Fire Tenders

Fire Tenders

BARANGAY OCANA CARCAR, CEBU Tender

Civil And Construction...+1Civil Works Others
Philippines
Closing Soon11 Nov 2024
Tender AmountPHP 715 K (USD 12.2 K)
Details: Description I. General Requirements & Preliminaries 1 Design & Engineering 1 Lot N/a 2 Mobilization, Demobilization & Waste Disposal 1 Lot 7,500.00 3 Temporary Facilities 1 Lot 5,000.00 4 Temporary Water & Electrical Connection 1 Lot 4,000.00 5 Personal Protective Equipment (ppe) 1 Lot 6,000.00 Subtotal - I 22,500.00 Ii. Site Preparation & Earthworks 1 Site Clearing, Staking & Lay-outing 1 Lot 3,000.00 3,000.00 2 Excavation Of Column Foundation (1.0x0.8x0.6m) X 8 3.84 Cu.m. 600.00 2,304.00 3 Excavatiion Of Wall Footing (0.4x0.6x22.66m) 5.44 Cu.m. 600.00 3,264.00 4 Backfill & Compaction 4.64 Cu.m. 300.00 1,392.00 Subtotal - Ii 9,960.00 Iii. Concreting Works Iii.1. Column Foundation X 8 Columns = 0.96 Cu.m. 1 Portland Cement 9 Bags 280.00 2,520.00 2 Washed Sand 0.5 Cu.m. 2,200.00 1,100.00 3 Gravel, 3/4" 1 Cu.m. 2,200.00 2,200.00 Iii.2. Wall Footing = 1.81 Cu.m. 1 Portland Cement 17 Bags 280.00 4,760.00 2 Washed Sand 1 Cu.m. 2,200.00 2,200.00 3 Gravel, 3/4" 1.9 Cu.m. 2,200.00 4,180.00 Iii.3 Columns (8 Sets) = 2.54 Cu.m. 1 Portland Cement 23 Bags 280.00 6,440.00 2 Washed Sand 1.3 Cu.m. 2,200.00 2,860.00 3 Gravel, 3/4" 2.6 Cu.m. 2,200.00 5,720.00 Iii.4. Flooring = 10.75 Sq.m. X 0.1m Thk. = 1.075 Cu.m. 1 Portland Cement 9 Bags 280.00 2,520.00 2 Washed Sand 0.6 Cu.m. 2,200.00 1,320.00 3 Gravel, 3/4" 1.1 Cu.m. 2,200.00 2,420.00 Iii.5. Roof Slab - Beams = 1.36 Cu.m. 1 Portland Cement 13 Bags 280.00 3,640.00 2 Washed Sand 0.7 Cu.m. 2,200.00 1,540.00 3 Gravel, 3/4" 1.4 Cu.m. 2,200.00 3,080.00 Iii.6. Roof Deck Slab = 5.1 Cu.m. 1 Portland Cement 13 Bags 280.00 3,640.00 2 Washed Sand 0.7 Cu.m. 2,200.00 1,540.00 3 Gravel, 3/4" 1.4 Cu.m. 2,200.00 3,080.00 Iii.7. Staircasee (14 Steps) = 1.18 Cu.m. 1 Portland Cement = 5.1 Cu.m. 11 Bags 280.00 3,080.00 2 Washed Sand 0.6 Cu.m. 2,200.00 1,320.00 3 Gravel, 3/4" 1.2 Cu.m. 2,200.00 2,640.00 Subtotal - Iii 61,800.00 Item No. Item Description / Particulars Qty. Unit Material Amount Unit Cost Iv. Masonry Works 1 Chb, 6" 600 Pcs 25.00 15,000.00 2 Chb, 4" 380 Pcs 18.00 6,840.00 3 Masonry Cement 90 Bags 200.00 18,000.00 4 Fine Sand 6.7 Cu.m. 2,200.00 14,740.00 5 Def. Steel Bar, 10mm Dia. 48 Lengths 180.00 8,640.00 6 G.i. Tie Wire #16 3 Kgs 90.00 270.00 7 Grill Station Fab'n. & Fire Bricks Laying (bricks-ex-stock) 1 Lot 5,000.00 5,000.00 Subtotal - Iv 68,490.00 V. Concrete Reinforcement Steel Bars V.1. Column Foundation 1 Def. Steel Bar, 12mm Dia. 12 Lengths 280.00 3,360.00 2 G.i. Tie Wire #16 3 Kgs 90.00 270.00 V.2. Wall Footing 1 Def. Steel Bar, 12mm Dia. 3 Lengths 280.00 840.00 2 Def. Steel Bar, 10mm Dia. 8 Lengths 180.00 1,440.00 3 G.i. Tie Wire #16 2 Kgs 90.00 180.00 V.3. Roof Slab - Beams 1 Def. Steel Bar, 12mm Dia. 16 Lengths 280.00 4,480.00 2 Def. Steel Bar, 10mm Dia. 19 Lengths 180.00 3,420.00 3 G.i. Tie Wire #16 2 Kgs 90.00 180.00 V.4. Columns 1 Def. Steel Bar, 12mm Dia. 64 Lengths 280.00 17,920.00 2 Def. Steel Bar, 10mm Dia. 46 Lengths 180.00 8,280.00 3 G.i. Tie Wire #16 7 Kgs 90.00 630.00 V.5. Staircase 1 Def. Steel Bar, 12mm Dia. 8 Lengths 280.00 2,240.00 2 Def. Steel Bar, 10mm Dia. 14 Lengths 180.00 2,520.00 3 G.i. Tie Wire #16 2 Kgs 90.00 180.00 Subtotal - V 45,940.00 Vi. Formworks & Scaffolding 1 Phenolic Board, 3/4" Thick 18 Sheets 1,200.00 21,600.00 2 Coco Lumber, 3" X 2" X 8' 96 Lengths 140.00 13,440.00 3 Coco Lumber, 2" X 2" X 8' 60 Lengths 95.00 5,700.00 4 Common Wire Nails #4 7 Kgs 90.00 630.00 5 Common Wire Nails #2 4 Kgs 90.00 360.00 Subtotal - Vi 41,730.00 Vii. Carpentry & Architectural Finishes Vii.1. Carpentry Works 1 Toilet Pvc Door, 0.6m W C/w Keyless Lockset 4 Sets 4,000.00 16,000.00 Vii.2. Floor Tiling Works 1 Tiles, 30x30 Cm, Matt Type (ground Floor & Staircase) 282 Pcs 60.00 16,920.00 2 Tiles, 60x60 Cm, Matt Type (roof Deck) 90 Pcs 185.00 16,650.00 3 Masonry Cement 16 Bags 200.00 3,200.00 4 Tile Adhesive 2 Bags 350.00 700.00 5 Fine Sand 1.35 Cu.m 2,200.00 2,970.00 6 Tile Grout 7 Kgs 80.00 560.00 Vii.3. Painting 1 Skimcoat 3 Bags 500.00 1,500.00 2 Water Based Primer 2 Gals 680.00 1,360.00 3 Elastomeric Top Coat Paint 2 Gals 800.00 1,600.00 4 Paint Tray, 7" 1 Pc 90.00 90.00 5 Roller Brush, 7" 1 Pc 120.00 120.00 6 Roller Brush Cotton Refill, 7" 1 Pc 65.00 65.00 7 Paint Brush, 1 1/2" 2 Pcs 40.00 80.00 Subtotal - G 61,815.00 Viii Steel Works (staircase & Roofdeck Rails 1 Stainless Steel Pipe, 2" Dia., Gr. 304, 1.5mm Thick 10 Lengths 3,036.00 30,360.00 2 Stainless Steel Pipe, 1" Dia., Gr. 304, 1.5mm Thick 18 Lengths 1,440.00 25,920.00 3 Welding Rod, Stainless Steel 10 Kgs 525.00 5,250.00 4 Buffing Tools & Consumables 1 Lot 3,000.00 3,000.00 Subtotal - Viii 64,530.00 Ix Tinsmithry 1 Exhaust Hood & Ducting Works 1 Lot 4,000.00 4,000.00 Subtotal - Ix 4,000.00 Item No. Item Description / Particulars Qty. Unit Material Amount Unit Cost X Plumbing Works & Fixtures X.1. Plumbing Works 1 Pe Pipe & Fittings From Water Source 1 Lot 1,500.00 1,500.00 2 Ppr Pipe, Pn 20, 1/2" Dia. X 4m L 8 Lengths 250.00 2,000.00 2 Ppr Elbow, 1/2" Dia. 12 Pcs 15.00 180.00 3 Ppr Coupling, 1/2" Dia. 4 Pcs 10.00 40.00 4 Ppr Tee, 1/2" Dia. 6 Pcs 15.00 90.00 5 Ppr Threaded Elbow, 1/2" Dia. 6 Pcs 80.00 480.00 6 Ppr Threaded Tee, 1/2" Dia. 6 Pcs 80.00 480.00 7 Teflon Tape, 1/2" 1 Roll 60.00 60.00 8 Faucet 3 Pcs 200.00 600.00 X.2. Fixtures 1 Telephone Shower Complete With Accessories 2 Sets 3,000.00 6,000.00 2 Water Closet Complete With Accessories 2 Sets 6,500.00 13,000.00 3 Lavatory With Stand & Accessories 2 Sets 5,000.00 10,000.00 4 Urinal Complete With Accessories 1 Set 3,000.00 3,000.00 Subtotal - X 37,430.00 Xi Electrical Works 1 Panel Board, 4-branches W/ Circuit Breakers As Follows: 1 Assy 3,500.00 3,500.00 Main : 30a, Lighting : 15a & Spare : 20a 2 Thhn Wire 5.5 Mm Sq. 30 M 42.00 1,260.00 3 Thhn Wire 3.5 Mm Sq. 10 M 30.00 300.00 4 Thhn Wire 2.0 Mm Sq. 50 M 18.00 900.00 5 1-gang Switch 3 Pcs 100.00 300.00 6 2-gang Switch 2 Pcs 190.00 380.00 7 Concealed Led Pinlight, 5w 3 Sets 550.00 1,650.00 8 Concealed Led Pinlight, 7w 1 Sets 600.00 600.00 9 Wall Lamp, 7w 1 Set 1,000.00 1,000.00 10 Wall Lamp, 9w 2 Sets 1,200.00 2,400.00 11 Pvc Pipe, 1/2" Dia. 8 Lengths 85.00 680.00 12 Pvc Elbow, 1/2" Dia. 16 Pcs 20.00 320.00 13 Electrical Tape 2 Rolls 60.00 120.00 14 Junction Box With Cover 3 Pcs 40.00 120.00 15 Utility Box 7 Pcs 30.00 210.00 Subtotal - Xi 13,740.00 Summary Of Costs: A. General Requirements & Preliminaries Item I 22,500.00 B. Material Cost Sum Of Ii To Xi 409,435.00 C. Labor Cost 30% Of B 122,830.50 D. Direct Cost A + B + C 554,765.50 E. Overhead, Contingencies & Miscellaneous 5% Of D 27,738.28 F. Contractor's Profit 10% Of D 55,476.55 G. Value Added Tax (vat) 12% Of (d +e + F) 76,557.64 Total Estimated Project Cost (d + E + F + G) ₱714,537.96

Philippine National Oil Company - PNOC Tender

Energy, Oil and Gas...+2Electrical Goods and Equipments, Electrical and Electronics
Corrigendum : Closing Date Modified
Philippines
Closing Soon12 Nov 2024
Tender AmountPHP 2.8 Million (USD 48 K)
Details: Description Terms Of Reference Procurement For The Supply, Delivery, Installation, Commissioning, Testing, And Operational Demonstration Of Electric Vehicle Charging Station (evcs) - Fast/rapid 1. Background In 2023, Bataan’s Provincial Government Launched The Green Mobility Program As Part Of Project Transform Of The Department Of Environment And Natural Resources (denr) In The Province. As Part Of This Initiative, Six Electric Vehicles (e-vehicles) Were Blessed And Turned Over To The Metro Bataan Development Authority (mbda) And Provincial Disaster Risk Reduction And Management Office (pdrrmo). In Furtherance Of Its Commitment In Promoting Sustainable Development And Environmental Protection, The Provincial Government Of Bataan (pgb) Aims To Install A 80kw Fast-charging Station At The Bataan Tourism Center In Balanga. This Initiative Also Supports The Electric Vehicle Industry Development Act (evida), And The Green Energy Management Program (gemp) Of The National Government. Currently, There Are Six Electric Vehicles Acquired By The Province For Patrol Services And The Provision Of Services To The People. These Vehicles Include Four (4) Volkswagen Id6 Cruzz Long Range Pro Versions; And Two (2) Byd Dolphin Models. There Are Plans Of Procuring Additional Four (4) Evs For The Sangguniang Bayan Office And Mbda In May 2024. The Bataan Provincial Government Is Currently Using Slow Charging Stations For Their Electric Vehicle (ev) Fleet, Requiring A Full Night To Charge Each Vehicle. Data Indicates That Evs Are More Economical Than Traditional Fuel-powered Vehicles. However, For Enhanced Efficiency And Time-saving, Particularly For Evs Deployed In Patrol And Emergency Response Roles Throughout The Province, There Is A Pressing Need To Upgrade To Fast Charging Infrastructure. The Installation Of A Fast-charging Station At The Bataan Tourism Center Will Address The Range Anxiety Of Ev Users, And Will Promote The Adoption Of Electric Vehicles. Bataan, As Our Industrial Park Host Province, Plays A Crucial Role In Our Current And Future Business Operations. The Cooperation Of Bataan Is Essential Not Only For Our Existing Business But Also For The New And Renewable Energy Resource Development Projects That Pnoc Will Be Embarking On In The Province. Pnoc Would Like To Showcase Its Commitment To Corporate Social Responsibility By Supporting The Necessary Infrastructure For These Electric Vehicles, Including The Charging Equipment, Infrastructure Support, Canopy, Signage, Cabling, And Network Connection. 2. Objectives 1. To Support The Adoption Of Electric Vehicles In Bataan By Providing An Express Charging Infrastructure. 2. To Reduce Carbon Emissions And Improve Air Quality In The Province. 3. To Promote Sustainable Development And Environmental Stewardship In Line With National And Local Government Policies. 3. Technical Specifications Item Qty. Unit Approved Budget Contract (abc) Mode 4, 80 Kw Evcs, Including 2 Spare Charging Cables 1 Unit Php 2.8 Million Specifications Mode 4 Evcs, 80kw (dc) General A. Rated Power 80 Kw Or Higher B. Number Of User Terminal One (1) For Each Electric Charging System C. Display Language English D. Charging Interface Ccs Combo 2 And Gb/t Dc E. Number Of Charging Gun And Cable Two (2) Charging Gun And Cables Other Requirements For The Evcs: General A. Casing Anti-corrosion Painted Steel Or Equivalent B. Minimum Ingress Protection Ip54 C. Charging Cable Minimum Length 5 Meters D. Connectivity Capable Of Connecting To The Internet E. Communication Protocol Open Charge Point Protocol (ocpp) 1.6 Or Equivalent Protective Function Overcurrent Protection, Surge Protection, Ground Fault Detection, Leakage Detection Equipped On/off Switch Equipped Emergency Stop Button Equipped Cabling A) Length Of Cable From Panelco Transformer To The Service Entrance Up To The Charger Is 50 To 70 Meters. The Electrical Cable Must Be Compatible With And Can Support The Electrical Load Requirement. B) The Cabling To The Charger Must Be Underground Installation Installation Including Civil Works And Electrical Works Necessary To Install All Equipment And Chargers; As Applicable. Includes Separate Circuit Breaker; Canopy And Signage Materials And Network Connection Equipment. Documents / User’s Manual Instruction Manual For Operation And Maintenance In English Evcs And Location The Delivery And Installation Site Shall Be At The Bataan Tourism Center, Balanga, Province Of Bataan Training And Awareness Two-day (2) Training For Selected Pnoc And Pgb Personnel Who Will Handle The Operation Of The Evcs Including Operation, Troubleshooting, And Preventive Maintenance Of The Evcs. 4. Scope Of Works By The Winning Bidder ● Conduct A Kick-off/inception Meeting For The Installation Of The Chargers Before The Commencement Of The Installation And Set-up Service. ● Prepare Plans/blueprint And Layout Of The Evcs Infrastructure. The Said Documents Shall Be Reviewed By The End-user For Approval. ● Provide The End-user With The Pre-built And As-built Site Development Plan, Electrical Plan, Mechanical Plan, Civil Work Plan, And Architectural Plan Necessary For The Execution Of This Project, As Applicable, Duly Signed By The Respective Licensed Professional Engineers And Architect. ● Provide A Turnkey Basis On The Supply, Delivery, Installation, Testing, And Commissioning Of The Evcs. ● Provide A 2-year Free After-sales Services Which Include But Not Limited To The Following: A. 24-hour Customer Support B. Routinary Diagnostic Checkup Of The Unit C. Troubleshooting And Repair (for Both Hardware And Software) D. Technology Transfer To Selected Pnoc And Pgb Personnel ● Provide A Free Bi-annual Maintenance Checks For The Evcs. ● Provide The Meter/sub-meter For The Evcs. 5. Other Terms And Conditions ● All Bidders Are Required To Conduct Ocular Inspections At The Same Time (date To Be Determined), At The Proposed Evcs Site To Be Assisted By The End-user For Bidders To Determine All Cost And Work Inclusions In The Implementation Of The Project. ● The Bidder Confirms That They Have Inspected The Site Where The Work Will Be Performed And Is Fully Aware Of The Conditions Which Might Affect The Nature, Extent And Cost Of The Work Required; Pnoc Shall In No Way Be Responsible For Any Costs Or Expenses Which May Be Incurred On Account Of Failure Of The Bidder To Make An Accurate Examination Of Present And/or Assessment Of Future Factors That May Affect The Cost Of Execution. ● The Bidder Must Also Include An “affidavit Of Undertaking” In Its Bid Information To Demonstrate Its Capacity To Provide After-sales Service. ● The Price Quoted Should Be Firm And Irrevocable And Not Subject To Any Change Whatsoever, Even Due To The Increase In The Cost Of Raw Materials, Components And Fluctuations In Foreign Exchange Rates And Excise Duties. Should The Bid Goods Be Rendered Obsolete Or Phased Out By The Manufacturer, The Upgraded Or Newer Version Shall Be Delivered At No Additional Cost To The End-user. The Winning Bidder Should Warrant That All Goods, Vehicles, Equipment, Parts And Components Shall Be Brand-new (unused), Not Cloned Nor Imitation, Whatsoever, And If Found So, Shall Be Replaced Immediately With No Additional Cost To Pnoc. ● One Hundred Percent (100%) Of The Contract Price Will Be Processed Upon Satisfactory Completion Of The Delivery, Installation, Commissioning, And Presentation Of Pnoc Acceptance. ● The Bid Price Must Be Inclusive Of All Costs (insurance, Freight, Brokerage, Duties, Taxes, Etc.) Attendant To The Delivery, Installation And Commissioning Of The Items At Pnoc. ● The Winning Bidder Must Carry Out Necessary Works For The Construction Of The Charging Station Such As, But Not Limited To, Electrical Wiring That Will Be Affected By The Construction Of Evcs Roof/awning Shed And Parking Area By The Pgb, Etc. ● The Winning Bidder Must Conduct Installation Of The Fast Charger In Accordance With Standards, Manuals, Etc. ● The Winning Bidder Must Conduct Installation Of At Least One (1) Outlet Capable Of Safely Servicing Ev On-board Charger. ● The Winning Bidder Shall Conduct Testing Prior To The Operational Commissioning, Including The Power Tie-in To Connect The Evcs To The Main Electrical Supply. ● The Winning Bidder Must Provide At Least A Two-day (2) Training For Selected Pnoc And Pgb Personnel Who Will Handle The Operation Of The Evcs Including Operation, Troubleshooting, And Preventive Maintenance Of The Evcs. ● The Winning Bidder Must Provide Two (2) Years Warranty Against Factory Defects On The Ev Charger Unit And Faulty Workmanship On Installation Which Shall Commence 2 Years After Signing Of Acceptance Certificate. The Winning Bidder Should Warrant That All Components Are New, Of First-class Quality, According To Specifications, And Free From Defects. The Defects, If Any, Shall Be Rectified Or Replaced Free Of Charge. ● The Winning Bidder Shall Be Responsible For Providing Claims, Doing Or Arranging Parts Replacement And Servicing For The Warranty During The Warranty Period. The End-user Shall Not Be Redirected By The Winning Bidder To Other Entities Including Suppliers Or Oems (original Equipment Manufacturers) In Executing The Warranty. ● The Winning Bidder Must Provide A Free Mobile Application, To Be Used For Monitoring And Payment Purposes (if Applicable). ● The Winning Bidder Must Submit Primary Material Manufacturer’s Brochures/catalogue, Manuals And Warranty Certificate For The Evaluation Of The Charging Unit And Its Ancillary Parts Prior To Installation As Proof That The Charging Unit And Its Ancillary Parts Are Brand New. ● The Winning Bidder May Avail Itself Of A Designated Area To Be Used As Temporary Facility/storage/administration Area In Connection With The Project. This Staging Area Must Be Boarded-up With A Minimum Height Of 8 Feet And Must Be Returned To Its Original State Upon Completion Of The Project. Any And All Materials, Tools, Supplies, Equipment And The Like Inside The Staging Area Premises Are The Responsibility Of The Winning Bidder, Whereby The End-user Shall Not Be Liable For Any Loss Or Damage Thereto. ● The Winning Bidder Shall Be Liable For All Fire And Accident Claims And Other Related Claims Arising From Injuries And Damages, Which May Occur In Relation To The Execution Of The Project. ● The Winning Bidder Shall Hold The End-user And Pnoc, Including Its Personnel, Free From Any And All Liabilities For Damages Arising From Injuries Or Liabilities To Persons Or Damages To Property Occasioned By Any Act Of Omissions Of The Winning Bidder Including Any And All Expenses Which May Be Incurred By The End-user And Pnoc, Including Its Personnel, In The Defense Of Any Claim, Action Or Suit And In Connection With, Resulting From Or By Reason Of The Performance Of This Project. ● The Winning Bidder Shall Submit A List Of Personnel Assigned To The Project Before Commencing The Above Scope Of Works. ● The Winning Bidder Shall Examine All The Issued Documents Relating To The Work And Must Have Verified All Existing Conditions At The Site. No Consideration Will Be Given To Any Alleged Misunderstanding Or Misinterpretation Of The Specifications And Materials To Be Used Or Work To Be Done. ● The Winning Bidder Shall Follow All The House Rules And Regulations Upon Entering The Premises Of The End-user And Are Required To Wear The Proper Ids, Uniforms And Safety Gear/equipment At All Times. ● The Winning Bidder Is Required To Coordinate All Activities And Work Relative To The Project With The End-user’s Authorized Representative For Proper Coordination And Monitoring. ● Tapping Of Equipment And Other Related Work Shall Be Properly Coordinated With The End-user’s Designated Representative For Provision Of Electrical Power Source Of Outlets. ● The Cost Of Any And All Rework And/or Restoration Of Damaged Properties Due To The Winning Bidder’s Poor Workmanship Or Negligence Shall Be Borne By The Winning Bidder. ● All Works Shall Be Done In Accordance With The Occupational Safety And Health Standards As Dictated By The End-user. ● The End-user Shall Not Provide Any Accommodation/ Transportation For The Engineers/representatives For Attending Commissioning And Demonstration Work. It Is The Absolute Responsibility Of The Winning Bidder To Make Their Own Arrangements. ● The Work Shall Be Executed In The Best Thorough Manner Throughout The Project Timeline To The Satisfaction Of The End-user And Pnoc, As Represented By Its Engineers And Supervisors Who Will Jointly Interpret The Meaning Of The Scope Of Work And Its Conditions And Shall Have The Power To Reject Any Work, Method Of Accomplishing Every Part Of Work And Material Used Which In Their Judgement Are Not In Full Accordance With The Specifications And/or Description As Provided Herein And Are Deemed Disadvantageous To The End-user And To Pnoc. 6. Eligibility ● The Supplier Must Be A Doe Accredited Evcs Provider And Shall Provide All The Necessary Government Permits And Licenses In Performing Their Obligations Under This Document. ● The Bidder Must Be Legally Incorporated Or Organized As A Legal Entity Under The Philippines’ Existing Laws And Regulations. 7. Delivery Terms ● The Delivery Period Of The Goods Shall Be Within 60 Calendar Days, Upon Receipt Of The Approved Notice To Proceed (ntp). ● The Delivery And Installation Site Shall Be Located In A Location Determined By The End-user: • Bataan Tourism Center, Roman Highway, City Of Balanga, Bataan 8. Completion Of Installation ● The Installation Works Must Also Be Completed Within Sixty (60) Calendar Days Following Receipt Of The Notice To Proceed (ntp). ● Work Schedule Is From 8:00am To 5:00pm On Weekdays, Weekends And Holidays ● The Winning Bidder Shall Commence Work On The Agreed Start Date And Shall Carry Out The Work In Accordance With The Program Of Work Submitted By The Bidder And Approved By The End-user And Shall Complete The Work Within The Number Of Calendar Days Specified Herein. ● Delays Due To Work Stoppage Ordered By The End-user Shall Not Be Counted Against The Set Completion Date. 9. Payment The Payment Terms Must Adhere To Republic Act No. 9184 Or The Government Procurement Reform Act. 10. Inspection And Testing ● The End-user May Reject Any Goods Or Any Part Thereof That Fail To Pass Any Tests And/or Inspections Or Do Not Conform To The Specifications As Specified In This Tor. The Winning Bidder Shall Immediately Rectify Or Replace Such Rejected Goods Or Parts Thereof At No Additional Cost. ● The Winning Bidder Must Conduct An Operational Demonstration Of The Goods As Part Of The End-user Acceptance. ● If Any Item Of Work Or Materials, Which Is/are Necessary For The Completion Of The Work And Full Operation Of The Charging Unit And Its Ancillary Parts As Outlined Herein, Has/have Been Omitted, Such Item Must Be Provided/included By The Winning Bidder To Complete The Work And Fully Operate The Charging Unit. 11. Warranty • In Order To Assure That Manufacturing Defects Shall Be Corrected By The Supplier, A Warranty Shall Be Required From The Supplier As Provided Under Section 62.1 Of The 2016 Revised Irr Of Ra No. 9184. • The Procuring Entity Shall Promptly Notify The Supplier In Writing Of Any Claims Arising Under This Warranty. Upon Receipt Of Such Notice, The Supplier Shall, Repair Or Replace The Defective Goods Or Parts Thereof Without Cost To The Procuring Entity, Pursuant To The Generic Procurement Manual. 12. Repair And Maintenance The End-user Shall Notify The Winning Bidder In Writing Whenever Repairs Need To Be Done And Shall Act And Conduct The Assessment Within One (1) Day Upon Receipt Of The Notice. The Repair And Maintenance Shall Be Completed Within The Maximum Period Of Three (3) Days. Should The Repair/maintenance Require A Longer Period, The End-user Should Be Notified In Writing Of The Reason And The Completion Period Which Is Subject To Approval/concurrence With Service Vehicle Replacement As May Be Required.

Côte-d'Or Departmental Fire and Rescue Service (SDIS 21) Tender

Services
Electrical Goods and Equipments...+1Electrical and Electronics
France
Closing Date16 Dec 2024
Tender AmountRefer Documents 
Purchaser Name: Côte-d'Or Departmental Fire and Rescue Service (SDIS 21) | France – Repair And Maintenance Services Of Building Installations – Marché Relatif À Des Prestations De Maintenance Et À La Réalisation De Petits Travaux Dans L'ensemble Des Bâtiments Du Sdis 21 - 3 Lots

Côte-d'Or Departmental Fire and Rescue Service (SDIS 21) Tender

Others
France
Closing Date16 Dec 2024
Tender AmountNA 
Purchaser Name: Côte-d'Or Departmental Fire and Rescue Service (SDIS 21) | Market Relating to Maintenance Services and the Carrying Out of Small Works in All Buildings of Sdis 21 - 3 Lots

Presidency of the Provincial Fire Fighting and Rescue Consortium of Toledo Tender

Corrigendum : Tender Amount Updated
Spain
Closing Date9 Feb 2025
Tender AmountEUR 15.5 Million (USD 16.7 Million)
Purchaser Name: Presidency of the Provincial Fire Fighting and Rescue Consortium of Toledo | Vehicle Weighing Service

Metropolitan Directorate Of Fire Safety And Protection Of The Population Sdpbzn - SDPBZN Tender

Electronics Equipment...+1Electrical and Electronics
Bulgaria
Closing Soon14 Nov 2024
Tender AmountBGN 39.2 K (USD 21.6 K)
Purchaser Name: Metropolitan Directorate Of Fire Safety And Protection Of The Population Sdpbzn | Repair Of State-Owned Buildings Located On The Territory Of 02 Rescue Activity Group To Sector Sod Address Gr. Sofia, Krasno Selo District, St. "Koloman" No. 6

Metropolitan Directorate Of Fire Safety And Protection Of The Population Sdpbzn - SDPBZN Tender

Works
Electrical and Electronics...+1Electrical Works
Bulgaria
Closing Soon13 Nov 2024
Tender AmountBGN 39.2 K (USD 21.6 K)
Purchaser Name: Metropolitan Directorate Of Fire Safety And Protection Of The Population Sdpbzn | Bulgaria – Construction Work – Ремонт На Сгради Държавна Собственост, Находящи Се На Територията На 02 Група Спасителна Дейност Към Сектор Сод С Адрес Гр. София, Район "красно Село", Ул. "коломан" № 6

Metropolitan Directorate Of Fire Safety And Protection Of The Population Sdpbzn - SDPBZN Tender

Works
Civil And Construction...+1Civil Works Others
Bulgaria
Closing Date27 Nov 2024
Tender AmountBGN 280 K (USD 154.6 K)
Purchaser Name: Metropolitan Directorate Of Fire Safety And Protection Of The Population Sdpbzn | Bulgaria – Construction Work – Текущ Ремонт На Сграда Държавна Собственост, Стопанисвана От Столична Дирекция „пожарна Безопасност И Защита На Населението“ На Адрес Град София, Район Кремиковци, Кв. Челопечене, Поземлен Имот С Идентификатор 68134.8504.7, Участък „пожарна Безопасност И Защита На Населението“ Кремиковци

Côte-d'Or Departmental Fire and Rescue Service (SDIS 21) Tender

Others
France
Closing Date16 Dec 2024
Tender AmountRefer Documents 
Purchaser Name: Côte-d'Or Departmental Fire and Rescue Service (SDIS 21) | Market Relating to Maintenance Services and the Carrying Out of Small Works in All Buildings of Sdis 21 - 3 Lots

City of Hradek nad Nisou Tender

Civil And Construction...+4Others, Civil Works Others, Electrical and Electronics, Electrical Works
Czech Republic
Closing Soon15 Nov 2024
Tender AmountCZK 3 Million (USD 129 K)
Details: The Subject of the Public Contract Is the Modification and Revitalization of the Existing Water Reservoir Intended for Small Recreation, Water Retention in the Landscape, and Also as a Water Source for Fire Fighting. As part of the public contract, a separate littoral area with a depth of up to 65 MV will be created in the inlet part of the reservoir. This littoral zone will be separated from the rest of the reservoir by a new boundary made of gabions. The goal of the revitalization is to make the operation and maintenance of the water tank easier, to make the tank more attractive as a recreation place, to bring the tank itself closer to the natural environment in which it is located, and to preserve the fire tank. Part of the construction will be desilting of the tank and settling tank, felling of trees near the dividing object, formation of the coastline, construction of a footbridge, stairs and pier, inlet from the settling tank, repair of the outflow object, dividing the object and planting and grassing.
5911-5920 of 6072 active Tenders