The Municipality has issued a formal invitation for competitive bids for Construction Of Rcc Culvert Over Drain At Vj Function Hall Along The Degree College Road In Pulivendula Municipality in Cuddapah, Andhra Pradesh, with an estimated contract value of Rs. 34,46,261. The bid opening date for this tender is 03-09-2020 and the last date for bid submission is 18-09-2020. Interested bidders for Municipality tender can download the important documents here to check the scope of work, eligibility criteria and technical requirements.

Municipality Tender

Opening Date3 Sep 2020
Closing Date18 Sep 2020
Tender Amount₹ 34,46,261 
This is an estimated amount, exact amount may vary.
Notes
Download

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Construction of RCC Culvert;Supplying and fixing of 100mm dia PVC pipes for weep holes including material, labour charges like cutting size, fixing in side wall etc as directed by Engineer- in- charge

118.8

-

20246

... More
Construction of RCC Culvert;Carting of surplus excavated rock/Soil within a lead of 1Km from the site to a distance suitable including loading charges, cost & conveyance, dumping, labour charges and other incidental and operational charges etc., complete

282.1

-

9070

... More
Construction of RCC Culvert;RBR-STCL-7 : Dismantling Stone Masonry as per Technical Specification Clause 202 : Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of stone masonry, including disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202 MORD / MORTH - Rubble Stone Masonry in Cement Mortar

100

-

39000

... More
Construction of RCC Culvert;RCC M- 30 Design mix using 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site , excluding Seigniorage charges, sales & other taxes on all materials including all operational, incidental and labour charges such as machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and its fabrication charges for finished item of work including form work.

114

-

594045

... More
Construction of RCC Culvert;Supply and filling, spreading Gravel brought from approved quarry of good quality including loading, unloading, conveyance charges, filling charges, tamping etc complete as per S.S for finished item of work.

28.21

-

7851

... More
Construction of RCC Culvert;BLD-CSTN-2-8 (16): Collection ,Supply and filling with HBG stone chips 2.36 mm & below from approved quarry to work site and stacking at work site to Dept. gauge for premeasurements including cost and convenyance of all material and all labour charges etc. complete as per standard specifications. Clause 305.3.9 MORD & 304 MORTH

19.5

-

12015

... More
Construction of RCC Culvert;Dewatering pipe line trenches etc, duly bailing out water from the pipe line trenches with oil engine driven pumpsets, including hire charges, fuel charges and wages for Driver and Helper and all other incidental and operational charges including suction and delivery hose, lead of drain in to natural drain etc, complete.

200

-

12800

... More
Construction of RCC Culvert;RCC M- 20 Nominal mix using 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site , excluding Seigniorage charges, sales & other taxes on all materials including all operational, incidental and labour charges such as machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and its fabrication charges for finished item of work.without formwork

195.5

-

904823

... More
Construction of RCC Culvert;RBR-FNDN-1- ( I-A-i ) In ordinary soils, up to 3.00 Mts depth below GL by Manual means: Earthwork excavation in all kinds of soil for Pipe line trenches as per drawings and technical specifications including setting out, construction of shoring and bracing, removal of stumps and other deleterious material , dressing of sides and bottom as per Technical Specification 305 MoRD / 304 MoRTH and as directed by the departmental officer including protecting the existing utility services wherever it is possible during the execution and taking all precautionary measures in the restricted areas for laying sewer/water pipe lines including divertion of traffic and backfilling in trenches with excavated suitable material and disposal of remaining earth upto a lead of 50 m, including all incidental and operational charges etc., complete by manual means.

120.9

-

25199

... More
Construction of RCC Culvert;Centering area of CC/RCC Vertical Walls of Drains( for both sides centering for walls) as per GO.Ms.No211 dt 15.12.2017

500

-

158500



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.