineer (ae). Va Intends To Retain The Services Of An Independent Cxa. Ae Field-verification And Documentation Of Compliant Systems Remains An Essential Part Of Construction Period Services. The General Contractor Is Responsible For Communication And Cooperation With The Ae And Cxa And Enabling Compliant Execution Of Contracts. No Action Or Inaction By The Ae, Cxa, Va, Or Other Government Agencies Ever Relieves The Gc From Responsibility To Deliver 100% Of The Project Requirements As Specified And Designed. The General Contractor Shall Have A Competent Supervisory Person On Site At All Times When Any Worker(s) Or Subcontractor(s) Are Present. The General Contractor Is Also Required To Maintain On Site A Competent Site Safety And Health Officer (see 01 35 26 Safety Requirements When Any Worker(s) Or Subcontractor(s) Are Present. The Va Cor May, At His Or Her Discretion, May Allow The Competent Supervisory Person To Also Act At The Ssho, Based On Demonstrated Competency And Performance In The Two Roles. If Demonstrated Lack Of Competency Or Effectiveness In Either Role Is Observed, The Va Cor May Revoke The Privilege. Safety: Prior To Any Activity, Review The Following With All Project And Craft Team Leaders: 01 35 26 Safety Requirements. The Contractor Shall Provide A Proactive And Complaint Construction Safety And Accident Prevention Plan In Accordance With The Occupational Safety And Health Act, 01 35 26 Safety Requirements, And Site-specific Policies: All Persons Working On Any Electrical Systems Rated 50 Volts Or More Shall Have The Minimum Qualification As A State Licensed Master Electrician Or Registered Journeyman Electrician, And All Activities Shall Follow The Safe Work Practices In Compliance With Nfpa 70e Electrical Safety In The Workplace. 01 35 26 Safety Requirements Is Included In Its Entirety In This Contract. Each Contractor-employer Is Required To Be Solely Responsible For The Health And Safety Of Its Employees In Accordance With 29 Cfr 1910, 1926, & 1960 Of The Occupational Safety And Health Act Of 1970, As Amended. Because Each Contractor-employer Is Required To Be Solely Responsible For The Health And Safety Of Its Employees, Part Of A Compliant And Effective Safety Management Program Requires Each Employer To Plan And Implement Their Own Compliant Permit- Required Work Including Written Permits. Do Not Rely On, Or Request That Va Generate Required Permits Such As Hot Work Or Confined Space Documents. Prior To The Beginning Of Any Work, Fire Extinguisher(s) Complying With Nfpa 10 Shall Be Pedestal-mounted In The Work Area. Inspection Of The Work Area Includes Verification That Inspection Tags Are Current. Where Non-compliant, The Contractor May Be Required To Remove And Replace The Unit(s) Before Resuming Work Activity. All Work In Crawl Spaces Shall Be Planned And Carried Out As Osha Permit-required Confined Space. Immediately Stop Work And Notify The Cor If Asbestos Is Noticed Or Suspected In The Area Of Work. Exception: The Above Will Not Necessarily Apply To Areas Where The Documents Call For Abatement Activities. This Item Is Concerned With Unplanned Locations. Fire-seal All Penetrations Made Or Discovered Through Any Wall Or Floor Assembly With Ul Listed Fire-rated Products Or Systems. Infection Control: 01 35 33 Infection Control Requirements Is Included In Its Entirety In This Contract. Its Construct Is Enabling For Each Condition Experienced Through Each Phase Of The Work. The Following Are High-level Requirements Most Often Found Deficient During Inspections Yet Required. Prior To Any Activity, Review The Following With All Project Team Leaders: 01 35 33 Infection Control Requirements. Review And Comply With Containment Construction And Sequence Described In The Design And Specification Documents. Provide A Modular Dust-tight System Designed And Manufactured Specifically To Be Used As A Temporary Construction Isolation Barrier. Before The Start Of Work Provide Pressure Differential Monitoring System At The Entry Door To The Construction Area To Prove That The Construction Area Is Under Negative Pressure. Maintain Daily Logs Of Readings And Submit To The Cor Weekly. Remove At The Completion Of Construction. Walk-off Sticky Mats Are Required At All Times Inside And Outside All Entry / Exit Points To All Workspaces. Sticky Mats Must Be Changed At Least Once Per Shift, Or More As Required By The Construction Or Cor. Size Sticky Mats To Match The Width Of The Door Opening And Ensure That No Less Than 24 Depth Is Provided. Block Off All Hvac Return Ductwork And Louvers To Prevent Introduction Of Dust Into The Hvac System. 1) Where Existing Hvac Ducts Are Being Removed, Immediately, Permanently, And Compliantly Seal Off The Opening. Provide High-efficiency Particulate Air Filtration (hepa) Recirculating Air Equipment Inside The Workspace. Size The Air Filtration System Sufficiently Large Enough To Ensure That Negative Pressure Remains Effective When Doors Are Opened. When Working Above The Ceiling Outside Of The Work Area, Such As In A Corridor, Open Only One Ceiling Tile At A Time, And Provide Dust Containment Tent Or Portable Containment Cube, With Hepa Filtering Negative Air System To Seal The One Opening. Broom-sweep The Work Area At The End Of Each Day (or Shift During Days With Multiple Shifts). Provide Hepa Vacuum And Damp (not Wet) Mop Daily Where Broom Sweeping Creates Airborne Dust. Provide Fire-sealing Of All Existing Wall And Ceiling Openings In Area Of Work Needed To Allow The Hepa Filtration Equipment To Effectively Generate Negative Air Pressure Within The Work Area, With Respect To The Surrounding Area. Provide Hepa-filtered Vacuum Cleaning Of All Surfaces, And Damp Mop The Work Area Every Day. Do Not Allow Corrugated Carboard To Be Stored For Any Period Of Time Within The Hospital. Upon Arrival, Unpack, And Transfer All Products From Cardboard Containers To Sealed Plastic Containers, And Immediately Dispose Of The Cardboard Outside Of The Building. Part 6: Site-specific Requirements Project Number And The Contract Number In The Subject Line Of All Emails And Documents. Example: 556-23-101 Renovate B134-2c Clc , Or Simply 556-23-101 B134-2c And Then Specific Subject Such As Pay App, Rfi, Submittal, Meeting, Etc. Transmissions Deviating From This Focused And Simple Standard May Be Rejected, Or Simply Lost Because Recipients Could Not Readily-acquire Their Subject Or Importance Over The Plethora Of Ambiguous Emails Received Each Day. Comply With All Site-specific Requirements And Sops Including And Not Limited To: Key Policy, Badging Policy, Rules Of Behavior, And Smoking Policy. Normal Construction Work Hours Are 7:00 Am To 3:30 Pm Monday Through Friday. Normal Work Hours Can Be Modified Only By Written Approval Of The Cor, And At No Additional Cost To Va. No Work By The Contractor On Federal Holidays, And No Work On The Weekend When The Federal Holiday Is On The Respective Monday Or Friday. No Work In Stairs, Corridors, Lobbies, Or Other Interior / Exterior Public Areas Shall Be Performed During The Above-designated Work Hours. Any Work Including And Not Limited To Noise, Vibration, Dust, Odors, Core Drilling, Hammer- Drilling, Saw Cutting, Equipment Moving In Public Corridors, Soil Compaction Shall Be Performed During The Above-designated Work Hours Only. Crane Lifts, Or Any Work That Closes Drive Isles, Closes Building Entries, Or Closes Public Corridors Shall Be During Low Patient Times And Performed Between Saturday 6 Pm Through Midnight Concluding By 6 Pm On The Following Sunday. All Building Systems Shall Be Maintained In Full Operation At All Times: Request Utility System Shutdowns In Writing Not Less Than 21 Calendar Days In Advance And Scheduled With The Cor At Times Least Impacting Patient Care. Shutdown Work Shall Be During Low Patient Times And Performed Between Saturday 6 Pm Through Midnight Concluding By 6 Pm On The Following Sunday. Wherever Demolition Is Planned, Ceiling Tiles Are To Be Removed, Or The Sprinkler System Is To Be Disabled, Gc Shall First Provide Uniform Heat Detection Throughout The Work Area, Connected To The Existing Supervised Building Master Fire Alarm System, For The Duration Of The Work. Fire And Or Smoke Detection Devices Shall Be Provided Prior To Turnover And Acceptance. Deliveries, Parking, Elevators: Deliveries At The Dock: At Time Of Delivery: Provide Vehicle Information To The Va Police And Remove The Vehicle As Soon As Delivery Is Complete. Move Materials In Public Corridors During Low Patient Times Between 6 Pm Through 6 Am The Following Day. No Parking In The Va Garages. As Part Of The Mobilization Plan Submission, Indicate Where Workers Are To Park. Contractor Shall Use Freight Elevators. Do Not Move Materials And Employees In Passenger Elevators Without Written Approval Of The Cor, And Never Within Elevators Occupied By Staff Or Patients. The Mobilization Plan Submission Shall Indicate If And Where A Construction Dumpster Is Intended To Be Placed. The Contractor Shall Provide A Construction Dumpster With A Locked Safety Fence Surrounding It, At A Location Submitted To And Approved By The Cor. Pavement, Concrete Surfaces, And Landscaping Shall Be Protected From Damage Resulting From Delivery And Retrieval, Loading And Unloading, And Dumpster Weight. Construction Waste Diversion Reports Are Required For Every Dumpster Removed From Every Construction Site At Every Va Facility. Provide These Reports To Va Cor Immediately After The Waste Hauler Removes Each Dumpster To Comply With Va Gems Policy. No Trash, Used Packaging, Or Construction Spoils Shall Be Stored In The Work Area. Never Use Dumpsters Other Than Those Rented For This Work. Severe Penalties, Including Potential Criminal Charges May Be Levied For Use Of Government-rented Or Owned Containers, Or Those Of Other Contractors. Trash Removal From The Work Area Shall Be Within Gondolas Which Have Sealed Covers (completely Enclosed), And During Non-business Hours, Via The Freight Elevators. No On-site Office Or Storage Container Shall Be Allowed. Provide Just-in-time Delivery And Pickup. Coordinate With The Cor For Staging Within The Area Of Work. No Music Radios Within Work Areas. No Noise Generated Within The Work Area Can Be Allowed To Leave It. The Use Of Powder-actuated Fasteners Is Forbidden. Performing Demolition Using Motorized Equipment, Whether Tracked Or Wheeled, Pushed Or Driven, Is Forbidden. Two-way Communications Radios Are Allowed Where Transmit/receive Frequencies Will Not Disrupt Any Hospital System. Before Starting Work The Contractor Shall Give 21 Days Notice To The Cor So That Security Arrangements Can Be Provided For The Employees. This Notice Is Separate From Any Notices Required For Utility Shutdown Described Elsewhere In This Section. Va Reserves The Right To Close Or Shut Down The Project Site And Or Require Contractor Employees To Leave The Premises In The Event Of A Civil Emergency Or Operational Requirement. The Contractor May Return To The Site Only With The Written Approval Of The Cor. Compatible System Procurements Shall Include The Following: Locks And Keys: Temporary And Permanent Door Hardware Shall Be Compatible With Bestâ® 7-pin, G-keyway, Interchangeable Core. Prior To Commencement Of Work, The Contractor Shall Provide Va With Blank Cores; Quantity Matching The Number Of Openings Planned. Va Shall Then Provide Construction Coring, And A Key For Same To The General Contractor, Who Will Sign Acknowledgement And Receipt And Responsibility For The Key Until Returned To The Va Cor. Final Pinout And Keying Is Provided By Va. Exit Signs: All Exit Signs Shall Be City Of Chicago Approved Specification Red Letters On White Edge-lit Led Fixtures Continuously Illuminated 90 Mins. After Loss Of Power, Push-to- Test Switch And Led Pilot Light On The Housing, Available As Single Or Double-sided Models, And Meeting Ul924. Building Automation: Components, Programming And Start Up: Native Bacnet Communications Protocol For Building Automation And Control (bac) Connected To The Existing Johnson Controls Head End Equipment. 27 15 00 Communications Cabling (and Other Specifications Which Include Telecom Cabling): All New Telecom Cabling Shall Be Cat 6a Vs. 5e. Cat 6a Telecom Cable, Termination Punch-down T-568-(b.1, B.2, C.2, Etc.), Tested And Certified (submit Result To Cor), 6-port Modular Wall Jacks With Two Rj45 On Top And Bottom And Two Blanks In Middle. While Va Facilities Generally Do Not Include Plenum Return Spaces Above Ceilings, It Nonetheless Requires Plenum-rated Teledata Cabling Complying With Codes Pertaining To Plenum Environments. Sole Source Procurement, The Contractor Shall Provide Fully Functional Complete Systems, Including The Following Sole Source Procurements For The Following Special Systems: Fire Alarm: Components, Programming And Start Up Within The West Campus Is By Johnson Controls/simplex. Building Automation: Components, Programming And Start Up: Automated Logic Company Of Chicago. Proximity Card Reader And Door Lock Release Entry System: Components, Programming And Start Up: Enorman Patient Lift Systems And Components: Guldmann

Department Of Energy Tender

Machinery and Tools
Corrigendum : Closing Date Modified
United States
Closing Soon17 Mar 2025
Tender AmountRefer Documents 
Description: ***** This Is A Request For Interest Only! This Request Does Not Constitute A Request For Proposal, Request For Quote, Or Invitation For Bid. The Intent Of This Request Is To Identify Potential Offerors For Market Research Purposes Only. ***** request For Information (rfi) savannah River Nuclear Solutions, Llc (srns), Which Manages And Operates Portions Of The Savannah River Site (srs) Under A Department Of Energy (doe) Prime Contract, Seeks Information From Parties Capable Of Providing An Electric Mixer To Be Used Within A Glovebox In The K-area Complex (kac). Experience From Parties Strongly Rooted In Fabrication And Design Suitable For Nuclear Application Is Preferred. This Rfi Is Issued To Assist With Finding Potential Suppliers Interested In This Solicitation. ­­­­ the Srs Complex Is Located Approximately 15 Miles South Of Aiken, South Carolina And Is 310 Contiguous Square Miles. scope Summary: Provide Labor, Materials, Services And Expertise For Design, Fabrication, Inspection, Testing, Documentation, Delivery, Installation Support, And Technical Services For Creation Of An Electric Mixer To Incorporate Inside Of The Kac Glovebox. The Kac Electric Mixer Is Used To Homogenously Mix Free Flowing Powder, Of Differing Densities And Particle Sizes, Containing Nuclear Material With An Adulterant Residing In Blend Cans. requirements: the Mixer Must Fit Inside Of The Glovebox With Dimensions Capable Of Fitting Within A 12” Bag-out Port. The Mixer Can Be Introduced Modularly, And Shall Be Easily Able To Assemble And Disassemble Within Glovebox Confinements. If Introduced Modularly, Each Mixer Component Shall Not Exceed A Footprint Of 11.75” Width X 11.75” Depth. the Speed Of Rotation Shall Range Between 50 & 70rpm, With Requirements That The Mixer Shall Complete 90 – 120 Turns Per Cycle. The Mixer Shall Contain Sufficient Locking Measures To Securely Fasten The Blend Can To The Mixer Without A Loss Of Containment. The Locking Measure Shall Be Designed In A Manner That Is Easily Accessible For Operators With Limited Hand Mobility. The Mixer Shall Sufficiently Blend The Adulterant With The Feed To Ensure A Homogenous Blend. the Mixer Shall Be Operated Within A Confined Glovebox With Other Equipment And Operations Within. Mixer Vibrations, Disturbances, And Noise Shall Be Dampened And Minimized During Mixing Operations. Vibrations From Mixing Operations Shall Not Cause The Mixer To Move Or “walk” While Operating.. the Mixer Shall Retain Structural Integrity When Mixing The Blend-can With The Determined Weight Range Of The Blend Cans Varying Between 4 – 8lbs. The Mixer Shall Allow Different Variations Of Blend Cans To Be Installed For Mixing. The Dimensions Of These Variations Are As Follows, Blend Cans With Dimensions Of 4.00” Diameter And 6.23” Tall Can With An Attached Screw Top Lid Of 3.00” Diameter And 0.485” Height And Another Style Of Blend Can With Dimensions Of 4.00” Diameter And 6.23” Tall Can With An Attached Screw Top Lid Of 3.00” Diameter And 0.55” Height. the Design Shall Minimize Sharp Edges And Pinch Points Located On The Mixer. The Mixer Components Shall Minimize The Use Of Organic Materials Such As Wood, And Plastics. The Weight Of The Mixer Shall Not Exceed 50 Lbs. The Mixer Shall Be Delivered With Machine Guarding In Accordance With 29 Cfr Subpart O, 1910.212. the Mixer Shall Be Installed And Operated Inside Of The Glovebox. The Temperature And Humidity Are Approximately 68-74 °f And 30-60%. The Interior Of The Glovebox Is Potentially Dusty, The Service Environment Will Include Radioactive Contamination. Given The Environment, The Vendor Shall Ensure That The Mixer Design Does Not Allow For The Mixer To Be Inoperable Due To An Accumulation Of Dust. the Mixer Will Be Installed Inside Of The Glovebox With Electrical Controls Mounted Outside Of The Glovebox, Receiving Power From Receptacles Energized By A Key Switch Also Located Outside Of The Glovebox. The Mixer Shall Provide A Method Of Obtaining Visible Diagnostic Information Displaying Errors, Faults, Etc. The Mixer Controls Shall Provide An Option To Adjust The Mixer Parameters Such As Rpm. The Mixer Shall Possess A Way Of Stopping Operations Of The Mixer Should An Accident Occur Via An Emergency Stop Button. the Provided Equipment Shall Comply With Nfpa 70, 2017. electric Motors Shall Comply With Nema Mg-1, 2016. electrical Enclosures Shall Be Nema 12, 4 Or 4x In Accordance With Nema 250, 2018. conductors And Cables Shall Comply With Insulated Cable Engineers Association And National Electrical Manufactures Association Standards. all Commercial Electrical Materials And Equipment Shall Be Tested And Listed By Underwriter’s Laboratories (ul) Or Approved By Factory Mutual Engineering And Research (fm) Or Other Osha Nationally Recognized Testing Laboratory (nrtl). the Mixer Shall Not Have Wi-fi, Bluetooth, Or Imaging Capabilities. considerations: supplier Must Consider Operator Mobility Regarding The Installation And Operability Of The Final Product. supplier Must Consider That The Design Of The Mixer Is Easily Accessible For Performing Maintenance On All Components Of The Mixer. supplier Must Consider The Tools Utilized For Performing Maintenance Activities And Avoid Using Pointed Tools To Mitigate Potential Puncture Of Glovebox Gloves. supplier Must Consider And Implement An Ergonomic Design Into Mixer Final Product. a Supplier's Response To The Rfi Does Not Guarantee They Will Be Selected To Participate In The Rfp. suppliers Responding To This Rfi Shall Include Evidence Of The Following: past Performance / Personnel Qualifications Relative To Subject Scope quality Assurance Manual (uncontrolled Copy) qualification For Codes And Standards manufacture Specification Sheet standard Lead Time For Delivery budgetary Estimated Cost visual / Audial Examples Of Similar Work Performed, If Available e-mail Response Addressing Items 1 Through 7 Above In Attachments (pdf Format), Shall Be Submitted By 5:00 P.m. Est. On 3/17/25 To Barbara Mccarty At Barbara.mccarty@srs.gov.

DEPT OF THE ARMY USA Tender

Civil And Construction...+1Civil Works Others
Corrigendum : Closing Date Modified
United States
Closing Date25 Mar 2025
Tender AmountRefer Documents 
Details: Sources Sought Notice this Notice Is Being Issued In Accordance With Federal Acquisition Regulation (far) Part 10, Market Research. The Purpose Of This Synopsis Is To Gain Knowledge Of Potential Sources For This Project Including Interested Small Business Concerns. Its Sole Purpose Is To Provide Information For Planning And Market Research Purposes Only And Shall Not Be Construed As Either A Solicitation Or Obligation On The Part Of The Government. The Government Welcomes Responses From All Interested Parties; However, No Decision Or Award Of Contract Will Be Made Based On Responses From Industry. The Government Will Not Pay For The Preparation Of, Nor The Subsequent Use Of, Information Submitted In Response To This Solicitation. Respondents Will Not Be Notified Of The Outcome Of The Government’s Review Of The Information Received. Additionally, The Government Does Not Intend To Hold Discussions Concerning This Notice With Any Interested Parties But Reserves The Right To Contact Vendors If Additional Information Is Required For Clarifications As It Pertains To The Solicitation. the Contractor Shall Provide All Plant, Labor, New And Current Material, Transportation, Tools, Equipment, Appliances, Supplies, Services, Permits, Insurance, And Supervision Necessary To Repair Building 23 Cyber Operations At Sepulveda Air National Guard Station, California (project Number Vhrj192233). All Work Shall Be Performed In Accordance With The Project’s Plans And Specifications. the Repair Work Encompasses About 6,027 Sf Of Secure Area Within Building 23 Located At Sepulveda Air National Guard Station, Ca. The Work Involves Demolition And Reconfiguration Of The Interior Partition Walls And Finishes, Openings, And Building Systems To Accommodate A New Secure Area. Renovation Work Includes New Finishes, Openings, Partitions, Raised Flooring, And Upgrades To Mechanical, Electrical, Telecom, And Life Systems To Support The New Secure Area. A Temporary Facility Shall Be Provided During The Repair Work At A Location That Already Has Utilities. in Accordance With Defense Far Supplement 236.204, Disclosure Of The Magnitude Of Construction Projects, The Anticipated Magnitude Of Construction Is Between $5,000,000 And $10,000,000. the Naics Code For This Requirement Is 236220, Commercial And Institutional Building Construction. The Small Business Administration Size Standard For Small Businesses In This Industry Is $45,000,000. instructions To Vendors all Interested Concerns Will Submit A Written Notice, Not To Exceed Five (5) Pages, Stating The Concern’s Positive Intention To Submit A Proposal As A Prime Contractor No Later Than The Deadline Posted With This Notice. Responses To This Solicitation Should Include The Following Information: a Positive Statement Of Intent To Submit A Proposal As A Prime Contractor, a Listing Of Projects Completed During The Past Five (5) Years For Both Government And Private Industry. The List Should Provide The Type Of Project, Dollar Value, Contract Number, Location, And Point Of Contact. Also, Please Indicate Whether The Firm Was A Prime Or Subcontractor—if The Firm Was A Subcontractor, Please Provide A Point Of Contact With The Prime Contractor, a Brief Outline Of Resources, Subcontractors, And Key Personnel That Would Be Used To Accomplish The Contract, And demonstration Of The Firm’s Socioeconomic Status (i.e., Sb, 8(a), Hubzone, Edwosb, Wosb, Sdvosb, Etc.), And Size. if Adequate Small Business Firms Are Not Available For Adequate Competition For This Project, It May Be Advertised As An Unrestricted Solicitation. submit Responses Directly To 195wg.fal.msc.contracting.org@us.af.mil; Telephone Calls And Facsimile Responses Will Not Be Honored. Please Reference The Notice Id And Project Title In The Subject Of Your Message. Please Limit Your Responses To Standard Documents (i.e., Microsoft Office, Adobe Pdf, Etc.). Do Not Send Compressed (i.e., .zip Or .exe Extension) Or Other File Types As They Will Be Stripped From Your Message.

PUBLIC BUILDINGS SERVICE USA Tender

Real Estate Service
Corrigendum : Closing Date Modified
United States
Closing Soon15 Mar 2025
Tender AmountRefer Documents 
Details: General Services Administration (gsa) Seeks To Lease The Following Space: state: Ne city: Omaha delineated Area: north: Fort Street To Military Avenue To 72nd Street To Crown Point Avenue To Hartman Avenue To N. 60th Street To Fort Street To Sorenson Pkwy To North Freeway 75 To Ames Avenue To N. 16th Street To Locust Street To N. 23rd Street E. east: N. 23rd Street E. To The Missouri River To E. Mission Avenue. south: North Mission Avenue To Lincoln Road To Galvin Road S To Harlan Drive Turning Into Highway 370 To S 144th Street/highway 50 To S. 144th Street To N. 144th Street To Fort Street. west: S. 144th Street/hwy. 50 To S. 144th Street To N. 144th. minimum Sq. Ft. (aboa): 17,411 maximum Sq. Ft. (aboa): 18,280 space Type: Office parking Spaces (total): 3 parking Spaces (surface): 3 parking Spaces (reserved): 3 full Term: 15 Years firm Term: 10 Years option Term: 1-5 Year Option additional Requirements: cannot Be Located Within 300 Walkable Feet Of Schools, Churches, Homeless Shelters, Drug Treatment Facilities And Dispensaries. at Least One Dual Port Ev Charging Station For The Exclusive Use Of The Government As Part Of The Three Reserved Onsite Parking Spaces. local Code For Parking Still Apply. parking Spaces Commercially Available Within 1 Block, Not To Exceed ¼ Mile. up To Two Consecutive Floors Are Acceptable, A Minimum Of 8,404 Sf Must Be One Of Those Floors For Public Use. offered Space Shall Provide For A Configuration That Will Allow For An Efficient Layout Of The Requires Adjacencies For The Agency Needs Of Space For Public Access, Offices, Workstations, And Special Use Spaces (file Rooms, Assembly Areas, Copy Rooms, Storage Rooms, Etc.). space Which Shall Be Located In A Prime Commercial/business Office District With Attractive, Prestigious, Professional Surroundings With A Prevalence Of Modern Design And/or Tasteful Rehabilitation In Modern Use. Offered Space Must Be Located In A Professional Office Setting And Not Within Strip Malls. the Successful Lessor, At The Lessor’s Cost And Expense, Shall Obtain Leed Certification For Commercial Interiors (leed-ci) For Existing Buildings Or Green Globes Si. offered Space Must Be In A Building That Has Earned The Energy Star Label In The Most Recent Year Or Will Have Obtained It Prior To Lease Award Unless The Offered Space Meets A Statutory Exception. a Loading Area With Double Doors Or An Overhead Door Must Be Available In The Building In Which The Space Is Offered For The Handling Of Pallet Sized Loads. The Loading Area Is Not Required To Be Above-grade. offered Space Must Have The Ability To Separate The Public Entrance From An Employee Entrance. one Or More Public Bus Lines Usable By Tenant Occupants And Their Customers Shall Be Located Within The Immediate Vicinity Of The Building, But Generally Not Exceeding A Safe Walkable 1/3 Mile, As Determined By The Lco. Bus Stops To Occur On A Regular, Frequent Basis (schedule Required To Be Provided. It Must Show Location And Frequency Of Bus Stops). the Proposed Tenant Will Have A High Volume Of Visitors (up To Approximately 250 Per Day). subleases Will Not Be Considered. a Detention Facility Cannot Be Within 1,000 Feet Of The Offered Space. the Space Offered Cannot Be Co-located With Law-enforcement Agencies In The Same Building. offered Space Must Meet Government Requirements For Fire Safety, Accessibility, Seismic, And Sustainability Standards Per The Terms Of The Lease. A Fully Serviced Lease Is Required. Offered Space Shall Not Be In The 1-percent-annual Chance Floodplain (formerly Referred To As “100-year” Floodplain). entities Are Advised To Familiarize Themselves With The Telecommunications Prohibitions Outlined Under Section 889 Of The Fy19 National Defense Authorization Act (ndaa), As Implemented By The Federal Acquisition Regulation (far). For More Information, Visit: Https://acquisition.gov/far-case-2019-009/889_part_b. offers Due: March 14, 2025 occupancy (estimated): June 1, 2026 send Offers To: offers Must Be Submitted Electronically Through The Requirement Specific Acquisition Platform (rsap), Located At Https://lop.gsa.gov/rsap/. interested Parties Must Go To The Rsap Website, Select The “registration” Link And Follow The Instructions To Register. Instructional Guides And Video Tutorials Are Offered On The Rsap Homepage And In The “help” Tab On The Rsap Website. solicitation (rlp) Number:3ne0160 government Contact Information (not For Offer Submission) frank Whiting - Lease Contracting Officer phone: (816) 446-4909 email: Frank.whiting@gsa.gov nicholas Zabelin, Broker Contractor - Carpenter/robbins Commercial Real Estate, Inc. phone: (925) 790-2124 email: Nicholas.zabelin@gsa.gov note: Entities Not Currently Registered In The System For Award Management (sam.gov) Are Advised To Start The Registration Process As Soon As Possible. an Offeror Checklist Has Been Included With The Rlp To Underscore The Documents That May Be Required By This Rlp. Detailed Requirements Are Contained In The Rlp. In The Event Of An Inconsistency Between This Checklist And The Rlp, The Rlp Is The Authoritative Source.

State Water Transport Department - SWTD Tender

Works
Furnitures and Fixtures
Eprocure
Corrigendum : Closing Date Modified
India
Closing Soon19 Mar 2025
Tender AmountINR 570 K (USD 6.5 K)
Description: Interior Work Of Boat No.s25

BARANGAY POBLACION, LIBACAO, AKLAN Tender

Civil And Construction...+2Civil Works Others, Excavation
Corrigendum : Tender Amount Updated
Philippines
Closing Date21 Mar 2025
Tender AmountPHP 207.3 K (USD 3.5 K)
Details: Description Republic Of The Philippines Province Of Aklan Municipality Of Libacao Barangay Poblacion * * * The Barangay Council Of Poblacion, Libacao, Aklan Through Its Bids And Awards Committee (bac), Invites Contractors To Submit Bids For The Following Contract: 1. Contract I.d.: 05poblacion2025 Contract Name: Concreting Of Barangay Road Portion Contract Location: Interior Pagharion Street (datag Village- Purok 6), Brgy. Poblacion, Libacao, Aklan Brief Description: I. Excavation Ii. Ground Surface Preparation Iii.concreting Approved Budget For The Contract (abc): ₱ 207, 394.00 Source Of Funds: Barangay Fund Contract Duration: 90 C.d. The Bac Is Conducting The Public Bidding For This Contract In Accordance With Ra 9184 And Its Implementing Rules And Regulations (irr). To Be Eligible To Bid For This Contract, A Contractor Must Meet The Following Major Requirements: (a)filipino Citizen Or 75% Filipino-owned Partnership/corporation With Pcab License For Size Range _____, (b) Completion Of A Similar Contract Costing At Least 50% Of The Abc, And (c) Net Financial Contracting Capacity (nfcc) At Least Equal To The Abc. The Bac Will Use Non-discretionary “pass/fail” Criteria In The Eligibility Check, Preliminary Examination Of Bids, Evaluation Of Bids, Post Qualification And Award. The Schedule Of Key Procurement Activities For This Contract Is Shown Below: Activity Time Place 1.issuance Of Bidding Documents March 05, 2025 – March 21, 2025 *hard Copies At Brgy. Office Brgy. Poblacion, Libacao, Aklan 2.pre-bid Conference - - 3.received Of Bids By The Bac March 21, 2025 10:00am Brgy. Office, Brgy. Poblacion, Libacao, Aklan 4.opening Of Bids March 21, 2025 10:00am Brgy. Office, Brgy. Poblacion, Libacao,aklan Bidders Shall Pay The Bac A Non-refundable Fee Of Php 500.00 For The Bidding Documents, Upon Securing Hard Copies Of The Documents. Bidders That Downloaded The Documents From The Philgeps Website Shall Pay The Fee Upon Submission Of Their Bids. Bidder Shall Show Proof Of Evidence That They Are The Authorized Representative To Submit/drop Bid Of The Contractor They Represent. The Barangay Council Of Poblacion Reserves The Right To Accept Or Reject Any Bid And To Annul The Bidding Process Any Time Before The Contract Award, Without Incurring Any Liability To The Affected Bidders, In Accordance With The Provisions Of Section 41 Of Ra 9184 And Its Irr. Any Requests For Additional Information Concerning This Bidding Shall Be Directed To The Following: Bac Chairman: Susana R. Asiong Address: Brgy. Poblacion, Libacao, Aklan Contact No. 09567132443 Bac Secretariat: Stella N. Rollo Address: Brgy. Poblacion, Libacao Aklan Contact No. 09462339453 Approved By: Susana R. Asiong Bac Chairman Date Of Publication: March 05, 2025

Department Of The Interior And Local Government - DILG Tender

Security and Emergency Services
Corrigendum : Tender Amount Updated
Philippines
Closing Date26 Mar 2025
Tender AmountPHP 26.7 Million (USD 461.1 K)
Purchaser Name: Department Of The Interior And Local Government | Description: Procurement Of Security Services , Security Services ,department Of The Interior And Local Government - Main

DEPT OF THE NAVY USA Tender

Others
Corrigendum : Closing Date Modified
United States
Closing Date28 Mar 2025
Tender AmountRefer Documents 
Details: Contact Information|4|n792.06|s8r|215-697-0275|patrick.j.horan23.civ@us.navy.mil| item Unique Identification And Valuation (jan 2023)|19|||||||||||||||||||| higher-level Contract Quality Requirement|8|x|||||||| inspection And Acceptance Of Supplies|26|x||||||||||||x|||||||||||||| wide Area Workflow Payment Instructions (jan 2023)|16|invoice And Receiving Report Combo Type ||tbd|n00383|tbd|tbd|see Schedule|tbd||||||||| navy Use Of Abilityone Support Contractor - Release Of Offeror Information (3-18))|1|| equal Opportunity (sep 2016)|2||| warranty Of Supplies Of A Noncomplex Nature (jun 2003)|6|12 Months|60 Days After Discovery Of Defect||||| equal Opportuity For Workers With Disabilities (jun 2020)|2||| buy American-free Trade Agreements-balance Of Payments Program-basic (feb 2024)|11|||||||||||| alternate A, Annual Representations And Certifications (nov 2023)|13|||||||||||||| buy American-free Trade Agreements-balance Of Payments Program Certificate-basic (feb 2024))|5|||||| buy American--balance Of Payments Program (feb 2024)|1|| royalty Information (apr 1984)|1|| annual Representations And Certifications (may 2024)|12|332439|600||||||||||| notice Of Priority Rating For National Defense, Emergency Preparedness, Andenergy Program Use (apr 2008))|2||x| navsup Is Looking For Firm Fixed Price Proposals. Estimated Pricing Can Be Submitted At Worse Case Scenario. Only Offers Submitted In Response To This Amendment Will Be Considered For Award. Solicitation Close Date Extended To March 28, 2025. interested Vendors Should Submit A Tiered Pricing Repair Proposal. please Submit An Evaluation Price As Well As Pricing For Minor, Moderate, And Major Repair Tiers. \ navsup Wss Has Been Granted A Class Deviation (cl-00-203) That Permits Us To Use The Award Forms Currently Available In Our Automated Procurement System Instead Of The Sf 1449 When Conducting Procurements For Commercial Items. this Procurement Is Being Conducted In Accordance With Far Part 12, Acquisition Of Commercial Products. information Appearing On The Face Of The Dd Form 1155 Or Sf 26 That Conflicts With Clauses Or Provisions Contained Elsewhere In This Solicitation Shall Be Disregarded. addendum To Far 52.212-4 Contract Terms And Conditions Commercial Products Under Paragraph(a) "inspection And Acceptance" Add The Following: 1. Far Clause 52.246-2 Inspection Of Supplies-fixed Price Applies As Amended Herein. All Product Audits Performed At The Discretion Of The Dcma Qar Shall Be Conducted By Witnessing Contractor Inspections Or Tests On A Non-interference Basis. erference Basis. 2. The Contractor Shall Maintain A Quality System That Addresses The Elements Of Iso9001-2000/as9100b, Quality System Model For Quality Assurance In Design/development, Production, Installation And Servicing, And A Calibration System That Addresses The Elements Of Iso-10012-1, Ansi/ncsl Z540 Or An Equivalent Program Approved By The Navy. 3. The Government Reserves The Right To Assess The Contractor's Compliance To Its Documented Quality System Throughout The Performance Of This Contract. The Quality System Shall Be Made Available To The Government For Their Review And Use. The Acceptance Of non-conforming Supplies Is A Prerogative Of And Shall Be As Prescribed By The Government. The Government Reserves The Right To Disapprove The Quality System Or Portions There Of When It Fails To Meet Its Intended Objectives. eserves 4. The Contractor Shall Not Make Any Configuration Changes, Engineering Changes Or Part Number Changes To The Contract/purchase Order Items, Including, But Not Limited To, The Item's Hardware, Software Or Firmware, Unless Approved By The Procurement contracting Officer (pco). In Addition, Approval By The Appropriate Technical Authority May Also Be Required. Guidance On How To Submit A Proposed Engineering Or Part Number Change May Be Obtained From The Pco. 5. The Contractor Shall Not Manufacture Any Item For Acceptance By The Government That Incorporates A Known Departure From Technical Or Contractual Requirements Unless A Request For A Deviation Has Been Approved. Authorized Deviations Are A Temporary Departure from The Requirements Only And Do Not Authorize A Change To The Item's Configuration Baseline. Any Deviation, Major Or Minor, Must Be Approved By The Pco Prior To Acceptance. the Government Will Award A Contract Resulting From This Solicitation To The Responsible Offeror Whose Offer Conforming To The Solicitation Will Be Most Advantageous To The Government, Price And Other Factors Considered. In Addition To Price, The Following non-price Evaluation Factor Shall Be Used To Evaluate Offers And Are Listed In Descending Order Of Importance. relevant Past Performance technical Capability the Non-price Evaluation Factors, When Combined, Are Significantly More Important Than Price. There Are No Subfactors. the Government Reserves The Right To Obtain Information For Use In The Evaluation Of Past Performance From Any And All Sources Including Sources Outside Of The Government. Offerors Lacking Relevant Past Performance History Will Not Be Evaluated Favorably Or unfavorably On Past Performance. The Government Will Consider The Quality Of An Offeror's Relevant Past Performance. This Consideration Is Separate And Distinct From The Contracting Officer's Responsibility Determination. The Assessment Of The Offeror's R relevant Past Performance Will Be Used As A Means Of Evaluating The Relative Risk Of The Offeror And Other Competitors In Successfully Meet The Requirements Of The Rfp. In Determining The Rating For The Past Performance Evaluation Factor, The Government Will Give Greater Consideration To The Contracts Which The Government Feels Are Most Relevant To The Rfp. the Government Reserves The Right To Award The Contract To Other Than The Lowest Priced Offeror. page Limitation-excluding The Cover Page, Table Of Contents, Past Performance Project Forms The Technical Capability Proposal Is Limited To Fifteen (25) Pages In At Least 11pt. Font And 1" Margins. Pages In Excess Of This Limitation Will Not Be Evaluated. The pages Excluded From Evaluation Will Be At The Discretion Of The Agency. contractors Are Informed That It Is The Government's Desire To Make Award On Initial Proposals When Deemed Possible By The Contracting Officer, However The Government Reserves The Right To Communicate And/or Negotiate With Offerors If Later Determined Necessary. none Price Proposal (all Non-price Factors) -the Contractor Is Required To Submit The Following Non-price Information: 1. Relevant Past Performance: the Contractor Is Provided An Opportunity To Demonstrate Relevant Past Performance On Contracts Currently Being Performed Or Performed Within The Past Three (3) Years. The Government Will Determine Relevance By Analyzing The Scope And Magnitude Of The Reference contracts And Comparing Them To The Instant Requirement. The Government Reserves The Right To Evaluate Submitted Projects Individually Or In The Aggregate In Order To Determine Relevance And Will Do So Consistently Across All Evaluated Offers. The Government will Consider The Quality Of The Contractor's Relevant Past Performance. reference Contracts: A. The Contractor May Submit Up To A Maximum Of Three (3) Contracts For Evaluation. The Government Reserves The Right To Obtain Information From Sources Other Than Those Identified By The Contractor. 2. Technical Capability the Government Desires That Offerors Demonstrate Technical Capability To Satisfy The Government's Requirements. The Offeror's Response Will Be Evaluated To Determine Whether Its Response Poses Risk To Performance Or Whether It Will Result In Better Value To The government. In Response To This Evaluation Factor, Offerors Shall Address Its Manufacturing Equipment; Inspection Method Sheets; Incoming Inspection Sheets; Process Sheets; Quality System Compliance; Welding Certification. in Responding To The Above Areas Of The Technical Capability Factor, It Is Incumbent Upon The Offeror Provide A Level Of Detail The Demonstrates To The Government's Satisfaction That The Offeror Has The Technical Capability To Perform The Requirement. If The proposal Lacks Sufficient Detail, It May Result In The Government Assessing Risk In The Proposal. While There Is No Prescribed Method For Demonstrating Technical Capability, The Below Are Items Of Interest To The Government That The Contractor May, At Its discretion, Address To Assist The Government In Gaining An Understanding Of The Offerors Technical Capability. Offerors Are Cautioned That While These Areas Of Interest Are Not Mandatory Elements That Are Required To Be Addressed, Failure To Address Them Or comparable Indicia Of Technical Capability, May Limit The Government's Understanding Of Technical Risk And Result In The Assignment Of Commensurate Risk. Offerors Are Also Notified That Some Of These Indicia Of Capability Are Overlapping, I.e., Two Or More May evidence The Same Facet Of Capability. certification Of Possession Or Access To The Following Equipment:for Aluminum And Steel Welded Containers, & Bladebox/riveted Construction 1.brake Press 2.extrusion Dies 3.cnc Machining Center(s) Capable Of Lathe And/or Milling Operations copies Of Inspection Method Sheets Used In-process And/or At Final Inspection copies Of Incoming Inspection Documents That Show Material Certificates Of Conformance, And If Applicable, Dimensional Conformance process/operation Sheets To Show Ability To Conform To Drawing Requirements In The Following Areas: Weld Preparation; Welding Procedure Specifications Production Lot Testing proof Of Compliance To Iso9001, And/or, As9100. applicable Up-to-date Welder Certifications Showing Highest-level Certification Obtained Aws D1.1 For Steel, Aws D1.2 Or Mil-w-22248,class 4 For Aluminum, Aws D1.3 For Sheet Steel And Aws D1.6 For Stainless Steel. if The Offeror Address Any Or All Of The Above, Or Provides Comparable Indicia Of Capability, It Is Encouraged To Provide Supporting Evidence And Detail, Such As But Not Limited To Receipts, Certifications, Drawings, Test Results/ Logs, Maintenance Records, calibration Records, Inspection Reports, Audits, Etc. The Weigh Accorded To Supporting Evidence Will Be At The Discretion Of The Government. the Technical Capability Proposals Will Be Evaluated To Determine The Risk Of Unsuccessful Performance As Well As Relative Risk Compared To Other Offerors. repair Turnaround Time (rtat) Definition: The Contractual Delivery Requirement Is Measured From Asset Return To The Date Of Asset Acceptance Under The Terms Of The Contract. For Purposes Of This Section, Return Is Defined As Physical Receipt Of The F-condition asset At The Contractor's Facility As Reflected In The Action Date Entry In The Commercial Asset Visibility (cav) System. In Accordance With The Cav Statement Of Work, The Contractor Is Required To Accurately Report All Transactions By The End Of The Fifth regular Business Day After Receipt And The Action Date Entered In Cav Must Be Dated To Reflect The Actual Date Of Physical Receipt. the Contractor Must Obtain Final Inspection And Acceptance By The Government For All Assets Within The Rtats Established In The Subsequent Contract. required Rtat: ## 103 Days After Receipt Of Asset throughput Constraint: Contractor Must Provide A Throughput Constraint For Each Nsn(s). Total Assets To Be Repaired Monthly After Initial Delivery Commences X/month (contractor Fill In #). A Throughput Of ##____ Per Month Reflects No Throughput Constraint. Induction Expiration Date: 365 Days After Contract Award Date. Any Asset Received After This Date In Days Is Not Authorized For Repair Without Bi-lateral Agreement Between The Contractor And Navsup Wss contracting Officer. reconciliation:a Reconciliation Modification Will Be Issued After Final Inspection And Acceptance Of All Assets Inducted Under The Subsequent Contract. The Parties Have Agreed To A Price (shown On The Schedule Page) For Each Unit At The Negotiated Rtat. Such prices Are Based On The Contractor Meeting The Rtat Requirements Described Within The Schedule Page. If The Contractor Does Not Meet The Applicable Rtat Requirement, Consideration Will Be Assessed And Subject To Negotiation. all Contractual Documents (i.e. Contracts, Purchase Orders, Task Ordersdelivery Orders And Modifications) Related To The Instant Procurement Are Considered To Be "issued" By The Government When Copies Are Either Deposited In The Mail, Transmitted By Facsimile, Or sent By Other Electronic Commerce Methods, Such As Email. The Government's Acceptance Of The Contractor's Proposal Constitutes Bilateral Agreement To "issue" Contractual Documents As Detailed Herein. early And Incremental Deliveries Accepted And Preferred. \ 1. Scope 1.1 Pre-award / Post Award Requirements: due To The Critical Use Of This Item And Its Quality History, A Pre-award Survey And Post-award Conference May Be Required For All New Manufacturers. For All Previous Sources, A Post-award Conference May Be Recommended. 1.2 Container Shell Material Is ;aluminum; . 1.3 When Discrepancies Exist Between These Requirements And Those On Current manufacturer's Drawings,contact Code ;buyer On Page 1 Of The Contract; Or Code N241.10 1.4 Articles To Be Furnished Hereunder Shall Be Manufactured, Tested And Inspected In Accordance With � See Schdule/line Item�,and All Details And Specifications Referenced Therein. 1.5 Articles To Be Furnished Hereunder Shall Be Repaired, Tested And Inspected In Accordance With The Terms And Conditions Specified In The Requirements Section Of This Document. 1.5.1 Any Item Contracted For Repair Shall Have A Statement Of Work To Ensure Compliance With All Repair Procedures And Requirements. repair Of: shipping And Storag ;6kh 8145 013574414; Nsn , ;583e001; Part Number, Shall Be Performed Iaw: Shipping And Storag ;ag-830ac-meb-000 Work Package 025 00; Publication (s). 1.5.2 There Will Be No Repair Deviation From The Approved Written Procedures Without Review And Acceptance By The Basic Design Engineer. All Requests For Waiver/deviation Shall Be Via Form 1694 Routed Throught The Local Dcma/aco Office For Review And recommendations Via Form 1998. 2. Applicable Documents - Not Applicable 3. Requirements 3.1 One Third (1/3) Unit Of Desiccant (mil-d-3464, Type Ii Nondusting) Per Cubic Foot Of Container Interior Volume Shall Be Placed In Desiccant Holder Of Each Container At Time Of Shipment. 3.2 Reference To Cadmium Plating Shall Be Deleted And The Following Substituted: "finish Shall Be Electrodeposited Alkaline Zinc-nickel Alloy In Accordance With Astm B 841 Class 1, Type B, Grade 3." all Containers Must Be Affixed With A Nameplate That Includes A unique Identification (uid) Marking As Referenced In The Drawing Package drawing ;(80132) 15930; And Iaw Mil-std-130 Latest Revision. The Contractor shall Contact Navicp Code ;contact Buyer On Page 1 Of The Contract; Or Code 0771.10 For The Alphanumeric sequential Serial Number Group That Makes Up Part Of The Uid. the Uidwill Be Included On The Nameplate In Data Matrix Format. contact Code ;buyer On Page 1 Of The Contract; Or Code N241.10 To Arrange For First Article Test Location when A First Article Is Required, The Contractor Shall Submit A Paper Copy Of The Drawings (size 11" X 17"), Contracts And Approved Ecp's Eco's, Deviations Waivers, And Modifications In The Records Recepticle Or Inside The Container Submitted For The First article. 3.3 Welding And Welder Qualifications Shall Be In Accordance With Aws D1.1 for Steel, Aws D1.2 Or Mil-w-22248,class 4 For Aluminum, Aws D1.3 for Sheet Steel And Aws D1.6 For Stainless Steel. Proper Controls Shall Be Used To Prevent Melt Through Or Burn Through. For Aluminum, Filler For Welding 6061 Alloy Shall Be 4043: Filler For Welding 5000 Series Alloys to Themselves Or To 6061 Shall Be 5356 Or 5556. In Addition,welding And weld Inspection Shall Include: (1) Visual Inspection Shall Include 5x (5power) Magnification When A Suspect condition Is To Be Examined Beyond The Capability Of Normal Vision. (2) Critical And Major Welds May Be Subjected To Further Non Destructive testing (such As Dye Penetrant Inspection)as Prescribed By The Buying Activity. (3) Proper Documentation Shall Be Available For Review By Government Personnel. 3.4 Work Instructions. Work Instructions Shall Be Posted At Theoperator's Work Station Giving Procedures To Control The Welding Process, I.e., Filler Material, Weld Size, Electrical And Gas Characteristics, Including Flow Rate. 3.5 Materials And Materials Control. The Quality Program Shall Assure That The Materials Used In Fabrication Or Processing, I.e., Base Metals And Weld Filler Material, Be Inspected And Conform To The Applicable Physical, Chemical And Other Technical requirements (supplier's Certification Is Sufficient). 3.6 Controls. Weld Filler Materials Shall Be Clearly Identified And Segregated From Each Other Both When In Storage And At The Work Station. Work Station Environment Shall Be Controlled To Prevent Conditions Adverse To Proper Gas Shielding. 3.7 Cleaning. Parts To Be Welded Shall Be Cleaned To Remove Surface Soils Such As Oils, Waxes, Grease, Inks, Etc. Except That Uninhibited Alkaline Solutions Such As Sodium Hydroxide Shall Not Be Used. 3.8 Deoxidizing. The Cleaned Parts Shall Be Chemically Deoxidized No More Than 10 Days Prior To Welding To Remove Thick Surface Oxide Films. (if The Material Or Work Is Exposed To An Outdoor Environment, This Time Limit Shall Be Reduced To A Maximum Of 3 Days, to Account For Atmospheric Effects.) Mechanical Cleaning Methods Shall Be Applied Just Prior To The Actual Start Of Welding, To Remove Any Reoxidation Or Residual Thin Oxide Films. 3.8.1 Chemical Treatment. An Acid Deoxidizing Treatment Shall Be Applied By Either Immersion Or Brushing/wiping. Deoxidizers Acceptable For Use Shall Include Nitric Acid, Sulfuric Chromic, Phosphoric Chromic, Or Equivalent Solutions. Sodium Hydroxide solutions Shall Not Be Used. Care Shall Be Taken To Assure 100% Solution Coverage Of The Area To Be Welded. To Allow An Adequately Sized Deoxidized Area For Good Welding, The Solution Shall Be Applied To An Area Extending At Least 2 Inches From The Weld Site, or Ending At Any Closer Adjacent Edge. 3.8.2 Mechanical Means. Immediately Prior To Welding, Mechanical Cleaning Methods Shall Be Applied To The Weld Areas Previously Chemically Treated To Assure Removal Of Residual Or Reformed Oxides, If Any. Acceptable Methods Of Mechanical Cleaning Include stainless Steel Wire Brushing, Scraping, Filing, Or Sanding. However, Abrasives Containing Iron And Its Oxides, Steel Wool And Wire, And Copper Alloy Based Wire, Which May Become Embedded With Galvanically Active Metals And Accelerate Corrosion Of Aluminum alloys Shall Not Be Used. Mechanical Methods Shall Be Vigorous Enough To Adequately Remove Any Residual Oxide Films, But Gentle Enough To Avoid Forming An Excessively Rough Surface In The Comparatively Soft Metal Underneath. 3.9 At Faying Surfaces, Discontinuous Welds, Or Other Areas Where Atmospheric Liquids May Be Retained By Capillary Action, The Crevice Shall Be Sealed Using Sealing Compound Mil-s-81733 Or Equivalent. 3.10 The Shock Mount Listed In The Drawing Package (whether Identified As Sole Source, Recommended, Or Suggested) Has Been Tested And Approved For The Shock Mitigation System Of This Container. No Other Shock Mount May Be Substituted Without Written Permission of Naval Inventory Control Point, Philadelphia Unless An Alternate Is Specifically Indentified In This Contract. ;no Other Mount; Is An Approved Alternate Mount. welding And Welder Qualifications Shall Meet Current Aws D1.2 Standards. additionally, Cleaning Preperations Shall Be In Accordance With Mil-c-5541 and The Cleaning Paragraph Located In The Welding Requirements Section Of The Contract 3.11 1.0 General 3.11.1 This Statement Of Work (sow) Establishes The Criteria For Repair And Testing /inspection Of The Subject Item. It Includes Inspection, Component Repair And Replacement,reassembly And Testing Procedures Required To Return Units Back Into A Servicable condition. 3.12 2.0 Definitions. 3.12.1 Contractor: Is Defined As The Successful Offeror Awarded A Contract, Orderor Issued A Project Work Order. The Term "contract" Encompasses A Contract, An Order, Or A Project Work Order. 3.12.2 Overhaul: An Overhauled Part Is One Which Has Been Disassembled, Cleaned, Inspected, Repaired As Necessary (by Replacing Or Repairing All Components Which Have Been Found To Exceed Limits Established By The Repair/overhaul Manual) Reassembled And Tested in Accordance With The Approved Repair/overhaul Manual Listed In This Sow And Returned To A Ready For Issue (rfi) Condition (refer To Contract Schedule For Items To Be Overhauled). 3.12.3 Repair: A Repaired Part Is One Which Has Been Restored To A Ready For Issue(rfi) Condition (by Replacing Or Repairing Those Components Found To Be Defective, Broken, Damaged Or Inoperative During The Initial Evaluation And Troubleshooting Phase) And tested In Accordance With The Approved Repair/overhaul Manual Listed In This Sow (refer To Contract Schedule For Items To Be Repaired). 3.13 3.0 Scope 3.13.1 General. The Items To Be Furnished Hereunder Shall Be Overhauled, Upgraded,repaired, Tested, Inspected, And Accepted In Accordance With The Terms And Conditions Specified In This Contract. Unless Expressly Provided Government Furnished Property, including Equipment Such As Fixtures, Jigs, Dies, Patterns, Mylars, Special Tooling, Special Test Equipment, Or Any Other Manufacturing Aid Required For The Repair, Manufacture, And/or Testing Of The Subject Item(s) Will Not Be Provided By The Government And shall Be The Responsibility Of The Contractor. The Foregoing Applies Notwithstanding Any Reference To Such Equipment Or The Furnishing Thereof That May Be Contained In Any Drawing, Manual, Or Specification For The Contract Items. 3.13.2 Repair Upgrade Requirements:the Contractor Shall Provide The Necessary facility, Labor, Materials, Parts, And Test And Tooling Equipment Required To To Return The Following Items To A Ready For Issue (rfi) Condition: shipping And Storag ;583e001; P/n, ;6kh 8145 013574414; Nsn, ;ag-830ac-meb-000 Work Package 025 00; Tech Publications 3.13.3 Rfi Is Defined As That Condition Allowing The Items To Perform Properly And Reliably In An Operational Environment In A Manner They Were Intended To Operate.the Contractor Must Perform All Repairs/upgrades At The Facility Identified Within This Sow. repairs Performed By The Contractor Or Subcontractor Shall Be Performed In Accordance With The Specified Drawings And Repair Manual(s). 3.14 Changes To Such Manuals Used For Repairs Under This Contract, Or Changes To Drawings Or Specifications Used In The Manufacture Of Parts Utilized In These Repairs, Require Procuring Contracting Officer (pco) Approval In Accordance With The Configuration management Provisions Of This Statement Of Work Or Contract. Under No Circumstances Should The Repair, Test, And Inspection Extend Beyond The Requirements Of This Paragraph Unless Authorized By The Government Qar.in Addition, Requests For Approval Of Changes to A Repair Source Or Repair Facility Shall Be Submitted In Writing To The Pco Prior To Making Any Such Change. 3.14.1 Any Repairs Performed Using Unapproved Changes To Such Manuals, Drawings, Specifications, Or Changes To Repair Source Or Facility Are Done At The Contractor's Own Risk. If The Government Disapproves The Requested Change, The Contractor Shall Replace Any delivered Items Repaired Using Such Unapproved Manuals,drawing, Specification, Repair Source Or Repair Facility Change. The Contractor Is Not Entitled To Any Equitable Adjustment To The Contract Price Or Terms Based On The Government's Disapproval Of A requested Change To Manuals, Drawings, Specifications, Or To A Repair Source Or Facility. 3.14.2 References On Drawings And Specifications:for Repair And Overhaul Purposes Only. All References To The "prime Contractor" Or The "actual Manufacturer" Appearing On The Drawings And / Or Specifications Or Technical Data Furnished By The Government Shall be Read As The "government Designated Agency" 3.14.3 Process Control Documentation: The Contractor Shall Prepare And Maintain Repair Procedures, And Test / Inspection Information / Procedures Which Shall Be Made Available To The Government For Review And Approval. The Procedures Shall Include Sequential diagrams Of Processes, As Well As The Performance Specifications To Perform The Testing / Inspection Procedures. Those Processes Shall Be Frozen After Approval Of The Inspection / Test. 3.14.4 Beyond Economical Repair (ber). An Item Is Ber If The Cost Of The Repair Exceeds 75% Of The Production Quantity Price To Replace The Item, Current At Time Of Award. This Replacement Price Is For The Purposes Of Ber Determinations Only, And May Not Be used Or Relied On By The Offeror In The Pricing Of The Repairs Required By This Contract. Items Determined Ber Are Not Included In The Contract Price. The Contractor Shall Obtain Written Concurrence From Dcma For All Units Determined By The Contractor To Be ber. All Such Determinations, Including The Basis For The Determination, The Repair Required, The Proposed Price To Repair And The Dcma Written Concurrence Shall Be Provided By The Contractor To The Pco, With A Copy To The Inventory Manager. After Receipt Of the Required Documentation, The Pco Shall Provide The Contractor Disposition Instructions Or Contractual Authority For Repair Of The Item. The Contractor Is Not Authorized To Proceed With The Repair Until Notification To Proceed Is Received From The Pco. Any disposal Ordered Shall Be Performed By The Contractor In Accordance With All Applicable Regulations And In Accordance With All Dcma Disposal Procedures And Requirements. 3.14.5 Missing On Induction (moi). A Weapons Repairable Assembly (wra) Is Subject To This Moi Provision If The Item Received By The Contractor For Repair Is Missing One Or More Shop Replaceable Assemblies (sras). Contractor Replacement Of Moi Sras Is Not included In The Contract Price. The Contractor Shall Immediately Notify Dcma When An Item Is Received With Moi Sra(s) And Shall Obtain Written Verification From Dcma For All Wras Determined To Have Moi Sra(s). The Contractor Shall Provide All Such determinations, Including Identification Of The Missing Sra(s), And The Dcma Written Verification, To The Inventory Manager With A Copy To The Pco And Aco Prior To Induction And/or Repair Of The Wra. The Contractor Shall Not Induct And/or Repair Wras With Moi sras Until Instructions On How To Proceed Are Provided To The Contractor By The Inventory Manager (where No Adjustment Price To The Contract Is Required) Or By The Pco. Items Received By The Contractor Missing Consumable Parts Are Not Moi Items. Rather, repair Of Such Items And Replacement Of The Missing Consumable Parts Are Included In The Contract Price And The Item Shall Be Inducted And Repaired By The Contractor Under This Contract. 3.14.6 Replacing Failed Or Missing Shop Replaceable Assembly (sra) When Repairinga Weapons Replaceable Assembly (wra). 3.14.7 A. When The Contractor Believes One Or More Sra(s) Within A Wra Are Either: 3.14.8 Beyond Economic Repair (ber) Or Beyond Repair (br) I. E. The Unit Is Not Capable Of Being Repaired Because Of The Extent Of Physical Damage), Or Missing On Induction (moi), The Contractor Shall Obtain Written Verification From Dcma And Advice From The inventory Manager Whether A Sra May Be Replaced By One Or More Of The Following Options: Ship In Place From An Existing Spares Or Repair Contract, If Any, Milstrip The Sra(s), Otherwise Be Provided Direction For Obtaining The Sra(s) At No Cost To The contractor.the Detailed Procedures Are Set Forth In Section 6.0 Of The Web-based Commercial Asset Visibility (cav) Statement Of Work. 3.14.9 B.when Not Otherwise Provided For (or Precluded) By Other Terms Of This Contract, The Contractor May Seek Written Authorization To Replace Failed Sra(s) With Ready For Issue Sra(s). When Authorized, The Procedures Set Forth In Paragraph 3.0 Of Section 6.2 Of The Web-based Commercial Asset Visibility (cav) Statement Of Work Shall Be Followed. 3.14.10 Over And Above Repair (oar). An Item Sent To The Contractor Shall Be Considered To Require Over And Above (oar) Repair Effort If The Repair Required Is Not The Type Of Repair That Would Be Anticipated As A Result Of Normal Navy Operation Of The Item and Is Not Included In The Contract Pricing Due To The Nature Or Scope Of The Repair Needed For That Particular Item. Therefore, Repair Of Oar Items May Be Subject To Equitable Adjustment. The Contractor Shall Obtain Written Concurrence From Dcma For All units Determined By The Contractor To Require Oar Effort. All Such Oar Determinations, Including The Basis For The Determination, The Repair Required, The Proposed Price To Repair And The Dcma Written Concurrence, Shall Be Provided By The Contractor To The Pco prior To Undertaking Repair Of The Item. after Receipt Of The Required Documentation, The Pco Shall Provide The Contractor Disposition Instructions Or Contractual Authority For Repair Of The Item. Any Ordered Disposal Shall Be Performed By The Contractor In Accordance With All Applicable Regulations and Dcma Disposal Procedures And Requirements. 3.15 4.0 Parts And Materials 3.15.1 General. The Contractor Is Responsible For Supplying All Parts And Material Necessary To Perform The Required Repairs Under This Contract Unless Parts Or Material Are Specifically Identified As Government Furnished Material (gfm). All Parts And material Used In Performance Of This Contract Shall Be In Accordance With The Latest Approved Revision Of Applicable Drawings And Specifications And Shall Be New In Accordance With Far 52.211-5, Material Requirements, Which Is Incorporated By Reference Herein. authorization To Use Other Than New Material As Defined By Far 52.211-5 Requires Written Approval From The Pco. In Addition, Cannibalization Must Be Approved By The Pco. Cannibalization Of Units That Have Not Been Inducted Is Not Typically Authorized And requires Specific Approval By The Pco. 3.15.2 The Contractor Shall Ensure It Has Access For The Duration Of This Contract To Updated Drawings And Specifications For Parts And Material Required For Repairs Performed Under This Contract. Any Change To Such Parts/material Drawings Or Specifications requires Government Approval In Accordance With The Configuration Management Provisions Of This Statement Of Work. Written Approval From The Pco Must Be Obtained Prior To Any Change To The Manufacturing Source Or Manufacturing Facility For All Parts Which require Source Approval, Unless The Contractor Is The Design Control Agent (dca) (i.e. The Entity Responsible For Maintaining The Latest Configuration Data) For The The Contract Item. If The Contractor Is The Dca, The Contractor May Approve Approve Changes To manufacturing Source Or Manufacturing Facility For All Parts, Including Those Which Require Source Approval. Any Repairs Performed Using Unapproved Changes To Such Drawings, Specifications Or Manufacturing Source Or Facility Are Done At The Contractor's Own risk. If The Government Disapproves The Requested Change, The Contractor Shall Replace Any Delivered Items Repaired Using Such Unapproved Change. The Contractor Is Not Entitled To Any Equitable Adjustment To The Contract Price Or Terms Based On The government's Disapproval Of A Requested Change To The Drawings, Specifications Or Manufacturing Source Or Facility. 3.15.3 Purchased Material Control And Parts Control. The Contractor Shall Establish And Maintain A System Of Control Over Purchased Parts And Material. Such Controls Shall, At A Minimum, Assure That The Parts And And Material Purchased Are In Compliance With the Requirements Of This Contract. 3.15.4 Receiving Inspection Of Purchased Parts And Material. (1)purchased Items Shall Be Inspected Upon Receipt At The Contractor's Facility To Assure Conformance With All Requirements Of The Applicable Drawings And Specifications Or (2)the Contractor Shall provide Prior To The Contract Award Evidence For Government Review And Approval Of A Purchased Parts And Material System Which Provides For The Inspections To Assure Conformance With All Requirements Of The Applicable Drawings And Specifications. Evidence Of such Inspections Of Such Inspections Shall Be Maintained By The Contractor Or Subcontractor For Government Review.the Inspection Report Shall, At A Minimum, Include A Record Of All Dimensional Data (coordinate/positional), Material, Finish, And Process With appropriate Pass/fail Criteria Such As Certifications and Actual Dimensonal Readings. 3.15.5 ^^^note^^^part Cannibalization Is Not Authorized Unless Specifically Approved By Navsup Wss And The Bde. 3.15.6 3.16 Source And Location Of Repair Source: 3.16.1 The Contractor Shall Specify The Name Of The Source/division Performing The Work And The Actual Location Where Work Will Be Performed. shipping And Storag ;tbd; Company Name , ;tbd; Address , ;tbd; Cage Code inspection Will Be Accomplished On The Contractor's Equipment 3.17 5.0 Contractor Quality Requirements: 3.17.1 Quality Program. The Contractor Shall Establish, Implement, Document And Maintain A Quality System That Ensures Conformance To All Applicable Requirements Of Iso 9001/ Sae As9100. The Contractor's Quality Management System/program Shall Be Designed To promptly Detect, Correct And Prevent Conditions That Adversely Affect Quality. 3.17.2 Calibration System Requirements. Contractor Shall Maintain A Calibration System That Meets The Requirements Of Ansi/ncsl Z540.3, Iso-10012-1 Or An Equivalent Calibration Program Acceptable To The Government. 3.18 6.0 Configuration Management (cm): 3.18.1 The Contractor Shall Maintain A Configuration Management Plan In Accordance With The Provisions Of Navsup Wss Configuration Management Clause Navicpia18. (refer To Contract). 3.19 7.0 Markings. 3.19.1 Marking Shall Be As Indicated In The Contract When Applicable. 3.20 8.0 Storage; 3.20.1 The Contractor Shall Provide A Proper Enclosed Warehouse Environment For Both Material Items Awaiting Repair And Assets Which Have Been Repaired And Are Awaiting Shipment To Ensure The Items Are Not Damaged While Being Stored. 4. Quality Assurance 4.1 The Tests To Be Performed Under The First Article Approval Clause (far 52.209-4) Of The Contract Are Listed Below. 4.1.1 Dimensional Test (special) ;applies; 4.1.2 Requirements Of: ;to Drawing (05259) 583e001 And Sub-drawings As Applicable; 4.1.3 Form: ;applies; 4.1.4 Fit: ;applies; 4.1.5 Function ;applies; 4.1.6 Compliance With Drawing ( ;05259; ) ;583e001; , Revision ;latest; And Specifications Referenced Therein. 4.2 In Addition To The Above Tests, The First Article(s) To Be Delivered Hereunder Shall Also Be Subjected To Those Tests Which Will Demonstrate That The Article(s) Comply With Contract Requirements Requirements. 4.3 The Contractor Shall Be Responsible For Providing The Necessary Parts And Repair Of The First Article Sample(s) During Testing. 4.4 The Cost Of The Government Testing Effort Set Forth In This Solicitation Is Estimated To Be $ ;12000; For The First Article Testing. This Cost Factor Will Be Added, For Solicitation Purposes, To The Price Of All Offerors For Whom The Government Will require Such Testing. 4.5 Disposition Of Fat Samples 4.5.1 ;zero; Sample(s) Shall Not Be Returned To The Contractor Because They Shall Be Destroyed During Testing. 4.5.2 ;all; Unless Otherwise Provided For In The Contract, Sample(s) Shall Be Returned To The Contractor And May Be Considered As Production Items Under The Contract Provided The Sample(s) Can Be Refurbished To Ready For Issue Condition And Provided The sample(s) Have Inspection Approval From The Cognizant Dcmc Qar. Sample(s) May Be Shipped As Production Items Only After All Other Units Required Under The Contract Have Been Produced And Are Ready For Shipment. ;n/a; Sample(s) Shall Be Returned To The Contractor But Shall Not Be Considered As Production Due. 4.6 Test Sample Coating Instructions 4.6.1 Samples Are To Be Unpainted. Corrosive Areas Are To Be Coated With A Light Preservative.this Paragraph Does Not Apply To Shipping Containers. 4.7 Fat Approval Criteria 4.7.1 Far 52.209-4 Applies (a) The Contractors Shall Deliver ;one (1); ; Unit(s) Of The Following Cage ( ;05259; ; ) Part Number ;583e001; ; , Revision ;latest; ; Within ;120; ; Calendar Days From The Date Of This Contract To The Government At ;contact Buyer On Page 1 Of The Contract; ; marking Of Test Sample(s) Shipping Container Shall Be As Follows, Citing This Contract Number: "for First Article Testing. Not Rfi Material. Do Not Take Up In Stock Contract Number:____________" for First Article Test, The Shipping Documentation Shall Contain This Contract Number And Lot/item Identification. The Characteristics That The First Article Must Meet And The Testing Requirements Are Specified Elsewhere In This Contract. (b) Upon Shipment Of First Article Sample(s), Two (2) Copies Of The Material Inspection And Receiving Report (dd Form 250) Bearing The Qar's Signature And Indication Of Preliminary Inspection Shall Be Forwarded To The Navicp- Philadelphia Code Cited In Block 10.a Of Sf33, With Duplicate Copies To Navicp Code 072 And To The Designated Test Facility. The Envelopes Shall Be Clearly Marked: "do Not Open In Mail Room". within ;90; ; Days After Receipt Of The Samples, The Test Site Shall Complete Testing/evaluation And Submit Two (2) Copies Of Their Test Report With Conclusions And Recommendations To The Navicp Code Cited In Block 10.a Of The Sf33. (c) Within ;120; ; Calendar Days After The Government Receives The First Article, The Contracting Officer Shall Notify The Contractor, In Writing, Of The Approval, Conditional Approval, Or Disapproval Of The First Article. The Notice Of Approval, Conditional approval, Or Disapproval Shall Not Relieve The Contractor From Complying With All Requirements Of The Specifications And All Other Terms And Conditions Of This Contract. A Notice Of Conditional Approval Shall State Any Further Action Required Of The Contractor. a Notice Of Disapproval Shall Cite Reasons For Disapproval. (d) If The First Article Is Disapproved, The Contractor, Upon Government Request, Shall Submit An Additional First Article For Testing. After Each Request, The Contractor Shall Make Any Necessary Changes, Modifications, Or Repairs To The First Article Or select Another First Article For Testing. All Costs Related To These Tests Are To Be Borne By The Contractor, Including Any And All Costs For Additional Tests Following A Disapproval. The Contractor Shall Furnish Any Additional First Article To The government Under The Terms And Conditions And Within The Time Specified By The Government. The Government Shall Act On This First Article Within The Time Limit Specified In Paragraph (b) Above. The Government Reserves The Right To Require An Equitable adjustment Of The Contract Price For Any Extension Of The Delivery Schedule Or For Any Additional Costs To The Government Related To These Tests. (e) If The Contractor Fails To Deliver Any First Article On Time, Or The Contracting Officer Disapproves Any First Article, The Contractor Shall Be Deemed To Have Failed To Make Delivery Within The Meaning Of The Default Clause Of This Contract (f) Unless Otherwise Provided In The Contract, The Contractor - (1) May Deliver The Approved First Article As Part Of The Contract Quantity, Provided It Meets All Contract Requirements For Acceptance And Was Not Consumed Or Destroyed In Testing: And (2) Shall Remove And Dispose Of Any First Article From The Government Test Facility At The Contractors Expense. (g) If The Government Does Not Act Within The Time Specified In Paragraph (b) Or (c) Above The Contracting Officer Shall, Upon Timely Written Request From The Contractor, Equitably Adjust Under The Changes Clause Of This Contract The Delivery Or Performance dates And/or The Contract Price, And Any Other Contractual Term Affected By The Delay. (h) The Contractor Is Responsible For Providing Operating And Maintenance Instructions, Spare Parts Support, And Repair Of The First Article During Any First Article Test. (i) Before First Article Approval, The Acquisition Of Materials Or Components For, Or The Commencement Of Production Of, The Balance Of The Contract Quantity Is At The Sole Risk Of The Contractor. Before First Article Approval, The Costs Thereof Shall Not Be allocable To This Contract For (1) Progress Payments, Or (2) Termination Settlements If The Contract Is Terminated For The Convenience Of The Government (j) The Contractor Shall Produce Both The First Article And The Production Quantity At The Same Facility And Shall Submit A Certification To This Effect With Each First Article. (k) The Contractor Shall Provide Specific Written Notification To The Procuring Contracting Officer Informing Him/her Of The Shipment Of Any Article(s) Furnished In Accordance With This Clause. Such Notification Must Be Addressed To The Attention Of The navicp Code Specified In Block 10.a Of The Sf33, With Copies To Navicp Code 072 And To The Testing Activity. Failure To Provide Such Notification Shall Excuse The Government From Any Delay In Performing First Article Testing And Informing The Contractor Of the Results Thereof. (l) Fourteen (14) Days Prior To Shipment Of First Article Samples, The Contractor Shall Notify The Designated Test Facility In Writing Of The Anticipated Shipping Date, With An Information Copy To The Pco, Navicp Philadelphia, Attn: (cite Code Found In Block 10.a Of The Sf33). The Contractor Shall Also Arrange For Preliminary Inspection Of Test Samples By The Dcmc/qar. 4.8 Alternate Offers - Waiver Of First Article Approval Requirements. (the Following Provisions Supersede Any Waiver Of First Article Approval Requirements Terms Set Forth In Clause 52.209-3 Or 52.209-4 As Appropriate) (a) Unless Otherwise Specified In The Solicitation, The Naval Inventory Control Point Reserves The Right To Waive The First Article Approval Requirements Specified Herein For Offerors Who Have Previously Furnished Identical Production Articles Accepted By The government Or The Original Equipment Manufacturer/prime Manufacturer. An Offeror Requesting Waiver Of First Article Requirements Shall Submit Evidence With Its Offer Establishing That: (i) The Last Production Unit Was Delivered Within Three (3) Years Of The Issue Date Of This Solicitation, And (ii) The Production Location To Be Used For This Requirement Is The Same As Used For The Previous Production Run additionally, The Offeror Shall Submit A Certification, To Be Executed By The Officer Or Employee For The Offer, Stating That: (i) The Articles To Be Provided Will Be Produced Using The Same Facilities, Processes, Sequences Of Operations And Approved Subcontractors As Those Previously Delivered And Accepted By The Government Or The Original Equipment Manufacturer/prime Manufacturer, and (ii) The Previous Production Units Were Manufactured Without Material Review Board Disposition Or Waiver/deviation Request Or Rejection Of Pre-production Samples For Cause. (note: This Certification Concerns A Matter Within The Jurisdiction Of An Agency Of The United States And The Making Of A False, Fictitious, Or Fraudulent Certification May Render The Maker Subject To Prosecution Under Title 18, United States Code, Section 1001.) (b) Offerors Requesting Waiver Of First Article Approval Requirements Under The Provisions Of This Clause Are Cautioned To Submit Two Prices For Articles Required Herein - One That Is Based On Compliance With The First Article Approval Requirements And One that Is Based On A Waiver Of Such Requirements. Where An Offeror Submits Only One Price And Fails To Clearly State That The Price Is Based On Waiver Of The First Article Approval Requirements It Will Be Deemed To Be Based On Compliance With The First Article approval Requirements (c) In The Event Of The First Article Approval Requirement Is Granted, The Delivery Schedule For The Production Items Shall Be Reduced By The Number Of Days Designated For Delivery Of First Article Test Unit Plus The Number Of Calendar Days Indicated For The government Notification Of Conditional Approval Or Approval. These Requirements Are Specified In The Quality Assurance Section Of This Solicitation. If The Offeror Is Unable To Meet The Desired Schedule, He Shall Insert Below The Alternate Delivery Schedule he Offers To The Government. Offeror's Proposed Alternate Delivery Schedule (based On Waiver Of First Article Approval Requirements) within Days: item No. _______________ Quantity:_______ After Date Of Contract:__________ all Costs And Responsibilities Related To The First Article Test Submission Container Shipment To And From The First Article Test Facility Are To Be Borne By The Contractor 4.9 100% Production Leak Test. Each Container, Uninstrumented And Without Dummy Load, Shall Be Raised To A Height Of 18 Inches And Allowed To Fall Freely To A Concrete Or Similarly Hard Surface, Landing Flat On Its Base. The Container Shall Then Be Prepared for Testing By Sealing All Breathing Devices And Inserting Suitable Pressurized Fittings And Gauges. The Container Shall Be Closed And Sealed In A Normal Manner. The Pneumatic-pressure Technique Of Method 5009 Of Federal Test Method Standard No. 101c Shall Be used To Detect Leakage. An Initial Pressure Setting Equal To 1.0 + 0.1 - 0 Psig Shall Be Used. After Stabilization, Pressure Shall Be Monitored For Thirty Minutes. Any Loss In Pressure In Excess Of 0.05 Psig (adjusted For Changes In Temperature And Barometric pressure) Shall Be Cause For Rejection. Warning container May Explode Or Fasteners May Fail During Test. Use Protective Barriers To Avoid Injury To Personnel. 5. Packaging- Mil-std 2073 Packaging Applies As Found Elsewhere In The Schedule 6. Notes - Not Applicable

DEPT OF THE NAVY USA Tender

Others
Corrigendum : Closing Date Modified
United States
Closing Date28 Mar 2025
Tender AmountRefer Documents 
Details: Item Unique Identification And Valuation (jan 2023)|19|n792.06|s8r|215-697-0275|patrick.j.horan23.civ@us.navy.mil|||||||||||||||| higher-level Contract Quality Requirement|8|x|||||||| inspection And Acceptance Of Supplies|26|x||||||||||||x|||||||||||||| time Of Delivery (june 1997)|20||||||||||||||||||||| stop-work Order (aug 1989)|1|| wide Area Workflow Payment Instructions (jan 2023)|16|invoice And Receiving Report Combo Type ||tbd|n00383|tbd|tbd|see Schedule|tbd||||||||| navy Use Of Abilityone Support Contractor - Release Of Offeror Information (3-18))|1|| equal Opportunity (sep 2016)|2||| integrity Of Unit Prices (nov 2021)|1|| warranty Of Supplies Of A Noncomplex Nature (jun 2003)|6|12 Months|60 Days After Discovery Of Defect||||| safeguarding Sensitive Conventional Arms, Ammunition, And Explosives (nov 2023)|9|||||||||| equal Opportuity For Workers With Disabilities (jun 2020)|2||| transportation Of Supplies By Sea (jan 2023)|2||| buy American-free Trade Agreements-balance Of Payments Program-basic (feb 2024)|11|||||||||||| alternate A, Annual Representations And Certifications (nov 2023)|13|||||||||||||| buy American-free Trade Agreements-balance Of Payments Program Certificate-basic (feb 2024))|5|||||| buy American--balance Of Payments Program (feb 2024)|1|| royalty Information (apr 1984)|1|| annual Representations And Certifications (may 2024)|12|332439|600||||||||||| type Of Contract (apr 1984)|1|| notice Of Priority Rating For National Defense, Emergency Preparedness, Andenergy Program Use (apr 2008))|2||x| navsup Is Looking For Firm Fixed Price Proposals. Estimated Pricing Can Be Submitted At Worse Case Scenario. Only Offers Submitted In Response To This Amendment Will Be Considered For Award. Solicitation Close Date Extended To March 28, 2025. interested Vendors Should Submit A Tiered Pricing Repair Proposal. please Submit An Evaluation Price As Well As Pricing For Minor, Moderate, And Major Repair Tiers. \ the Following Language Is Hereby Added To The Solicitation Notes: repair Turnaround Time (rtat) Definition: The Contractual Delivery Requirement Is Measured From Asset Return To The Date Of Asset Acceptance Under The Terms Of The Contract. For Purposes Of This Section, Return Is Defined As Physical Receipt Of The F-condition asset At The Contractor's Facility As Reflected In The Action Date Entry In The Commercial Asset Visibility (cav) System. In Accordance With The Cav Statement Of Work, The Contractor Is Required To Accurately Report All Transactions By The End Of The Fifth regular Business Day After Receipt And The Action Date Entered In Cav Must Be Dated To Reflect The Actual Date Of Physical Receipt. the Contractor Must Obtain Final Inspection And Acceptance By The Government For All Assets Within The Rtats Established In The Subsequent Contract. required Rtat: ## 111 Days After Receipt Of Asset throughput Constraint: Contractor Must Provide A Throughput Constraint For Each Nsn(s). Total Assets To Be Repaired Monthly After Initial Delivery Commences X/month (contractor Fill In #). A Throughput Of ##____ Per Month Reflects No Throughput Constraint. Induction Expiration Date: 365 Days After Contract Award Date. Any Asset Received After This Date In Days Is Not Authorized For Repair Without Bi-lateral Agreement Between The Contractor And Navsup Wss contracting Officer. reconciliation:a Reconciliation Modification Will Be Issued After Final Inspection And Acceptance Of All Assets Inducted Under The Subsequent Contract. The Parties Have Agreed To A Price (shown On The Schedule Page) For Each Unit At The Negotiated Rtat. Such prices Are Based On The Contractor Meeting The Rtat Requirements Described Within The Schedule Page. If The Contractor Does Not Meet The Applicable Rtat Requirement, Consideration Will Be Assessed And Subject To Negotiation. \ the Government Will Award A Contract Resulting From This Solicitation To The Responsible Offeror Whose Offer Conforming To The Solicitation Will Be Most Advantageous To The Government, Price And Other Factors Considered. In Addition To Price, The Following non-price Evaluation Factor Shall Be Used To Evaluate Offers And Are Listed In Descending Order Of Importance. relevant Past Performance technical Capability the Non-price Evaluation Factors, When Combined, Are Significantly More Important Than Price. There Are No Subfactors. the Government Reserves The Right To Obtain Information For Use In The Evaluation Of Past Performance From Any And All Sources Including Sources Outside Of The Government. Offerors Lacking Relevant Past Performance History Will Not Be Evaluated Favorably Or unfavorably On Past Performance. The Government Will Consider The Quality Of An Offeror's Relevant Past Performance. This Consideration Is Separate And Distinct From The Contracting Officer's Responsibility Determination. The Assessment Of The Offeror's R relevant Past Performance Will Be Used As A Means Of Evaluating The Relative Risk Of The Offeror And Other Competitors In Successfully Meet The Requirements Of The Rfp. In Determining The Rating For The Past Performance Evaluation Factor, The Government Will Give Greater Consideration To The Contracts Which The Government Feels Are Most Relevant To The Rfp. the Government Reserves The Right To Award The Contract To Other Than The Lowest Priced Offeror. page Limitation-excluding The Cover Page, Table Of Contents, Past Performance Project Forms The Technical Capability Proposal Is Limited To Fifteen (25) Pages In At Least 11pt. Font And 1" Margins. Pages In Excess Of This Limitation Will Not Be Evaluated. The pages Excluded From Evaluation Will Be At The Discretion Of The Agency. contractors Are Informed That It Is The Government's Desire To Make Award On Initial Proposals When Deemed Possible By The Contracting Officer, However The Government Reserves The Right To Communicate And/or Negotiate With Offerors If Later Determined Necessary. none Price Proposal (all Non-price Factors) -the Contractor Is Required To Submit The Following Non-price Information: 1. Relevant Past Performance: the Contractor Is Provided An Opportunity To Demonstrate Relevant Past Performance On Contracts Currently Being Performed Or Performed Within The Past Three (3) Years. The Government Will Determine Relevance By Analyzing The Scope And Magnitude Of The Reference contracts And Comparing Them To The Instant Requirement. The Government Reserves The Right To Evaluate Submitted Projects Individually Or In The Aggregate In Order To Determine Relevance And Will Do So Consistently Across All Evaluated Offers. The Government will Consider The Quality Of The Contractor's Relevant Past Performance. reference Contracts: A. The Contractor May Submit Up To A Maximum Of Three (3) Contracts For Evaluation. The Government Reserves The Right To Obtain Information From Sources Other Than Those Identified By The Contractor. 2. Technical Capability the Government Desires That Offerors Demonstrate Technical Capability To Satisfy The Government's Requirements. The Offeror's Response Will Be Evaluated To Determine Whether Its Response Poses Risk To Performance Or Whether It Will Result In Better Value To The government. In Response To This Evaluation Factor, Offerors Shall Address Its Manufacturing Equipment; Inspection Method Sheets; Incoming Inspection Sheets; Process Sheets; Quality System Compliance; Welding Certification. in Responding To The Above Areas Of The Technical Capability Factor, It Is Incumbent Upon The Offeror Provide A Level Of Detail The Demonstrates To The Government's Satisfaction That The Offeror Has The Technical Capability To Perform The Requirement. If The proposal Lacks Sufficient Detail, It May Result In The Government Assessing Risk In The Proposal. While There Is No Prescribed Method For Demonstrating Technical Capability, The Below Are Items Of Interest To The Government That The Contractor May, At Its discretion, Address To Assist The Government In Gaining An Understanding Of The Offerors Technical Capability. Offerors Are Cautioned That While These Areas Of Interest Are Not Mandatory Elements That Are Required To Be Addressed, Failure To Address Them Or comparable Indicia Of Technical Capability, May Limit The Government's Understanding Of Technical Risk And Result In The Assignment Of Commensurate Risk. Offerors Are Also Notified That Some Of These Indicia Of Capability Are Overlapping, I.e., Two Or More May evidence The Same Facet Of Capability. certification Of Possession Or Access To The Following Equipment:for Aluminum And Steel Welded Containers, & Bladebox/riveted Construction 1.brake Press 2.extrusion Dies 3.cnc Machining Center(s) Capable Of Lathe And/or Milling Operations copies Of Inspection Method Sheets Used In-process And/or At Final Inspection copies Of Incoming Inspection Documents That Show Material Certificates Of Conformance, And If Applicable, Dimensional Conformance process/operation Sheets To Show Ability To Conform To Drawing Requirements In The Following Areas: Weld Preparation; Welding Procedure Specifications Production Lot Testing proof Of Compliance To Iso9001, And/or, As9100. applicable Up-to-date Welder Certifications Showing Highest-level Certification Obtained Aws D1.1 For Steel, Aws D1.2 Or Mil-w-22248,class 4 For Aluminum, Aws D1.3 For Sheet Steel And Aws D1.6 For Stainless Steel. if The Offeror Address Any Or All Of The Above, Or Provides Comparable Indicia Of Capability, It Is Encouraged To Provide Supporting Evidence And Detail, Such As But Not Limited To Receipts, Certifications, Drawings, Test Results/ Logs, Maintenance Records, calibration Records, Inspection Reports, Audits, Etc. The Weigh Accorded To Supporting Evidence Will Be At The Discretion Of The Government. the Technical Capability Proposals Will Be Evaluated To Determine The Risk Of Unsuccessful Performance As Well As Relative Risk Compared To Other Offerors. navsup Wss Has Been Granted A Class Deviation (cl-00-203) That Permits Us To Use The Award Forms Currently Available In Our Automated Procurement System Instead Of The Sf 1449 When Conducting Procurements For Commercial Items. this Procurement Is Being Conducted In Accordance With Far Part 12, Acquisition Of Commercial Products. information Appearing On The Face Of The Dd Form 1155 Or Sf 26 That Conflicts With Clauses Or Provisions Contained Elsewhere In This Solicitation Shall Be Disregarded. addendum To Far 52.212-4 Contract Terms And Conditions Commercial Products Under Paragraph(a) "inspection And Acceptance" Add The Following: 1. Far Clause 52.246-2 Inspection Of Supplies-fixed Price Applies As Amended Herein. All Product Audits Performed At The Discretion Of The Dcma Qar Shall Be Conducted By Witnessing Contractor Inspections Or Tests On A Non-interference Basis. 2. The Contractor Shall Maintain A Quality System That Addresses The Elements Of Iso9001-2000/as9100b, Quality System Model For Quality Assurance In Design/development, Production, Installation And Servicing, And A Calibration System That Addresses The Elements Of Iso-10012-1, Ansi/ncsl Z540 Or An Equivalent Program Approved By The Navy. 3. The Government Reserves The Right To Assess The Contractor's Compliance To Its Documented Quality System Throughout The Performance Of This Contract. The Quality System Procedures, Planning, And All Other Documentation, Media, And Data Which Comprise The quality System Shall Be Made Available To The Government For Their Review And Use. The Acceptance Of Non-conforming Supplies Is A Prerogative Of And Shall Be As Prescribed By The Government. The Government Reserves The Right To Disapprove The Quality System Or portions There Of When It Fails To Meet Its Intended Objectives. 4. The Contractor Shall Not Make Any Configuration Changes, Engineering Changes Or Part Number Changes To The Contract/purchase Order Items, Including, But Not Limited To, The Item's Hardware, Software Or Firmware, Unless Approved By The Procurement Contracting officer (pco). In Addition, Approval By The Appropriate Technical Authority May Also Be Required. Guidance On How To Submit A Proposed Engineering Or Part Number Change May Be Obtained From The Pco. 5. The Contractor Shall Not Manufacture Any Item For Acceptance By The Government That Incorporates A Known Departure From Technical Or Contractual Requirements Unless A Request For A Deviation Has Been Approved. Authorized Deviations Are A Temporary Departure from The Requirements Only And Do Not Authorize A Change To The Item's Configuration Baseline. Any Deviation, Major Or Minor, Must Be Approved By The Pco Prior To Acceptance. all Contractual Documents (i.e. Contracts, Purchase Orders, Task Ordersdelivery Orders And Modifications) Related To The Instant Procurement Are Considered To Be "issued" By The Government When Copies Are Either Deposited In The Mail, Transmitted By Facsimile, Or sent By Other Electronic Commerce Methods, Such As Email. The Government's Acceptance Of The Contractor's Proposal Constitutes Bilateral Agreement To "issue" Contractual Documents As Detailed Herein. early And Incremental Deliveries Accepted And Preferred. \ 1. Scope 1.1 Articles To Be Furnished Hereunder Shall Be Repaired, Tested And Inspected In Accordance With The Terms And Conditions Specified In The Requirements Section Of This Document. 1.1.1 Any Item Contracted For Repair Shall Have A Statement Of Work To Ensure Compliance With All Repair Procedures And Requirements. repair Of: shipping And Storag ;8145-01-437-5024; Nsn , ;21c14061g01; Part Number, Shall Be Performed Iaw: Shipping And Storag ;ag-830ac-meb-000 Work Package 039 00; Publication (s). 1.1.2 There Will Be No Repair Deviation From The Approved Written Procedures Without Review And Acceptance By The Basic Design Engineer. All Requests For Waiver/deviation Shall Be Via Form 1694 Routed Throught The Local Dcma/aco Office For Review And recommendations Via Form 1998. 1.2 Articles To Be Furnished Hereunder Shall Be Manufactured, Tested And Inspected In Accordance With � See Schdule/line Item�,and All Details And Specifications Referenced Therein. 1.3 When Discrepancies Exist Between These Requirements And Those On Current manufacturer's Drawings,contact Code ;contact Buyer On Page 1 Of The Contract; Or Code N241.10 1.4 Pre-award / Post Award Requirements: due To The Critical Use Of This Item And Its Quality History, A Pre-award Survey And Post-award Conference May Be Required For All New Manufacturers. For All Previous Sources, A Post-award Conference May Be Recommended. 1.5 Container Shell Material Is ;aluminum; . container Shall Include Revision R And S. Revision R & S May Be Provided By The Government As An Email Or Dod Safe Transfer. Revision R & S May Not Be The Latest Revision, Check With N241.12 For Latest Revision. when Discrepancies Exist Between These Requirements And Those On Current Manufacturer's Drawings, Contact Buyer Found On Page One Block Five Of The Contract. Until Drawings Have Been Updated Current Cid Changes Apply. 2. Applicable Documents - Not Applicable 3. Requirements 3.1 1.0 General 3.1.1 This Statement Of Work (sow) Establishes The Criteria For Repair And Testing /inspection Of The Subject Item. It Includes Inspection, Component Repair And Replacement,reassembly And Testing Procedures Required To Return Units Back Into A Servicable condition. 3.2 2.0 Definitions. 3.2.1 Contractor: Is Defined As The Successful Offeror Awarded A Contract, Orderor Issued A Project Work Order. The Term "contract" Encompasses A Contract, An Order, Or A Project Work Order. 3.2.2 Overhaul: An Overhauled Part Is One Which Has Been Disassembled, Cleaned, Inspected, Repaired As Necessary (by Replacing Or Repairing All Components Which Have Been Found To Exceed Limits Established By The Repair/overhaul Manual) Reassembled And Tested in Accordance With The Approved Repair/overhaul Manual Listed In This Sow And Returned To A Ready For Issue (rfi) Condition (refer To Contract Schedule For Items To Be Overhauled). 3.2.3 Repair: A Repaired Part Is One Which Has Been Restored To A Ready For Issue(rfi) Condition (by Replacing Or Repairing Those Components Found To Be Defective, Broken, Damaged Or Inoperative During The Initial Evaluation And Troubleshooting Phase) And tested In Accordance With The Approved Repair/overhaul Manual Listed In This Sow (refer To Contract Schedule For Items To Be Repaired). 3.3 3.0 Scope 3.3.1 General. The Items To Be Furnished Hereunder Shall Be Overhauled, Upgraded,repaired, Tested, Inspected, And Accepted In Accordance With The Terms And Conditions Specified In This Contract. Unless Expressly Provided Government Furnished Property, including Equipment Such As Fixtures, Jigs, Dies, Patterns, Mylars, Special Tooling, Special Test Equipment, Or Any Other Manufacturing Aid Required For The Repair, Manufacture, And/or Testing Of The Subject Item(s) Will Not Be Provided By The Government And shall Be The Responsibility Of The Contractor. The Foregoing Applies Notwithstanding Any Reference To Such Equipment Or The Furnishing Thereof That May Be Contained In Any Drawing, Manual, Or Specification For The Contract Items. 3.3.2 Repair Upgrade Requirements:the Contractor Shall Provide The Necessary facility, Labor, Materials, Parts, And Test And Tooling Equipment Required To To Return The Following Items To A Ready For Issue (rfi) Condition: shipping And Storag ;21c14061g01; P/n, ;8145-01-437-5024; Nsn, ;ag-830ac-meb-000 Work Package 039 00; Tech Publications 3.3.3 Rfi Is Defined As That Condition Allowing The Items To Perform Properly And Reliably In An Operational Environment In A Manner They Were Intended To Operate.the Contractor Must Perform All Repairs/upgrades At The Facility Identified Within This Sow. repairs Performed By The Contractor Or Subcontractor Shall Be Performed In Accordance With The Specified Drawings And Repair Manual(s). 3.4 Changes To Such Manuals Used For Repairs Under This Contract, Or Changes To Drawings Or Specifications Used In The Manufacture Of Parts Utilized In These Repairs, Require Procuring Contracting Officer (pco) Approval In Accordance With The Configuration management Provisions Of This Statement Of Work Or Contract. Under No Circumstances Should The Repair, Test, And Inspection Extend Beyond The Requirements Of This Paragraph Unless Authorized By The Government Qar.in Addition, Requests For Approval Of Changes to A Repair Source Or Repair Facility Shall Be Submitted In Writing To The Pco Prior To Making Any Such Change. 3.4.1 Any Repairs Performed Using Unapproved Changes To Such Manuals, Drawings, Specifications, Or Changes To Repair Source Or Facility Are Done At The Contractor's Own Risk. If The Government Disapproves The Requested Change, The Contractor Shall Replace Any delivered Items Repaired Using Such Unapproved Manuals,drawing, Specification, Repair Source Or Repair Facility Change. The Contractor Is Not Entitled To Any Equitable Adjustment To The Contract Price Or Terms Based On The Government's Disapproval Of A requested Change To Manuals, Drawings, Specifications, Or To A Repair Source Or Facility. 3.4.2 References On Drawings And Specifications:for Repair And Overhaul Purposes Only. All References To The "prime Contractor" Or The "actual Manufacturer" Appearing On The Drawings And / Or Specifications Or Technical Data Furnished By The Government Shall Be read As The "government Designated Agency" 3.4.3 Process Control Documentation: The Contractor Shall Prepare And Maintain Repair Procedures, And Test / Inspection Information / Procedures Which Shall Be Made Available To The Government For Review And Approval. The Procedures Shall Include Sequential diagrams Of Processes, As Well As The Performance Specifications To Perform The Testing / Inspection Procedures. Those Processes Shall Be Frozen After Approval Of The Inspection / Test. 3.4.4 Beyond Economical Repair (ber). An Item Is Ber If The Cost Of The Repair Exceeds 75% Of The Production Quantity Price To Replace The Item, Current At Time Of Award. This Replacement Price Is For The Purposes Of Ber Determinations Only, And May Not Be used Or Relied On By The Offeror In The Pricing Of The Repairs Required By This Contract. Items Determined Ber Are Not Included In The Contract Price. The Contractor Shall Obtain Written Concurrence From Dcma For All Units Determined By The Contractor To Be ber. All Such Determinations, Including The Basis For The Determination, The Repair Required, The Proposed Price To Repair And The Dcma Written Concurrence Shall Be Provided By The Contractor To The Pco, With A Copy To The Inventory Manager. After Receipt Of the Required Documentation, The Pco Shall Provide The Contractor Disposition Instructions Or Contractual Authority For Repair Of The Item. The Contractor Is Not Authorized To Proceed With The Repair Until Notification To Proceed Is Received From The Pco. Any disposal Ordered Shall Be Performed By The Contractor In Accordance With All Applicable Regulations And In Accordance With All Dcma Disposal Procedures And Requirements. 3.4.5 Missing On Induction (moi). A Weapons Repairable Assembly (wra) Is Subject To This Moi Provision If The Item Received By The Contractor For Repair Is Missing One Or More Shop Replaceable Assemblies (sras). Contractor Replacement Of Moi Sras Is Not included In The Contract Price. The Contractor Shall Immediately Notify Dcma When An Item Is Received With Moi Sra(s) And Shall Obtain Written Verification From Dcma For All Wras Determined To Have Moi Sra(s). The Contractor Shall Provide All Such determinations, Including Identification Of The Missing Sra(s), And The Dcma Written Verification, To The Inventory Manager With A Copy To The Pco And Aco Prior To Induction And/or Repair Of The Wra. The Contractor Shall Not Induct And/or Repair Wras With Moi sras Until Instructions On How To Proceed Are Provided To The Contractor By The Inventory Manager (where No Adjustment Price To The Contract Is Required) Or By The Pco. Items Received By The Contractor Missing Consumable Parts Are Not Moi Items. Rather, repair Of Such Items And Replacement Of The Missing Consumable Parts Are Included In The Contract Price And The Item Shall Be Inducted And Repaired By The Contractor Under This Contract. 3.4.6 Replacing Failed Or Missing Shop Replaceable Assembly (sra) When Repairinga Weapons Replaceable Assembly (wra). 3.4.7 A. When The Contractor Believes One Or More Sra(s) Within A Wra Are Either: 3.4.8 Beyond Economic Repair (ber) Or Beyond Repair (br) I. E. The Unit Is Not Capable Of Being Repaired Because Of The Extent Of Physical Damage), Or Missing On Induction (moi), The Contractor Shall Obtain Written Verification From Dcma And Advice From The inventory Manager Whether A Sra May Be Replaced By One Or More Of The Following Options: Ship In Place From An Existing Spares Or Repair Contract, If Any, Milstrip The Sra(s), Otherwise Be Provided Direction For Obtaining The Sra(s) At No Cost To The contractor.the Detailed Procedures Are Set Forth In Section 6.0 Of The Web-based Commercial Asset Visibility (cav) Statement Of Work. 3.4.9 B.when Not Otherwise Provided For (or Precluded) By Other Terms Of This Contract, The Contractor May Seek Written Authorization To Replace Failed Sra(s) With Ready For Issue Sra(s). When Authorized, The Procedures Set Forth In Paragraph 3.0 Of Section 6.2 Of The Web-based Commercial Asset Visibility (cav) Statement Of Work Shall Be Followed. 3.4.10 Over And Above Repair (oar). An Item Sent To The Contractor Shall Be Considered To Require Over And Above (oar) Repair Effort If The Repair Required Is Not The Type Of Repair That Would Be Anticipated As A Result Of Normal Navy Operation Of The Item And is Not Included In The Contract Pricing Due To The Nature Or Scope Of The Repair Needed For That Particular Item. Therefore, Repair Of Oar Items May Be Subject To Equitable Adjustment. The Contractor Shall Obtain Written Concurrence From Dcma For All Units determined By The Contractor To Require Oar Effort. All Such Oar Determinations, Including The Basis For The Determination, The Repair Required, The Proposed Price To Repair And The Dcma Written Concurrence, Shall Be Provided By The Contractor To The Pco Prior to Undertaking Repair Of The Item. after Receipt Of The Required Documentation, The Pco Shall Provide The Contractor Disposition Instructions Or Contractual Authority For Repair Of The Item. Any Ordered Disposal Shall Be Performed By The Contractor In Accordance With All Applicable Regulations and Dcma Disposal Procedures And Requirements. 3.5 4.0 Parts And Materials 3.5.1 General. The Contractor Is Responsible For Supplying All Parts And Material Necessary To Perform The Required Repairs Under This Contract Unless Parts Or Material Are Specifically Identified As Government Furnished Material (gfm). All Parts And Material used In Performance Of This Contract Shall Be In Accordance With The Latest Approved Revision Of Applicable Drawings And Specifications And Shall Be New In Accordance With Far 52.211-5, Material Requirements, Which Is Incorporated By Reference Herein. authorization To Use Other Than New Material As Defined By Far 52.211-5 Requires Written Approval From The Pco. In Addition, Cannibalization Must Be Approved By The Pco. Cannibalization Of Units That Have Not Been Inducted Is Not Typically Authorized And requires Specific Approval By The Pco. 3.5.2 The Contractor Shall Ensure It Has Access For The Duration Of This Contract To Updated Drawings And Specifications For Parts And Material Required For Repairs Performed Under This Contract. Any Change To Such Parts/material Drawings Or Specifications requires Government Approval In Accordance With The Configuration Management Provisions Of This Statement Of Work. Written Approval From The Pco Must Be Obtained Prior To Any Change To The Manufacturing Source Or Manufacturing Facility For All Parts Which require Source Approval, Unless The Contractor Is The Design Control Agent (dca) (i.e. The Entity Responsible For Maintaining The Latest Configuration Data) For The The Contract Item. If The Contractor Is The Dca, The Contractor May Approve Approve Changes To manufacturing Source Or Manufacturing Facility For All Parts, Including Those Which Require Source Approval. Any Repairs Performed Using Unapproved Changes To Such Drawings, Specifications Or Manufacturing Source Or Facility Are Done At The Contractor's Own risk. If The Government Disapproves The Requested Change, The Contractor Shall Replace Any Delivered Items Repaired Using Such Unapproved Change. The Contractor Is Not Entitled To Any Equitable Adjustment To The Contract Price Or Terms Based On The government's Disapproval Of A Requested Change To The Drawings, Specifications Or Manufacturing Source Or Facility. 3.5.3 Purchased Material Control And Parts Control. The Contractor Shall Establish And Maintain A System Of Control Over Purchased Parts And Material. Such Controls Shall, At A Minimum, Assure That The Parts And And Material Purchased Are In Compliance With The requirements Of This Contract. 3.5.4 Receiving Inspection Of Purchased Parts And Material. (1)purchased Items Shall Be Inspected Upon Receipt At The Contractor's Facility To Assure Conformance With All Requirements Of The Applicable Drawings And Specifications Or (2)the Contractor Shall provide Prior To The Contract Award Evidence For Government Review And Approval Of A Purchased Parts And Material System Which Provides For The Inspections To Assure Conformance With All Requirements Of The Applicable Drawings And Specifications. Evidence Of such Inspections Of Such Inspections Shall Be Maintained By The Contractor Or Subcontractor For Government Review.the Inspection Report Shall, At A Minimum, Include A Record Of All Dimensional Data (coordinate/positional), Material, Finish, And Process With appropriate Pass/fail Criteria Such As Certifications and Actual Dimensonal Readings. 3.5.5 ^^^note^^^part Cannibalization Is Not Authorized Unless Specifically Approved By Navsup Wss And The Bde. 3.5.6 3.6 Source And Location Of Repair Source: 3.6.1 The Contractor Shall Specify The Name Of The Source/division Performing The Work And The Actual Location Where Work Will Be Performed. shipping And Storag ;general Electric Co.; Company Name , ;1 Neuman Way Cincinnati Ohio; Address , ;66464; Cage Code inspection Will Be Accomplished On The Contractor's Equipment 3.7 5.0 Contractor Quality Requirements: 3.7.1 Quality Program. The Contractor Shall Establish, Implement, Document And Maintain A Quality System That Ensures Conformance To All Applicable Requirements Of Iso 9001/ Sae As9100. The Contractor's Quality Management System/program Shall Be Designed To promptly Detect, Correct And Prevent Conditions That Adversely Affect Quality. 3.7.2 Calibration System Requirements. Contractor Shall Maintain A Calibration System That Meets The Requirements Of Ansi/ncsl Z540.3, Iso-10012-1 Or An Equivalent Calibration Program Acceptable To The Government. 3.8 6.0 Configuration Management (cm): 3.8.1 The Contractor Shall Maintain A Configuration Management Plan In Accordance With The Provisions Of Navsup Wss Configuration Management Clause Navicpia18. (refer To Contract). 3.9 7.0 Markings. 3.9.1 Marking Shall Be As Indicated In The Contract When Applicable. 3.10 8.0 Storage; 3.10.1 The Contractor Shall Provide A Proper Enclosed Warehouse Environment For Both Material Items Awaiting Repair And Assets Which Have Been Repaired And Are Awaiting Shipment To Ensure The Items Are Not Damaged While Being Stored. 3.11 One Third (1/3) Unit Of Desiccant (mil-d-3464, Type Ii Nondusting) Per Cubic Foot Of Container Interior Volume Shall Be Placed In Desiccant Holder Of Each Container At Time Of Shipment. 3.12 At Faying Surfaces, Discontinuous Welds, Or Other Areas Where Atmospheric Liquids May Be Retained By Capillary Action, The Crevice Shall Be Sealed Using Sealing Compound Mil-s-81733 Or Equivalent. 3.13 Reference To Cadmium Plating Shall Be Deleted And The Following Substituted: "finish Shall Be Electrodeposited Alkaline Zinc-nickel Alloy In Accordance With Astm B 841 Class 1, Type B, Grade 3." 3.14 The Shock Mount Listed In The Drawing Package (whether Identified As Sole Source, Recommended, Or Suggested) Has Been Tested And Approved For The Shock Mitigation System Of This Container. No Other Shock Mount May Be Substituted Without Written Permission of Naval Inventory Control Point, Philadelphia Unless An Alternate Is Specifically Indentified In This Contract. ;no Other Shock Mount Approved; Is An Approved Alternate Mount. all Containers Must Be Affixed With A Nameplate That Includes A unique Identification (uid) Marking As Referenced In The Drawing Package drawing ;(80132) 15930; And Iaw Mil-std-130 Latest Revision. The Contractor shall Contact Navicp Code ;contact Buyer On Page 1; Or Code 0771.10 For The Alphanumeric sequential Serial Number Group That Makes Up Part Of The Uid. the Uidwill Be Included On The Nameplate In Data Matrix Format. 3.15 Welding And Welder Qualifications Shall Be In Accordance With Aws D1.1 for Steel, Aws D1.2 Or Mil-w-22248,class 4 For Aluminum, Aws D1.3 for Sheet Steel And Aws D1.6 For Stainless Steel. Proper Controls Shall Be Used To Prevent Melt Through Or Burn Through. For Aluminum, Filler For Welding 6061 Alloy Shall Be 4043: Filler For Welding 5000 Series Alloys to Themselves Or To 6061 Shall Be 5356 Or 5556. In Addition,welding And weld Inspection Shall Include: (1) Visual Inspection Shall Include 5x (5power) Magnification When A Suspect condition Is To Be Examined Beyond The Capability Of Normal Vision. (2) Critical And Major Welds May Be Subjected To Further Non Destructive testing (such As Dye Penetrant Inspection)as Prescribed By The Buying Activity. (3) Proper Documentation Shall Be Available For Review By Government Personnel. 3.16 Work Instructions. Work Instructions Shall Be Posted At Theoperator's Work Station Giving Procedures To Control The Welding Process, I.e., Filler Material, Weld Size, Electrical And Gas Characteristics, Including Flow Rate. 3.17 Materials And Materials Control. The Quality Program Shall Assure That The Materials Used In Fabrication Or Processing, I.e., Base Metals And Weld Filler Material, Be Inspected And Conform To The Applicable Physical, Chemical And Other Technical requirements (supplier's Certification Is Sufficient). 3.18 Controls. Weld Filler Materials Shall Be Clearly Identified And Segregated From Each Other Both When In Storage And At The Work Station. Work Station Environment Shall Be Controlled To Prevent Conditions Adverse To Proper Gas Shielding. 3.19 Cleaning. Parts To Be Welded Shall Be Cleaned To Remove Surface Soils Such As Oils, Waxes, Grease, Inks, Etc. Except That Uninhibited Alkaline Solutions Such As Sodium Hydroxide Shall Not Be Used. 3.20 Deoxidizing. The Cleaned Parts Shall Be Chemically Deoxidized No More Than 10 Days Prior To Welding To Remove Thick Surface Oxide Films. (if The Material Or Work Is Exposed To An Outdoor Environment, This Time Limit Shall Be Reduced To A Maximum Of 3 days, To Account For Atmospheric Effects.) Mechanical Cleaning Methods Shall Be Applied Just Prior To The Actual Start Of Welding, To Remove Any Reoxidation Or Residual Thin Oxide Films. 3.20.1 Chemical Treatment. An Acid Deoxidizing Treatment Shall Be Applied By Either Immersion Or Brushing/wiping. Deoxidizers Acceptable For Use Shall Include Nitric Acid, Sulfuric Chromic, Phosphoric Chromic, Or Equivalent Solutions. Sodium Hydroxide solutions Shall Not Be Used. Care Shall Be Taken To Assure 100% Solution Coverage Of The Area To Be Welded. To Allow An Adequately Sized Deoxidized Area For Good Welding, The Solution Shall Be Applied To An Area Extending At Least 2 Inches From The Weld Site, or Ending At Any Closer Adjacent Edge. 3.20.2 Mechanical Means. Immediately Prior To Welding, Mechanical Cleaning Methods Shall Be Applied To The Weld Areas Previously Chemically Treated To Assure Removal Of Residual Or Reformed Oxides, If Any. Acceptable Methods Of Mechanical Cleaning Include stainless Steel Wire Brushing, Scraping, Filing, Or Sanding. However, Abrasives Containing Iron And Its Oxides, Steel Wool And Wire, And Copper Alloy Based Wire, Which May Become Embedded With Galvanically Active Metals And Accelerate Corrosion Of Aluminum alloys Shall Not Be Used. Mechanical Methods Shall Be Vigorous Enough To Adequately Remove Any Residual Oxide Films, But Gentle Enough To Avoid Forming An Excessively Rough Surface In The Comparatively Soft Metal Underneath. 3.21 Surface Finishing. All Containers Shall Be Glass Bead Blasted On Exterior Surfaces Only To Provide A Uniform Matte Finish That Will Hide Minor Surface Imperfections, Such As Scratches, Weld Irregularities, Etc. Size #8 Glass Beads Per Mil-g-9954 Shall Be used With Direct Air Pressure Ranging From 50 To 70 Psig. A Separator Shall Be Used To Provide A Reclaim Efficiency Of 90%, I.e., A Minimum Of 90% By Weight Of The Original Sized Material Shall Be In The Reclaim. The Glass Bead Media Shall Be Maintained In A condition Free From Contamination With Other Metals, I.e., The Media Shall Not Have Been Used To Blast Equipment Containing Other Metals Or Alloys. contact Code ;contact Buyer On Page 1 Of Contract; Or Code N241.10 To Arrange For First Article Test Location welding And Welder Qualifications Shall Meet Current Aws D1.2 Standards. additionally, Cleaning Preperations Shall Be In Accordance With Mil-c-5541 and The Cleaning Paragraph Located In The Welding Requirements Section Of The Contract when A First Article Is Required, The Contractor Shall Submit A Paper Copy Of The Drawings (size 11" X 17"), Contracts And Approved Ecp's Eco's, Deviations Waivers, And Modifications In The Records Recepticle Or Inside The Container Submitted For The First article. 4. Quality Assurance 4.1 The Tests To Be Performed Under The First Article Approval Clause (far 52.209-4) Of The Contract Are Listed Below. 4.1.1 Dimensional Test (special) ;to Drawing (66464) 21c14061g01 And Sub Drawings Applicable; 4.1.2 Requirements Of: ;to Drawing (66464) 21c14061g01 And Sub Drawings Applicable; 4.1.3 Form: ;applies; 4.1.4 Fit: ;applies; 4.1.5 Function ;per 100% Production Leak Test; 4.1.6 Compliance With Drawing ( ;(66464); ) ;21c14061g01; , Revision ;latest; And Specifications Referenced Therein. 4.2 In Addition To The Above Tests, The First Article(s) To Be Delivered Hereunder Shall Also Be Subjected To Those Tests Which Will Demonstrate That The Article(s) Comply With Contract Requirements Requirements. 4.3 The Contractor Shall Be Responsible For Providing The Necessary Parts And Repair Of The First Article Sample(s) During Testing. 4.4 The Cost Of The Government Testing Effort Set Forth In This Solicitation Is Estimated To Be $ ;12k; For The First Article Testing. This Cost Factor Will Be Added, For Solicitation Purposes, To The Price Of All Offerors For Whom The Government Will Require such Testing. 4.5 Disposition Of Fat Samples 4.5.1 ;zero; Sample(s) Shall Not Be Returned To The Contractor Because They Shall Be Destroyed During Testing. 4.5.2 ;all; Unless Otherwise Provided For In The Contract, Sample(s) Shall Be Returned To The Contractor And May Be Considered As Production Items Under The Contract Provided The Sample(s) Can Be Refurbished To Ready For Issue Condition And Provided The sample(s) Have Inspection Approval From The Cognizant Dcmc Qar. Sample(s) May Be Shipped As Production Items Only After All Other Units Required Under The Contract Have Been Produced And Are Ready For Shipment. ;n/a; Sample(s) Shall Be Returned To The Contractor But Shall Not Be Considered As Production Due. 4.6 Test Sample Coating Instructions 4.6.1 Samples Are To Be Unpainted. Corrosive Areas Are To Be Coated With A Light Preservative.this Paragraph Does Not Apply To Shipping Containers. 4.7 Fat Approval Criteria 4.7.1 Far 52.209-4 Applies (a) The Contractors Shall Deliver ;one(1); ; Unit(s) Of The Following Cage ( ;(66464); ; ) Part Number ;21c14061g01; ; , Revision ;latest; ; Within ;120; ; Calendar Days From The Date Of This Contract To The Government At ; Test Facility Addresses Naval Air Warfare Center Aircraft Division; ; marking Of Test Sample(s) Shipping Container Shall Be As Follows, Citing This Contract Number: "for First Article Testing. Not Rfi Material. Do Not Take Up In Stock Contract Number:____________" for First Article Test, The Shipping Documentation Shall Contain This Contract Number And Lot/item Identification. The Characteristics That The First Article Must Meet And The Testing Requirements Are Specified Elsewhere In This Contract. (b) Upon Shipment Of First Article Sample(s), Two (2) Copies Of The Material Inspection And Receiving Report (dd Form 250) Bearing The Qar's Signature And Indication Of Preliminary Inspection Shall Be Forwarded To The Navicp- Philadelphia Code Cited In Block 10.a Of Sf33, With Duplicate Copies To Navicp Code 072 And To The Designated Test Facility. The Envelopes Shall Be Clearly Marked: "do Not Open In Mail Room". within ;90; ; Days After Receipt Of The Samples, The Test Site Shall Complete Testing/evaluation And Submit Two (2) Copies Of Their Test Report With Conclusions And Recommendations To The Navicp Code Cited In Block 10.a Of The Sf33. (c) Within ;90; ; Calendar Days After The Government Receives The First Article, The Contracting Officer Shall Notify The Contractor, In Writing, Of The Approval, Conditional Approval, Or Disapproval Of The First Article. The Notice Of Approval, Conditional approval, Or Disapproval Shall Not Relieve The Contractor From Complying With All Requirements Of The Specifications And All Other Terms And Conditions Of This Contract. A Notice Of Conditional Approval Shall State Any Further Action Required Of The Contractor. a Notice Of Disapproval Shall Cite Reasons For Disapproval. (d) If The First Article Is Disapproved, The Contractor, Upon Government Request, Shall Submit An Additional First Article For Testing. After Each Request, The Contractor Shall Make Any Necessary Changes, Modifications, Or Repairs To The First Article Or select Another First Article For Testing. All Costs Related To These Tests Are To Be Borne By The Contractor, Including Any And All Costs For Additional Tests Following A Disapproval. The Contractor Shall Furnish Any Additional First Article To The government Under The Terms And Conditions And Within The Time Specified By The Government. The Government Shall Act On This First Article Within The Time Limit Specified In Paragraph (b) Above. The Government Reserves The Right To Require An Equitable adjustment Of The Contract Price For Any Extension Of The Delivery Schedule Or For Any Additional Costs To The Government Related To These Tests. (e) If The Contractor Fails To Deliver Any First Article On Time, Or The Contracting Officer Disapproves Any First Article, The Contractor Shall Be Deemed To Have Failed To Make Delivery Within The Meaning Of The Default Clause Of This Contract (f) Unless Otherwise Provided In The Contract, The Contractor - (1) May Deliver The Approved First Article As Part Of The Contract Quantity, Provided It Meets All Contract Requirements For Acceptance And Was Not Consumed Or Destroyed In Testing: And (2) Shall Remove And Dispose Of Any First Article From The Government Test Facility At The Contractors Expense. (g) If The Government Does Not Act Within The Time Specified In Paragraph (b) Or (c) Above The Contracting Officer Shall, Upon Timely Written Request From The Contractor, Equitably Adjust Under The Changes Clause Of This Contract The Delivery Or Performance dates And/or The Contract Price, And Any Other Contractual Term Affected By The Delay. (h) The Contractor Is Responsible For Providing Operating And Maintenance Instructions, Spare Parts Support, And Repair Of The First Article During Any First Article Test. (i) Before First Article Approval, The Acquisition Of Materials Or Components For, Or The Commencement Of Production Of, The Balance Of The Contract Quantity Is At The Sole Risk Of The Contractor. Before First Article Approval, The Costs Thereof Shall Not Be allocable To This Contract For (1) Progress Payments, Or (2) Termination Settlements If The Contract Is Terminated For The Convenience Of The Government (j) The Contractor Shall Produce Both The First Article And The Production Quantity At The Same Facility And Shall Submit A Certification To This Effect With Each First Article. (k) The Contractor Shall Provide Specific Written Notification To The Procuring Contracting Officer Informing Him/her Of The Shipment Of Any Article(s) Furnished In Accordance With This Clause. Such Notification Must Be Addressed To The Attention Of The navicp Code Specified In Block 10.a Of The Sf33, With Copies To Navicp Code 072 And To The Testing Activity. Failure To Provide Such Notification Shall Excuse The Government From Any Delay In Performing First Article Testing And Informing The Contractor Of the Results Thereof. (l) Fourteen (14) Days Prior To Shipment Of First Article Samples, The Contractor Shall Notify The Designated Test Facility In Writing Of The Anticipated Shipping Date, With An Information Copy To The Pco, Navicp Philadelphia, Attn: (cite Code Found In Block 10.a Of The Sf33). The Contractor Shall Also Arrange For Preliminary Inspection Of Test Samples By The Dcmc/qar. 4.8 Alternate Offers - Waiver Of First Article Approval Requirements. (the Following Provisions Supersede Any Waiver Of First Article Approval Requirements Terms Set Forth In Clause 52.209-3 Or 52.209-4 As Appropriate) (a) Unless Otherwise Specified In The Solicitation, The Naval Inventory Control Point Reserves The Right To Waive The First Article Approval Requirements Specified Herein For Offerors Who Have Previously Furnished Identical Production Articles Accepted By The government Or The Original Equipment Manufacturer/prime Manufacturer. An Offeror Requesting Waiver Of First Article Requirements Shall Submit Evidence With Its Offer Establishing That: (i) The Last Production Unit Was Delivered Within Three (3) Years Of The Issue Date Of This Solicitation, And (ii) The Production Location To Be Used For This Requirement Is The Same As Used For The Previous Production Run additionally, The Offeror Shall Submit A Certification, To Be Executed By The Officer Or Employee For The Offer, Stating That: (i) The Articles To Be Provided Will Be Produced Using The Same Facilities, Processes, Sequences Of Operations And Approved Subcontractors As Those Previously Delivered And Accepted By The Government Or The Original Equipment Manufacturer/prime Manufacturer, and (ii) The Previous Production Units Were Manufactured Without Material Review Board Disposition Or Waiver/deviation Request Or Rejection Of Pre-production Samples For Cause. (note: This Certification Concerns A Matter Within The Jurisdiction Of An Agency Of The United States And The Making Of A False, Fictitious, Or Fraudulent Certification May Render The Maker Subject To Prosecution Under Title 18, United States Code, Section 1001.) (b) Offerors Requesting Waiver Of First Article Approval Requirements Under The Provisions Of This Clause Are Cautioned To Submit Two Prices For Articles Required Herein - One That Is Based On Compliance With The First Article Approval Requirements And One that Is Based On A Waiver Of Such Requirements. Where An Offeror Submits Only One Price And Fails To Clearly State That The Price Is Based On Waiver Of The First Article Approval Requirements It Will Be Deemed To Be Based On Compliance With The First Article approval Requirements (c) In The Event Of The First Article Approval Requirement Is Granted, The Delivery Schedule For The Production Items Shall Be Reduced By The Number Of Days Designated For Delivery Of First Article Test Unit Plus The Number Of Calendar Days Indicated For The government Notification Of Conditional Approval Or Approval. These Requirements Are Specified In The Quality Assurance Section Of This Solicitation. If The Offeror Is Unable To Meet The Desired Schedule, He Shall Insert Below The Alternate Delivery Schedule he Offers To The Government. Offeror's Proposed Alternate Delivery Schedule (based On Waiver Of First Article Approval Requirements) within Days: item No. _______________ Quantity:_______ After Date Of Contract:__________ 4.9 100% Production Leak Test. Each Container, Uninstrumented And Without Dummy Load, Shall Be Raised To A Height Of 18 Inches And Allowed To Fall Freely To A Concrete Or Similarly Hard Surface, Landing Flat On Its Base. The Container Shall Then Be Prepared for Testing By Sealing All Breathing Devices And Inserting Suitable Pressurized Fittings And Gauges. The Container Shall Be Closed And Sealed In A Normal Manner. The Pneumatic-pressure Technique Of Method 5009 Of Federal Test Method Standard No. 101c Shall Be used To Detect Leakage. An Initial Pressure Setting Equal To 1.0 + 0.1 - 0 Psig Shall Be Used. After Stabilization, Pressure Shall Be Monitored For Thirty Minutes. Any Loss In Pressure In Excess Of 0.05 Psig (adjusted For Changes In Temperature And Barometric pressure) Shall Be Cause For Rejection. Warning container May Explode Or Fasteners May Fail During Test. Use Protective Barriers To Avoid Injury To Personnel. 4.10 Painting Of Container Interior Steel Surfaces. steel Surfaces (excluding Stainless Steel) Shall Be Cleaned And Pretreated For Painting In Accordance With Tt-c-490 (salt Spray Test Requirements Excluded). Paint Coating Shall Consist Of 2 Coats Of Primer In Accordance With Mil-p-53022, Mil-p-53030, Tt-p-664, or Mil-e-52891b. The Total Paint Thickness Shall Be 1.5 Mils (0.015 Inches) Minimum. To Comply With Ozone Depleting Substance Regulation, Whenever Cleaning In Accordance With Tt-c-490 Is Required, The Use Of Trichlorethylene (mil-t-81533) Is Deleted. all Costs And Responsibilities Related To The First Article Test Submission Container Shipment To And From The First Article Test Facility Are To Be Borne By The Contractor. 5. Packaging- Mil-std 2073 Packaging Applies As Found Elsewhere In The Schedule 6. Notes - Not Applicable

DEPT OF THE NAVY USA Tender

Others
Corrigendum : Closing Date Modified
United States
Closing Date21 Mar 2025
Tender AmountRefer Documents 
Description: Item Unique Identification And Valuation (jan 2023)|19|n792.06|g5k|215-697-0275|patrick.j.horan23.civ@us.navy.mil|||||||||||||||| higher-level Contract Quality Requirement|8|x|||||||| inspection And Acceptance Of Supplies|26|x||||||||||||x|||||||||||||| time Of Delivery (june 1997)|20||||||||||||||||||||| stop-work Order (aug 1989)|1|| wide Area Workflow Payment Instructions (jan 2023)|16|invoice And Receiving Report Combo Type ||tbd|n00383|tbd|tbd|see Schedule|tbd||||||||| navy Use Of Abilityone Support Contractor - Release Of Offeror Information (3-18))|1|| value Engineering (jun 2020)|3|||| equal Opportunity (sep 2016)|2||| integrity Of Unit Prices (nov 2021)|1|| warranty Of Supplies Of A Noncomplex Nature (jun 2003)|6|12 Months|60 Days After Discovery Of Defect||||| equal Opportuity For Workers With Disabilities (jun 2020)|2||| transportation Of Supplies By Sea (jan 2023)|2||| buy American-free Trade Agreements-balance Of Payments Program-basic (feb 2024)|11|||||||||||| limitation Of Liability--high-value Items (feb 1997)|1|| alternate A, Annual Representations And Certifications (nov 2023)|13|||||||||||||| buy American-free Trade Agreements-balance Of Payments Program Certificate-basic (feb 2024))|5|||||| buy American--balance Of Payments Program (feb 2024)|1|| royalty Information (apr 1984)|1|| annual Representations And Certifications (may 2024)|12|332439|600||||||||||| facsimile Proposals (oct 1997)|1|| notice Of Priority Rating For National Defense, Emergency Preparedness, Andenergy Program Use (apr 2008))|2||x| only Offers Submitted In Response To This Amendment Will Be Considered For Award. soliciation Close Date Extended To 3/21/25. \ the Government Will Award A Contract Resulting From This Solicitation To The Responsible Offeror Whose Offer Conforming To The Solicitation Will Be Most Advantageous To The Government, Price And Other Factors Considered. In Addition To Price, The Following non-price Evaluation Factor Shall Be Used To Evaluate Offers And Are Listed In Descending Order Of Importance. relevant Past Performance technical Capability the Non-price Evaluation Factors, When Combined, Are Significantly More Important Than Price. There Are No Subfactors. the Government Reserves The Right To Obtain Information For Use In The Evaluation Of Past Performance From Any And All Sources Including Sources Outside Of The Government. Offerors Lacking Relevant Past Performance History Will Not Be Evaluated Favorably Or unfavorably On Past Performance. The Government Will Consider The Quality Of An Offeror's Relevant Past Performance. This Consideration Is Separate And Distinct From The Contracting Officer's Responsibility Determination. The Assessment Of The Offeror's R relevant Past Performance Will Be Used As A Means Of Evaluating The Relative Risk Of The Offeror And Other Competitors In Successfully Meet The Requirements Of The Rfp. In Determining The Rating For The Past Performance Evaluation Factor, The Government Will Give Greater Consideration To The Contracts Which The Government Feels Are Most Relevant To The Rfp. the Government Reserves The Right To Award The Contract To Other Than The Lowest Priced Offeror. page Limitation-excluding The Cover Page, Table Of Contents, Past Performance Project Forms The Technical Capability Proposal Is Limited To Fifteen (25) Pages In At Least 11pt. Font And 1" Margins. Pages In Excess Of This Limitation Will Not Be Evaluated. The pages Excluded From Evaluation Will Be At The Discretion Of The Agency. contractors Are Informed That It Is The Government's Desire To Make Award On Initial Proposals When Deemed Possible By The Contracting Officer, However The Government Reserves The Right To Communicate And/or Negotiate With Offerors If Later Determined Necessary. none Price Proposal (all Non-price Factors) -the Contractor Is Required To Submit The Following Non-price Information: 1. Relevant Past Performance: the Contractor Is Provided An Opportunity To Demonstrate Relevant Past Performance On Contracts Currently Being Performed Or Performed Within The Past Three (3) Years. The Government Will Determine Relevance By Analyzing The Scope And Magnitude Of The Reference contracts And Comparing Them To The Instant Requirement. The Government Reserves The Right To Evaluate Submitted Projects Individually Or In The Aggregate In Order To Determine Relevance And Will Do So Consistently Across All Evaluated Offers. The Government will Consider The Quality Of The Contractor's Relevant Past Performance. reference Contracts: A. The Contractor May Submit Up To A Maximum Of Three (3) Contracts For Evaluation. The Government Reserves The Right To Obtain Information From Sources Other Than Those Identified By The Contractor. 2. Technical Capability the Government Desires That Offerors Demonstrate Technical Capability To Satisfy The Government's Requirements. The Offeror's Response Will Be Evaluated To Determine Whether Its Response Poses Risk To Performance Or Whether It Will Result In Better Value To The government. In Response To This Evaluation Factor, Offerors Shall Address Its Manufacturing Equipment; Inspection Method Sheets; Incoming Inspection Sheets; Process Sheets; Quality System Compliance; Welding Certification. in Responding To The Above Areas Of The Technical Capability Factor, It Is Incumbent Upon The Offeror Provide A Level Of Detail The Demonstrates To The Government's Satisfaction That The Offeror Has The Technical Capability To Perform The Requirement. If The proposal Lacks Sufficient Detail, It May Result In The Government Assessing Risk In The Proposal. While There Is No Prescribed Method For Demonstrating Technical Capability, The Below Are Items Of Interest To The Government That The Contractor May, At Its discretion, Address To Assist The Government In Gaining An Understanding Of The Offerors Technical Capability. Offerors Are Cautioned That While These Areas Of Interest Are Not Mandatory Elements That Are Required To Be Addressed, Failure To Address Them Or comparable Indicia Of Technical Capability, May Limit The Government's Understanding Of Technical Risk And Result In The Assignment Of Commensurate Risk. Offerors Are Also Notified That Some Of These Indicia Of Capability Are Overlapping, I.e., Two Or More May evidence The Same Facet Of Capability. certification Of Possession Or Access To The Following Equipment:for Aluminum And Steel Welded Containers, & Bladebox/riveted Construction 1.brake Press 2.extrusion Dies 3.cnc Machining Center(s) Capable Of Lathe And/or Milling Operations copies Of Inspection Method Sheets Used In-process And/or At Final Inspection copies Of Incoming Inspection Documents That Show Material Certificates Of Conformance, And If Applicable, Dimensional Conformance process/operation Sheets To Show Ability To Conform To Drawing Requirements In The Following Areas: Weld Preparation; Welding Procedure Specifications Production Lot Testing proof Of Compliance To Iso9001, And/or, As9100. applicable Up-to-date Welder Certifications Showing Highest-level Certification Obtained Aws D1.1 For Steel, Aws D1.2 Or Mil-w-22248,class 4 For Aluminum, Aws D1.3 For Sheet Steel And Aws D1.6 For Stainless Steel. if The Offeror Address Any Or All Of The Above, Or Provides Comparable Indicia Of Capability, It Is Encouraged To Provide Supporting Evidence And Detail, Such As But Not Limited To Receipts, Certifications, Drawings, Test Results/ Logs, Maintenance Records, calibration Records, Inspection Reports, Audits, Etc. The Weigh Accorded To Supporting Evidence Will Be At The Discretion Of The Government. the Technical Capability Proposals Will Be Evaluated To Determine The Risk Of Unsuccessful Performance As Well As Relative Risk Compared To Other Offerors. all Contractual Documents (i.e. Contracts, Purchase Orders, Task Ordersdelivery Orders And Modifications) Related To The Instant Procurement Are Considered To Be "issued" By The Government When Copies Are Either Deposited In The Mail, Transmitted By Facsimile, Or sent By Other Electronic Commerce Methods, Such As Email. The Government's Acceptance Of The Contractor's Proposal Constitutes Bilateral Agreement To "issue" Contractual Documents As Detailed Herein. early And Incremental Deliveries Accepted And Preferred. \ 1. Scope 1.1 Due To The Critical Use Of This Item And Its Quality History, A Pre-award Survey And Post-award Conference May Be Required For All New Manufacturers. For All Previous Sources, A Post-award Conference May Be Recommended. 1.2 Container Shell Material Is ;polyethylene; . 1.3 Manufacturing Process Is ;rotomolded; . 1.4 Articles To Be Furnished Hereunder Shall Be Manufactured, Tested And Inspected In Accordance With ;container Research Corporation; Drawing Number ( ;05259; ) ;434e001; , Revision ;latest; And All Details And Specifications Referenced Therein. 1.5 Unless Expressly Provided For Elsewhere In This Clause, Equipment Such As Fixtures, Jigs, Dies, Patterns, Mylars, Special Tooling, Test Equipment, Or Any Other Manufacturing Aid Required For The Manufacture And/or Testing Of The Subject Item(s) Will Not Be provided By The Government Or Any Other Source And Is The Sole Responsibility Of The Contractor. The Foregoing Applies Notwithstanding Any Reference To Such Equipment Or The Furnishing Thereof That May Be Contained In Any Drawing Or Referenced Specification. 1.6 If Mil-std-454 Is Referenced In The Drawings Or In The Specification, The Contractor Is Expected To Show Compliance With Ipc/eiaj-std-001c. 1.7 When Discrepancies Exist Between These Requirements And Those On Current manufacturer's Drawings,contact Code ;buyer Found On Page 1 Of The Contract; Or Code N241.10 2. Applicable Documents drawing Data=std-245 |05259| | |d| | | | drawing Data=std-314 |05259| | |d| | | | drawing Data=15930 |80132| | |a| | | | drawing Data=434b003 |05259| | |d| | | | drawing Data=434d002 |05259| | |d| | | | drawing Data=434e001 |05259| A| |d| | | | drawing Data=434e001 Dl |05259| | |d| | | | drawing Data=434e004 |05259| | |d| | | | 3. Requirements 3.1 One Third (1/3) Unit Of Desiccant (mil-d-3464, Type Ii Nondusting) Per Cubic Foot Of Container Interior Volume Shall Be Placed In Desiccant Holder Of Each Container At Time Of Shipment. 3.2 Reference To Cadmium Plating Shall Be Deleted And The Following Substituted: "finish Shall Be Electrodeposited Alkaline Zinc-nickel Alloy In Accordance With Astm B 841 Class 1, Type B, Grade 3." all Containers Must Be Affixed With A Nameplate That Includes A unique Identification (uid) Marking As Referenced In The Drawing Package drawing ;(80132) 15930; And Iaw Mil-std-130 Latest Revision. The Contractor shall Contact Navicp Code ;buyer On Page 1 Of The Contract; Or Code 0771.10 For The Alphanumeric sequential Serial Number Group That Makes Up Part Of The Uid. the Uidwill Be Included On The Nameplate In Data Matrix Format. when A First Article Is Required, The Contractor Shall Submit A Paper Copy Of The Drawings (size 11" X 17"), Contracts And Approved Ecp's Eco's, Deviations Waivers, And Modifications In The Records Recepticle Or Inside The Container Submitted For The First article. contact Code ;buyer On Page One; Or Code N241.10 To Arrange For First Article Test Location 4. Quality Assurance 4.1 100% Production Leak Tests. Each Container Shall Be Prepared For Testing By Sealing All Breathing Devices And Inserting Pressurizing Fittings And Gauges. The Container Shall Be Closed And Sealed In A Normal Manner. The Pneumatic - Pressure Technique Of method 5009 Of Federal Test Method Standard No. 101c Shall Be Used To Detect Leakage. An Initial Pressure Setting Equal To 0.5 + 0.1-0 Psig Shall Be Used. After Stabilization, Pressure Shall Be Monitored For Thirty Minutes. Any Loss In Pressure In Excess Of 0.05 Psig (adjusted For Changes In Temperature And Barometric Pressure) Shall Be Cause For Rejection. Any Deformation Of The Container Shell, While Pressurized, Which Is Greater Than Three Quarters Of An Inch Beyond Its Point At Ambient Pressure Shall Also Be cause For Rejection. Warning container May Explode Or Fasteners May Fail During This Test. Use Protective Barriers To Avoid Injury To Personnel. 100% Production Leak Tests. Each Container Shall Be Prepared For Testing By Sealing All Breathing Devices And Inserting Pressurizing Fittings And Gauges. The Container Shall Be Closed And Sealed In A Normal Manner. The Pneumatic - Pressure Technique of Method 5009 Of Federal Test Method Standard No. 101c Shall Be Used To Detect Leakage. An Initial Pressure Setting Equal To 0.55 + 0.1-0 Psig Shall Be Used. After Stabilization, Pressure Shall Be Monitored For Thirty Minutes. Any Loss In Pressure In Excess of 0.025 Psig (adjusted For Changes In Temperature And Barometric Pressure) Shall Be Cause For Rejection. Any Deformation Of The Container Shell, While Pressurized, Which Is Greater Than Three Quarters Of An Inch Beyond Its Point At Ambient Pressure Shall Also be Cause For Rejection. welding And Welder Qualifications Shall Meet Current Aws D1.2 Standards. Additionally, Cleaning Preparations Shall Be In Accordance With Mil-c-5541 And The Cleaning Paragraph Located In The Welding Requirements Section Of The Contract. 4.2 The Tests To Be Performed Under The First Article Approval Clause (far 52.209-4) Of The Contract Are Listed Below. 4.2.1 Dimensional Test (special) ;to Drawing (05259) 434e001 And Sub-drawings Is Applicable; 4.2.2 Requirements Of: ;to Drawing (05259) 434e001 And Sub-drawings Are Applicable.; 4.2.3 Form: ;applies; 4.2.4 Fit: ;applies; 4.2.5 Function ;applies; 4.2.6 Compliance With Drawing ( ;05259; ) ;434e001; , Revision ;latest; And Specifications Referenced Therein. 4.3 In Addition To The Above Tests, The First Article(s) To Be Delivered Hereunder Shall Also Be Subjected To Those Tests Which Will Demonstrate That The Article(s) Comply With Contract Requirements Requirements. 4.4 The Contractor Shall Be Responsible For Providing The Necessary Parts And Repair Of The First Article Sample(s) During Testing. 4.5 The Cost Of The Government Testing Effort Set Forth In This Solicitation Is Estimated To Be $ ;12000; For The First Article Testing. This Cost Factor Will Be Added, For Solicitation Purposes, To The Price Of All Offerors For Whom The Government Will require Such Testing. 4.6 Disposition Of Fat Samples 4.6.1 ;zero; Sample(s) Shall Not Be Returned To The Contractor Because They Shall Be Destroyed During Testing. 4.6.2 ;all; Unless Otherwise Provided For In The Contract, Sample(s) Shall Be Returned To The Contractor And May Be Considered As Production Items Under The Contract Provided The Sample(s) Can Be Refurbished To Ready For Issue Condition And Provided The sample(s) Have Inspection Approval From The Cognizant Dcmc Qar. Sample(s) May Be Shipped As Production Items Only After All Other Units Required Under The Contract Have Been Produced And Are Ready For Shipment. ;n/a; Sample(s) Shall Be Returned To The Contractor But Shall Not Be Considered As Production Due. 4.7 Test Sample Coating Instructions 4.7.1 Samples Are To Be Unpainted. Corrosive Areas Are To Be Coated With A Light Preservative. 4.8 Fat Approval Criteria 4.8.1 Far 52.209-4 Applies (a) The Contractors Shall Deliver ;one (1); ; Unit(s) Of The Following Cage ( ;05259; ; ) Part Number ;434e001; ; , Revision ;latest; ; Within ;90; ; Calendar Days From The Date Of This Contract To The Government At ;contact Buyer On Page 1 nswc Indian Head Division, Detachment Picatinny; ; marking Of Test Sample(s) Shipping Container Shall Be As Follows, Citing This Contract Number: "for First Article Testing. Not Rfi Material. Do Not Take Up In Stock Contract Number:____________" for First Article Test, The Shipping Documentation Shall Contain This Contract Number And Lot/item Identification. The Characteristics That The First Article Must Meet And The Testing Requirements Are Specified Elsewhere In This Contract. (b) Upon Shipment Of First Article Sample(s), Two (2) Copies Of The Material Inspection And Receiving Report (dd Form 250) Bearing The Qar's Signature And Indication Of Preliminary Inspection Shall Be Forwarded To The Navicp- Philadelphia Code Cited In Block 10.a Of Sf33, With Duplicate Copies To Navicp Code 072 And To The Designated Test Facility. The Envelopes Shall Be Clearly Marked: "do Not Open In Mail Room". within ;60; ; Days After Receipt Of The Samples, The Test Site Shall Complete Testing/evaluation And Submit Two (2) Copies Of Their Test Report With Conclusions And Recommendations To The Navicp Code Cited In Block 10.a Of The Sf33. (c) Within ;120; ; Calendar Days After The Government Receives The First Article, The Contracting Officer Shall Notify The Contractor, In Writing, Of The Approval, Conditional Approval, Or Disapproval Of The First Article. The Notice Of Approval, Conditional approval, Or Disapproval Shall Not Relieve The Contractor From Complying With All Requirements Of The Specifications And All Other Terms And Conditions Of This Contract. A Notice Of Conditional Approval Shall State Any Further Action Required Of The Contractor. a Notice Of Disapproval Shall Cite Reasons For Disapproval. (d) If The First Article Is Disapproved, The Contractor, Upon Government Request, Shall Submit An Additional First Article For Testing. After Each Request, The Contractor Shall Make Any Necessary Changes, Modifications, Or Repairs To The First Article Or select Another First Article For Testing. All Costs Related To These Tests Are To Be Borne By The Contractor, Including Any And All Costs For Additional Tests Following A Disapproval. The Contractor Shall Furnish Any Additional First Article To The government Under The Terms And Conditions And Within The Time Specified By The Government. The Government Shall Act On This First Article Within The Time Limit Specified In Paragraph (b) Above. The Government Reserves The Right To Require An Equitable adjustment Of The Contract Price For Any Extension Of The Delivery Schedule Or For Any Additional Costs To The Government Related To These Tests. (e) If The Contractor Fails To Deliver Any First Article On Time, Or The Contracting Officer Disapproves Any First Article, The Contractor Shall Be Deemed To Have Failed To Make Delivery Within The Meaning Of The Default Clause Of This Contract (f) Unless Otherwise Provided In The Contract, The Contractor - (1) May Deliver The Approved First Article As Part Of The Contract Quantity, Provided It Meets All Contract Requirements For Acceptance And Was Not Consumed Or Destroyed In Testing: And (2) Shall Remove And Dispose Of Any First Article From The Government Test Facility At The Contractors Expense. (g) If The Government Does Not Act Within The Time Specified In Paragraph (b) Or (c) Above The Contracting Officer Shall, Upon Timely Written Request From The Contractor, Equitably Adjust Under The Changes Clause Of This Contract The Delivery Or Performance dates And/or The Contract Price, And Any Other Contractual Term Affected By The Delay. (h) The Contractor Is Responsible For Providing Operating And Maintenance Instructions, Spare Parts Support, And Repair Of The First Article During Any First Article Test. (i) Before First Article Approval, The Acquisition Of Materials Or Components For, Or The Commencement Of Production Of, The Balance Of The Contract Quantity Is At The Sole Risk Of The Contractor. Before First Article Approval, The Costs Thereof Shall Not Be allocable To This Contract For (1) Progress Payments, Or (2) Termination Settlements If The Contract Is Terminated For The Convenience Of The Government (j) The Contractor Shall Produce Both The First Article And The Production Quantity At The Same Facility And Shall Submit A Certification To This Effect With Each First Article. (k) The Contractor Shall Provide Specific Written Notification To The Procuring Contracting Officer Informing Him/her Of The Shipment Of Any Article(s) Furnished In Accordance With This Clause. Such Notification Must Be Addressed To The Attention Of The navicp Code Specified In Block 10.a Of The Sf33, With Copies To Navicp Code 072 And To The Testing Activity. Failure To Provide Such Notification Shall Excuse The Government From Any Delay In Performing First Article Testing And Informing The Contractor Of the Results Thereof. (l) Fourteen (14) Days Prior To Shipment Of First Article Samples, The Contractor Shall Notify The Designated Test Facility In Writing Of The Anticipated Shipping Date, With An Information Copy To The Pco, Navicp Philadelphia, Attn: (cite Code Found In Block 10.a Of The Sf33). The Contractor Shall Also Arrange For Preliminary Inspection Of Test Samples By The Dcmc/qar. 4.9 Alternate Offers - Waiver Of First Article Approval Requirements. (the Following Provisions Supersede Any Waiver Of First Article Approval Requirements Terms Set Forth In Clause 52.209-3 Or 52.209-4 As Appropriate) (a) Unless Otherwise Specified In The Solicitation, The Naval Inventory Control Point Reserves The Right To Waive The First Article Approval Requirements Specified Herein For Offerors Who Have Previously Furnished Identical Production Articles Accepted By The government Or The Original Equipment Manufacturer/prime Manufacturer. An Offeror Requesting Waiver Of First Article Requirements Shall Submit Evidence With Its Offer Establishing That: (i) The Last Production Unit Was Delivered Within Three (3) Years Of The Issue Date Of This Solicitation, And (ii) The Production Location To Be Used For This Requirement Is The Same As Used For The Previous Production Run additionally, The Offeror Shall Submit A Certification, To Be Executed By The Officer Or Employee For The Offer, Stating That: (i) The Articles To Be Provided Will Be Produced Using The Same Facilities, Processes, Sequences Of Operations And Approved Subcontractors As Those Previously Delivered And Accepted By The Government Or The Original Equipment Manufacturer/prime Manufacturer, and (ii) The Previous Production Units Were Manufactured Without Material Review Board Disposition Or Waiver/deviation Request Or Rejection Of Pre-production Samples For Cause. (note: This Certification Concerns A Matter Within The Jurisdiction Of An Agency Of The United States And The Making Of A False, Fictitious, Or Fraudulent Certification May Render The Maker Subject To Prosecution Under Title 18, United States Code, Section 1001.) (b) Offerors Requesting Waiver Of First Article Approval Requirements Under The Provisions Of This Clause Are Cautioned To Submit Two Prices For Articles Required Herein - One That Is Based On Compliance With The First Article Approval Requirements And One that Is Based On A Waiver Of Such Requirements. Where An Offeror Submits Only One Price And Fails To Clearly State That The Price Is Based On Waiver Of The First Article Approval Requirements It Will Be Deemed To Be Based On Compliance With The First Article approval Requirements (c) In The Event Of The First Article Approval Requirement Is Granted, The Delivery Schedule For The Production Items Shall Be Reduced By The Number Of Days Designated For Delivery Of First Article Test Unit Plus The Number Of Calendar Days Indicated For The government Notification Of Conditional Approval Or Approval. These Requirements Are Specified In The Quality Assurance Section Of This Solicitation. If The Offeror Is Unable To Meet The Desired Schedule, He Shall Insert Below The Alternate Delivery Schedule he Offers To The Government. Offeror's Proposed Alternate Delivery Schedule (based On Waiver Of First Article Approval Requirements) within Days: item No. _______________ Quantity:_______ After Date Of Contract:__________ 4.10 100% Production Leak Test. Each Container Shall Be Prepared For Testing By Sealing All Breathing Devices And Inserting Suitable Pressurized Fittings And Gauges. The Container Shall Be Closed And Sealed In A Normal Manner. Each Container, Uninstrumented and Without Dummy Load, Shall Then Be Subjected To A Single 18 Inch Flat Drop. The Pneumatic-pressure Technique Of Method 5008 Of Federal Test Method Standard No. 101c Shall Be Used To Detect Leakage. An Initial Setting Equal To 0.5 + 0.1 - 0 Psig Shall Be used. After Stabilization, Pressure Shall Be Monitored For Thirty Minutes. Any Loss In Pressure Over A 30 Minute Period That Exceeds 25% Of The Stabilized Pressure Shall Be Cause For Rejection; Tests Shall Be Conducted To Ascertain Sources Of Leaks and Corrective Action Taken. Any Deformation Of The Container Shell While Pressurized Which Is Greater Than Three-quarters Of An Inch Beyond Its Point At Ambient Pressure Shall Also Be Cause For Rejection. Warning container May Explode Or Fasteners May Fail During Test. Use Protective Barriers To Avoid Injury To Personnel. sampling Per Ansi/asq Z1.4, Sample Plan S-2aql 1.0 (13 Pcs) accept 0, Reject 1.one (1) Rejection Will Require 100% Of The Shipment To Be Tested. A Lot Shall Consist Of Any Scheduled Shipment Quantity Under Contract. Representative Sampling Shall Be Used, I.e. The Samples Are To Be Selected At Random Throughout The lot.remove Either The Vortex Or Breather Valve And install A Suitable Airtight Fitting.draw A Vacuum On The Sample Container(s) To .025+/- 0.01 Psig.stabilize Vacuum Within Tolerance For A Minimum Of 15 Minutes, Then Disconnect The Vacuum Input And Test Monitor The Container For 15 Minutes.the Vacuum Should hold Within +/- 0.05 Psig At The End Of The 15 Minutes For The Container To Pass. testing Specifications For Cases: drop Test:fed-std-101c. Method 5007.1 Paragraph 6.3,procedure -a- Level -a-. procedure A Falling Dart Impact: Ata 300, Category I,general Requirements for Category I & Ii Reusable Containers Vibration (loose Cargo): fed-std-101c, Method Of 5019 Vibration (sweep):ata300, (jan 15th/96),which States In Appendix Ii, B4 Simulated Method 506.4, Procedure Ii Of 4.1.2 fed-std-101c Method 5009.1, Section 6.7.1. all Costs And Responsibilities Related To The First Article Test Submission Container Shipment To And From The First Article Test Facility Are To Be Borne By The Contractor 5. Packaging- Mil-std 2073 Packaging Applies As Found Elsewhere In The Schedule 6. Notes - Not Applicable block 9: Statement B, Us Government, Naval Inventory Control Point block 14: When Navicp 02 Is Referenced In Distribution, Forward To The Navicp Code Cited On Block 10.a. On Page 1. block 3: Separate Reports Shall Be Provided For The Below Listed Subtitles And Shall Include Certification That All Vendors Performing These Processes Are Prime (oem) Approved Sources. In The Case Where Other Than The Oem's Specifications Are To Be Utilized, separate Certifications Are Required. block 12: First Submission To Be Made Upon Submission Of ;one; Testing Sample. ^ Block 14: Make Submission To ;code N241.15; .
1361-1370 of 1720 active Tenders