Andhra Pradesh Education And Welfare Infrastructure Development Corporation Tender

To know what Andhra Pradesh government has posted about any AP etender, Bidassist helps us to get a one-stop platform where a registered bidder can have access to the details on each and every eprocurement tender. There is no need to provide the details on the AP E-procurement website i.e. https://www.apeprocurement.gov.in as BidAssist helps us find the specific etender we're looking for. BidAassist has collated each and every Eproc Andhra Pradesh Tender on its website.

Andhra Pradesh Education And Welfare Infrastructure Development Corporation - APEWIDC Tender

Civil And Construction
Building Construction
Construction Material
Opening Date20 May 2022
Closing Date27 May 2022
Tender Amount₹ 61,08,728 
This is an estimated amount, exact amount may vary.
Notes
Download

Costs

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Chennur;Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, seigniorage charges, sales & other taxes on all materials,all operational, incidental and labour charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall for finished item of work. (APSS 901,903 & 904.

785

-

305993

... More
Chennur;Flooring with Soluble salt porcelain vitrified tiles screen printed and polished of size 600 x 600 mm and thickness between 8-10 mm 1st quality conforming to IS:13711, IS:13712,IS:13630 (Parts 1 to 15) of any colour and finish in all shades and Designs set over a base coat of CM (1:8), 12mm thick (joints of stone must be flushed) over C.C. bed already laid or R.C.C. roof slab only after it is properly cured, cleaned, moistered and where necessary treated with neat grey cement slurry of honey like consistency spred at3.3 kgs of cement for 1 sqm. and jointed with neat cement paste to full depth, including cost and conveyance of all materials like cement, sand, water, flooring stones etc. to site, seigniorage charges, sales and other taxes on all materials, all operational, incidental and labour charges such as dressing of flooring stones to the required sizes, mixing of cement mortar, laying, jointing, curing, lift charges etc., complete for finished item of work.(APSS No.703 & 701)

260

-

234546

... More
Chennur;Providing Skirting with Soluble salt porcelain vitrified tiles screen printed and polished of size 600 x 600 mm and thickness between 8-10 mm 1st quality of any size of brand as approved by Engineer - in - charge and set over a base coat of CM (1:5), 12mm thick and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with white cement paste mixed with pigment of matching shade including cost and conveyance of all materials like cement, sand, water, tiles, etc. to site, seigniorage charges, sales and other taxes on all materials such as mixing of cement mortar, laying in position, curing, lift charges etc., complete for finished item of work (APSS No.701 & 707) in All Floors

13

-

11686

... More
Chennur;Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 mtrs with medium teak wood of sections size 73mm x 100mm with Flush Door Shutter Solid Bond Wood black board type with commercial ply on both faces of 30mm thick including cost of fixtures such as Aluminium Tower Bolts 150 mm long- 2 Nos, Alluminium Handles 100mm- 4 Nos, 300mm long MS Aldrops 1No, 125mm long M.S.Powder Coated butt hinges 6 Nos, Door stoppers 2 Nos, MS Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to site all Labour charges such as Fixing of Door Frame on shutter Fixing in position , with Hardware fixtures etc., complete for finsihed utem of work.

5

-

52834

... More
Chennur;ProvidingandfixingfactorymadeuPVCwhite colour sliding glazed windowabove 1.50 m in height imensioncomprising of uPVC multi-chamberedframe with in-built roller track and sashextruded profilesdulyreinforced with 1.60±0.2mm thick galvanizedmildsteel section made from rollformingprocess of required length (shape & sizeaccording to uPVCprofile), appropriatedimension of uPVC extruded glazingbeads, uPVCextruded interlocks anduPVC extruded Inline sash adaptor (ifrequired), PDMgasket,woolpile,zincalloy(white powder coated) handle ononeside of extreme panel along with zincplated mild steel multi pointlockinghaving transmission gear with keeps,zinc alloy (white powdercoated) touchlock with hook (if required for wire meshpanel), stainlesssteel (SS 304 grade) body with adjustable doublenylonrollers (weight bearing capacity to be120kg), G.I fasteners 100 x 8 mm size forfixingframe to finished wall and necessary stainless steelscrews etc .Profileof frame & sash shall be mitredcut and fusion welded at allcorners,including drilling of holes for fixing hardware's and drainage of water etc. After fixing frame the gap between frame and adjacent finished walls hall be filled with weather proof silicon sealentover backer rod of requiredsize and ofapproved quality, all complete as perapproved drawing & directionof Engineer-in- Charge inclusive of cost of Single / doublegl asspanes, wire meshand silicon sealent .Two track two panels sliding windowmade of (big series)frame 67 x 50 mm& sash 46 x 62 mm both having wall thickness of 2.3 ± 0.2 mm and single glazing bead/double glazing be adofappropriate dimension.(Area of window

16.2

-

113637

... More
Chennur;Supply and Fixing of Ventilator of size 1.52 x 0.45 with 32mm x 32mm x 5mm thick equal L angles and 10mm square rods (4H+6V) fixing in position ,complete for finsihed item of work

120

-

12010

... More
Chennur;Supply and Fixing of Ventilator of size 1.22 x 0.45 with 32mm x32mm x 5 mm thick equal L angles and 10mm square rods (4H+4V) fixing in position ,complete for finsihed item of work

99

-

9908

... More
Chennur;Supply and Fixing of Grill Door cum Grill of size2.80 x 2.80 mts with outer angular frame of rolled steel equal angle 35x35x6m and inner shutter angular frame rolled steel equal angle 35 x 35 x 6 mm, MS aldrop 300mm long-2No ,MS Heay Hinges 75mm long-4No safety rods of 10mm Square rods with primary coat of Red oxide paint including cost,conveyance of all materials to site ,sales and other taxes on all materials and labour charges etc complete

195

-

19516

... More
Chennur;Supplying and fixing of High Polished Granite 16 to 18 mm thick up to 2.43 M other than black and regular colours in Single piece with the edges flat nosed and set over a base coat of CM (1:8), 12mm thick, and fixing in position with neat cement paste including cost and conveyance of all materials like cement, sand, water, stones etc. to site, seigniorage charges, sales and other taxes on all materials, all operational, incidental and labour charges such as dressing of stones to the required sizes, mixing of cement mortar, fixing in position, curing, lift charges etc., complete for finished item of work for Treads

11

-

38478

... More
Chennur;Supplying and fixing of High Polished Granite 16 to 18 mm thick up to 2.43 M other than black and regular colours in Single piece with the edges flat nosed and set over a base coat of CM (1:8), 12mm thick, and fixing in position with neat cement paste including cost and conveyance of all materials like cement, sand, water, stones etc. to site, seigniorage charges, sales and other taxes on all materials, all operational, incidental and labour charges such as dressing of stones to the required sizes, mixing of cement mortar, fixing in position, curing, lift charges etc., complete for finished item of work for Risers

6

-

19342

... More
Chennur;Painting to New walls with two coats of acrylic emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/liter of superior quality of approved brand and shade over base coat of cement primer grade -I making three coats in all to give an even shade after thoroughly brushing the surface to remove all loose powdered materials, including cost and conveyance of all materials, including cost and conveyance of all materials, cost of brushes, water to site, etc., sales & other taxes, all operational, incidental and labour charges such as scaffolding charges, lift charges, curing etc., complete for finished item of work in all floors for Walls.(APSS No. 911) INTERNAL WALLS

900

-

139860

... More
Chennur;Painting to New walls with two coats of acrylic emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/liter of superior quality of approved brand and shade over base coat of cement primer grade -I making three coats in all to give an even shade after thoroughly brushing the surface to remove all loose powdered materials, including cost and conveyance of all materials, including cost and conveyance of all materials, cost of brushes, water to site, etc., sales & other taxes, all operational, incidental and labour charges such as scaffolding charges, lift charges, curing etc., complete for finished item of work in all floors for Walls.(APSS No. 911) EXTERNAL WALLS

370

-

78866

... More
Chennur;Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 Kgs. of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., complete but excluding cost of steel and it?s fabrication charges for finished item of work (APSS No. 402 & 403) RCC Lintels for First Floor

1.35

-

13920

... More
Chennur;Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 380 Kgs. of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., complete but excluding cost of steel and it?s fabrication charges for finished item of work (APSS No. 402 & 403) Sunshade 0.0625 M First Floor

19.5

-

14947

... More
Chennur;Plain Cement Concrete M20 Design Mix ( by Batching Plant) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concrete including cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including steel centering, shuttering, machine mixing, laying concrete, lift charges, curing etc., complete for finished item of work for steps (APSS No. 402 ) First Floor

1

-

6841

... More
Chennur;Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to (1:5:10) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 20mm size Hard Blasted Granite (IS383, 1970) Machine Crushed graded metal from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental, and labour charges such as mixing, laying concrete, finishing top surface, curing concrete, etc., complete for finished item of work for Dummy Columns.

3

-

22125

... More
Chennur;Brick Masonry in superstructure with CM (1:8) prop: using Fly ASH Bricks of size 290x225x140mm with compressive of 50 Kgs / Sqcm from approved source including cost and conveyance of all materials like cement, sand, fly ash bricks, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc., complete for finished item of work. (APSS No. 501 & 504).

110

-

731175.5

... More
Chennur;Providing impervious coat over RCC roof slab to required slopes with CM (1:3) prop. 20mm thick (average) mixed with water proofing compound manufactured by reputed manufacturers as approved by Engineer-in-charge at 1Kg/bag of cement, laid over roof slab when it is green, finished smooth with a floating coat of neat cement and thread lining at regular intervals of 45cmx45cm including cost and conveyance of all materials like cement, sand, water proofing compound, water etc., to site, seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing mortar, laying, rounding off at junctions of wall and slab, rendering smooth with thread lining, curing, lift charges, etc., complete for finished item of work (APSS No. 901 & 903). First Floor

305

-

143274

... More
Chennur;Ornamental Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:5) and top coat of 4mm thick in CM (1:3) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, sales & other taxes on all materials,all operational, incidental and labour charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall but excluding seigniorage charges for finished item of work. (APSS 901,903 & 904) First Floor

420

-

188176

... More
Chennur;Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, seigniorage charges, sales & other taxes on all materials,all operational, incidental and labour charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall for finished item of work. (APSS 901,903 & 904. First Floor

1380

-

591468

... More
Chennur;Flooring with Soluble salt porcelain vitrified tiles screen printed and polished of size 600 x 600 mm and thickness between 8-10 mm 1st quality conforming to IS:13711, IS:13712,IS:13630 (Parts 1 to 15) of any colour and finish in all shades and Designs set over a base coat of CM (1:8), 12mm thick (joints of stone must be flushed) over C.C. bed already laid or R.C.C. roof slab only after it is properly cured, cleaned, moistered and where necessary treated with neat grey cement slurry of honey like consistency spred at3.3 kgs of cement for 1 sqm. and jointed with neat cement paste to full depth, including cost and conveyance of all materials like cement, sand, water, flooring stones etc. to site, seigniorage charges, sales and other taxes on all materials, all operational, incidental and labour charges such as dressing of flooring stones to the required sizes, mixing of cement mortar, laying, jointing, curing, lift charges etc., complete for finished item of work.(APSS No.703 & 701) First Floor

230

-

216258

... More
Chennur;Providing Skirting with Soluble salt porcelain vitrified tiles screen printed and polished of size 600 x 600 mm and thickness between 8-10 mm 1st quality of any size of brand as approved by Engineer - in - charge and set over a base coat of CM (1:5), 12mm thick and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with white cement paste mixed with pigment of matching shade including cost and conveyance of all materials like cement, sand, water, tiles, etc. to site, seigniorage charges, sales and other taxes on all materials such as mixing of cement mortar, laying in position, curing, lift charges etc., complete for finished item of work (APSS No.701 & 707) in All Floors First Floor

17

-

15930

... More
Chennur;Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 mtrs with medium teak wood of sections size 73mm x 100mm with Flush Door Shutter Solid Bond Wood black board type with commercial ply on both faces of 30mm thick including cost of fixtures such as Aluminium Tower Bolts 150 mm long- 2 Nos, Alluminium Handles 100mm- 4 Nos, 300mm long MS Aldrops 1No, 125mm long M.S.Powder Coated butt hinges 6 Nos, Door stoppers 2 Nos, MS Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to site all Labour charges such as Fixing of Door Frame on shutter Fixing in position , with Hardware fixtures etc., complete for finsihed utem of work. First Floor

5

-

52834

... More
Chennur;ProvidingandfixingfactorymadeuPVCwhite colour sliding glazed window above 1.50 m in height dimension comprising of uPVC multi-chamberedframe with in-built roller track and sashextruded profilesduly reinforced with 1.60±0.2mm thick galvanized mildsteel section made from rollformingprocess of required length (shape & sizeaccording to uPVCprofile), appropriatedimension of uPVC extruded glazingbeads, uPVCextruded interlocks anduPVC extruded Inline sash adaptor (ifrequired), EPDMgasket,woolpile,zincalloy(whitepowder coated) handle ononeside of extreme panel along with zincplated mild steel multi pointlockinghaving transmission gear with keeps,zinc alloy (white powdercoated) touchlock with hook (if required for wire meshpanel), stainlesssteel (SS 304 grade)body with adjustable doublenylonrolers (weight bearing capacity tobe 120kg), G.I fasteners 100 x 8 mm size for fixing frame to finished wallnd necessary stainless steel screws etc.Profileof frame & sash shall be mitredcut and fusion welded at allcorners,including drilling of holes for fixing hardware'snd drainage of water etc. After fixing frame the gap between frame and adjacent finished walls hall be filled with weather proof silicon sealentover backer rod of requiredsize and ofapproved quality, all complete as per approved drawing & directionof Engineer-in- Charge inclusive of cost of Single/ doublegl asspanes, wire meshand silicon sealent .Two track two panels sliding window made of (big series)frame 67 x 50 mm& sash 46 x 62 mm both having wallthickness of 2.3 ± 0.2 mm and single glazing bead/double glazing be adofappropriate dimension.(Area of window. First Floor

21.6

-

151515

... More
Chennur;Supply and Fixing of Window of size 1.52 x 1.20 with 32mm x 32mm x 5mm thick equal L angles and 10mm square rods fixing in position ,complete for finsihed item of work First Floor

420

-

42034

... More
Chennur;Supply and Fixing of Ventilator of size 1.52 x 0.45 with 32mm x 32mm x 5mm thick equal L angles and 10mm square rods (4H+6V) fixing in position ,complete for finsihed item of work First Floor

90

-

9007

... More
Chennur;Supply and Fixing of Ventilator of size 1.22 x 0.45 with 32mm x32mm x 5 mm thick equal L angles and 10mm square rods (4H+4V) fixing in position ,complete for finsihed item of work First Floor

72

-

7206

... More
Chennur;Supplying and fixing of High Polished Granite 16 to 18 mm thick up to 2.43 M other than black and regular colours in Single piece with the edges flat nosed and set over a base coat of CM (1:8), 12mm thick, and fixing in position with neat cement paste including cost and conveyance of all materials like cement, sand, water, stones etc. to site, seigniorage charges, sales and other taxes on all materials, all operational, incidental and labour charges such as dressing of stones to the required sizes, mixing of cement mortar, fixing in position, curing, lift charges etc., complete for finished item of work for Treads (APSS No.701 & 707)

11

-

38829

... More
Chennur;Supplying and fixing of High Polished Granite 16 to 18 mm thick up to 2.43 M other than black and regular colours in Single piece with the edges flat nosed and set over a base coat of CM (1:8), 12mm thick, and fixing in position with neat cement paste including cost and conveyance of all materials like cement, sand, water, stones etc. to site, seigniorage charges, sales and other taxes on all materials, all operational, incidental and labour charges such as dressing of stones to the required sizes, mixing of cement mortar, fixing in position, curing, lift charges etc., complete for finished item of work for Risers (APSS No.701 & 707)

6

-

19564

... More
Chennur;Providing High Yield Strength Deformed (HYSD) steel bars (Fe 415 grade as per IS 1786-1985) of 8mm to 40mm diameters, cutting, bending, to required sizes and shapes placing in position with cover blocks of approved size and binding wire of 20SWG, forming grills for reinforcement work as per approved designs and drawings including cost and conveyance of bars from approved sources to site of work, including cost and conveyance of binding wire, cover blocks, chairs, overlaps, spacers, dowels, wastage etc., and all operational, incidental, and labour charges such as cutting, bending, placing in position, tying etc., and sales & other taxes,on cost of all materials complete for finished item of work (APSS No.126) in all floors. First Floor

0.25

-

21421

... More
Chennur;Painting to New walls with two coats of acrylic emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/liter of superior quality of approved brand and shade over base coat of cement primer grade -I making three coats in all to give an even shade after thoroughly brushing the surface to remove all loose powdered materials, including cost and conveyance of all materials, including cost and conveyance of all materials, cost of brushes, water to site, etc., sales & other taxes, all operational, incidental and labour charges such as scaffolding charges, lift charges, curing etc., complete for finished item of work in all floors for Walls.(APSS No. 911) Internal walls First Floor

940

-

146076

... More
Chennur;Painting to New walls with two coats of acrylic emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/liter of superior quality of approved brand and shade over base coat of cement primer grade -I making three coats in all to give an even shade after thoroughly brushing the surface to remove all loose powdered materials, including cost and conveyance of all materials, including cost and conveyance of all materials, cost of brushes, water to site, etc., sales & other taxes, all operational, incidental and labour charges such as scaffolding charges, lift charges, curing etc., complete for finished item of work in all floors for Walls.(APSS No. 911) External walls First Floor

580

-

123627

... More
Chennur;Supply and fixing of 110mm dia ISI mark PVC rain water spouts of 4 Kg/cm2 pressure including Cost of necessary pvc bends, shoes and M.S.clamps and all other accessories and fixing in position including cost and conveyance of all materials to site , seigniorage charges sales and other taxes on all materials, all operational, incidental and labour cahrges such as fixing in alignment etc., complete for finished item of work.(APSS NO1328) in All Floors First Floor

12

-

7730

... More
Chennur;Supply and Fixing of 25 mm dia 1.80 mm thick PVC pipe (ISI MARK) concealed in Roof Slabs with all required accessories including masonary work and labour charges etc., complete. Make : Sudhakar/Maru plast/Avon plast

200

-

19890

... More
Chennur;Wiring with 2 runs of 22/0.3mm (1.5 Sq.mm) FR P.V.C. insulated F.R.L.S. 1110 V graded as per IS:69411990 of flexible copper cable (Phase, Neutral) in the metalic/Non Metalic condduit pipe with 6A flush type switch control, switch control box including all labour charges etc., complete:for Light and Fan Points:

80

-

58248

... More
Chennur;Supply and fixing of 6A ISI Mark 3/2 pin Modular socket with 6A 1way Modular switch, 3 Module box with cover frame and GI switch box on common switch board with connections etc., complete. Accessories Makes: Legrand Lyncus / Havells Coral

16

-

4182

... More
Chennur;Supply and run of 2 of 2.5 sq.mm FRLS PVC insulated flexible copper cable and one run of 1.0 sq.mm flexible copper wire for earthing in existing PVC/ MS conduit pipe for circuit mains including labour charges (phase neutral and earth) etc., complete as required for switch board circuit mains.

200

-

16870

... More
Chennur;Supply, Fixing and Transportation of 20W/24W, not less than 1100mm length LED batten light with extruded alluminium housing and polycarbonate cover, input voltage AC 220 - 260 Volts with PF>0.9, Surge protection: 2KV,THD<15%, with inbuilt driver and frosted cover CCT: 3000K - 5700K, minimum CRI>70, .etc., complete. with Fixing of 18W/20W LED luminaire on wall / Ceiling with / TW round blocks with all accessories including giving connections and all labour charges etc., complete.

40

-

39854

... More
Chennur;Supply of 1200 mm (48") sweep 230V, A.C 50 Hz.Ceiling Fan with 3 Blades and double ball bearings with all standard accessories.etc., complete

40

-

105571

... More
Chennur;Supply and Fixing of modular of 1-model Electronis Type Fan regulator with 2 modul for ceiling fans 1200 mm sweep complete erected on existing board.Make : Anchor / Gold Medal Olive / Million Zoom

32

-

14615

... More
Chennur;Labour charges for Fixing of Ceiling fan and regulator including transportation and giving connections with twin core wire etc., complete

32

-

5488

... More
Chennur;Supply and fixing of (8 +12) 4 Way TPN DB Horizontal with IP 43 Protection suitable for 12Nos S.P. out goings and Supply and Fixing of 1 No., of 32A FP MCB as incomer and 12 Nos 6-32 A 10kA SP MCBs for 1 No 4 pole Incommer etc complete as per IS 8623; IS 13032; IEC 61439-3 Makes: Makes: Legrand(Ekinox 3) / Schneider-A9/Hager -Novello+/ Seimens/Havells STADx/L&T-Newrange/Indo Asian-Opti Pro/ HPL (Techno). as out goings including internal connections and labour charges for FLUSH Mounting etc., complete. (For Lighting DBs)

2

-

19851

... More
Chennur;Providing independent earthing for Important equipment with 40mm dia 'B' class 2.5m long G.I pipe and 20mm dia 'B' class G.I pipe of 0.3mtr. long connected with reducer providing G.I funnel with mesh enclosed in C.C.Chamber of 400m x 400m x 400mm with R.C.C. Slab cover duly providing staggered holes filling with salt and charcoal from the bottom of the pipe giving earth connection from electrode through G.I strip of 40 x 6mm x 200mm length with all accessories and labour charges complete, as per IS specifications 732/1982 (

2

-

12279

... More
Chennur;Supply and Run of 2 of 10 Sq.mm WPSC Aluminium cable along with No.10 SWG G.I bearer wire through PVC cleats with all accessories including labour charges etc., complete for service mains

80

-

5264

... More
Chennur;Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 3m in Loamy & Clayey Soils like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) including all operational incidental labour charges such as shoring, strutting, sheeting, planking and dewatering including cost of hire charges of T & P, labour charges etc., complete for finished item of work including seignerage charges excluding dewatering charges etc., complete for Foundation of Building.(APSS No. 308)

120.38

-

24395

... More
Chennur;Plain Cement Concrete corresponding to M7.5 grade as per IS 456 equivalent to (1:4:8) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm size Hard Blasted Granite (IS383, 1970) metal from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental, and labour charges such as mixing, laying and ramming concrete in layers in position not exceeding 15cm, finishing top surface, curing concrete, etc., complete for finished item of work for Foundations and Flooring Bed (APSS No. 402)

2.44

-

9628

... More
Chennur;Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to (1:5:10) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm size Hard Blasted Granite (IS383, 1970) metal from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental, and labour charges such as mixing, laying and ramming concrete in layers in position not exceeding 15cm, finishing top surface, curing concrete, etc., complete for finished item of work for Foundations and Flooring Bed (APSS No. 402)

11.72

-

44688

... More
Chennur;Plain Cement Concrete corresponding to M15 grade as per IS 456 equivalent to (1:2:4) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 20mm size Hard Blasted Granite (IS383, 1970) Machine Crushed graded metal from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing, laying, curing concrete, etc., complete for finished item of work (APSS No. 402)

1.8

-

9974

... More
Chennur;Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., but excluding cost of steel and it?s fabrication charges for finished item of work. (APSS No. 402 & 403) footings

4.88

-

43011

... More
Chennur;Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., but excluding cost of steel and it?s fabrication charges for finished item of work. (APSS No. 402 & 403) For pedestals

1.1

-

10272

... More
Chennur;Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., but excluding cost of steel and it?s fabrication charges for finished item of work. (APSS No. 402 & 403) For PLINTH BEAM

4.76

-

53246

... More
Chennur;Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., but excluding cost of steel and it?s fabrication charges for finished item of work. (APSS No. 402 & 403) For COLUMNS

2.92

-

31014

... More
Chennur;Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., but excluding cost of steel and it?s fabrication charges for finished item of work. (APSS No. 402 & 403) ROOF BEAMS

3.4

-

30994

... More
Chennur;Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., but excluding cost of steel and it?s fabrication charges for finished item of work. (APSS No. 402 & 403) ROOF SLAB 125mm thick

82.35

-

91277

... More
Chennur;Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., but excluding cost of steel and it?s fabrication charges for finished item of work. (APSS No. 402 & 403) ROOF SLAB 100mm thick

6.24

-

6031

... More
Chennur;Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., but excluding cost of steel and it?s fabrication charges for finished item of work. (APSS No. 402 & 403) ROOF SLAB 200mm thick

6.6

-

10216

... More
Chennur;Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., but excluding cost of steel and it?s fabrication charges for finished item of work. (APSS No. 402 & 403) FOR TANK SIDE WALLS

11.89

-

126389

... More
Chennur;Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., but excluding cost of steel and it?s fabrication charges for finished item of work. (APSS No. 402 & 403) LINTELS

0.37

-

3857

... More
Chennur;Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., but excluding cost of steel and it?s fabrication charges for finished item of work. (APSS No. 402 & 403) BOTTAM SLAB for SEPTIC TANK 225mm thick

18.97

-

32053

... More
Chennur;Filling with useful avilable excavated earth sides of foundations and basement with initial lead in layers not exceeding 15cm thick, consolidating each deposited layer by watering and ramming including cost and conveyence of water to the work site and all operational, incidental, labour charges, seignorage charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310)

37.25

-

1078

... More
Chennur;Filling with Gravel in trenches, sides of foundations and basement with initial lead in layers not exceeding 15cm thick, consolidating each deposited layer by watering and ramming including cost and conveyence of water to the work site and all operational, incidental, labour charges, seignorage charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310)

197.87

-

88893

... More
Chennur;Providing impervious coat over RCC roof slab to required slopes with CM (1:3) prop. 20mm thick (average) mixed with water proofing compound manufactured by reputed manufacturers as approved by Engineer-in-charge at 1Kg/bag of cement, laid over roof slab when it is green, finished smooth with a floating coat of neat cement and thread lining at regular intervals of 45cmx45cm including cost and conveyance of all materials like cement, sand, water proofing compound, water etc., to site, seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing mortar, laying, rounding off at junctions of wall and slab, rendering smooth with thread lining, curing, lift charges, etc., complete for finished item of work (APSS No. 901 & 903).

60.05

-

26158

... More
Chennur;Brick Masonry in Basement with CM (1:6) prop: using Fly ASH Bricks of size 290x225x140mm with compressive of 50 Kgs / Sqcm from approved source including cost and conveyance of all materials like cement, sand, fly ash bricks, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc., complete for finished item of work. for basement (APSS No. 501 & 504).

7.81

-

45049

... More
Chennur;Brick Masonry in Superstructure with CM (1:8) prop: using Fly ASH Bricks of size 290x225x140mm with compressive of 50 Kgs / Sqcm from approved source including cost and conveyance of all materials like cement, sand, fly ash bricks, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc., complete for finished item of work. (APSS No. 501 & 504).

24.61

-

153141

... More
Chennur;Providing and fixing factory made Solid Wood Polymer Composite (WPC) single extruded door frame section of size 45x75mm. the two vertical members are to be joined togheter with the horizontal member using 8x50mm long MS Star full thread screws to be used with reverse forward speed control and drilling machine. The ready/ assembled door frame is fixed to the wall using hold fasts or bolt Fastenes. A minimum of 4Nos of screws to be provided for each vertical member and minimum 2 Nos for horizontal member with encapsulation of 8mm rigid layer on all the six surfaces. the door framewill have a rebat of 32mm. etc. complete as per manufacturers specification and direction of Engineer-in-Charge for finished item of work

53.13

-

30544

... More
Chennur;Providing and fixing 28-30mm thick Solid wood Polymer composite (WPC) single extruded door shutter with 3mm top and bottom rigid layer with an overall density of 750 kg/cum. it will be fixed to the frame using 100 mm long hinges including all labour charges etc., Complete for finished item of work.

16.15

-

55584

... More
Chennur;Supply & Fixing of Ventilators of Various sizes with outet frame of Rolled steel equal angle 40x40x6mm and safety rods of 10 mm square 5H+9V including cost and conveyance of all materials and labour charges etc., complete

282.95

-

28318

... More
Chennur;Ceiling Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:5) and top coat of 4mm thick in CM (1:3) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, sales & other taxes on all materials,all operational, incidental and labour charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall for finished item of work. (APSS 901,903 & 904)

61.08

-

24755

... More
Chennur;Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing mortar,scaffolding charges, lift charges, finishing,including cutting of Grooves wherever necessary as directed by Engineer - in - charge, curing, etc., complete for Uneven Surfaces of Brick Wall for finished item of work. (APSS 901,903 & 904)

141.67

-

55222

... More
Chennur;Flooring with Ceramic non skid Tiles of 7.3mm thick 1st. quality of any shade as approved by Engineer - in - charge set over a base coat of CM (1:8), 12mm thick laid over flooring bed / V.R.C.C. slab, with neat grey cement slurry of honey like consistency spread at the rate of 3.3 Kgs of cement per Sq.m and jointed with neat white cement paste mixed with pigment of matching shade including cost and conveyance of all materials like cement, sand, water, ceramic tiles etc. to site, seigniorage charges, sales and other taxes on all materials, all operational, incidental and labour charges such as mixing of cement mortar, laying, curing, lift charges etc., complete for finished item of work.(APSS No.701 & 707).

39.83

-

33889

... More
Chennur;Dadooing to walls with white glazed ceramic tiles 1st. quality of any size 300x450mm of brand as approved by Engineer - in - charge and set over a base coat of CM (1:5), 12mm thick and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with white cement paste mixed with pigment of matching shade including cost and conveyance of all materials like cement, sand, water, tiles, etc. to site, seigniorage charges, sales and other taxes on all materials, C921 such as mixing of cement mortar, laying in position, curing, lift charges etc., complete for finished item of work (APSS No.701 & 707)

153.83

-

78974

... More
Chennur;Painting to New walls with two coats of acrylic emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/liter of superior quality of approved brand and shade over base coat of cement primer grade -I making three coats in all to give an even shade after thoroughly brushing the surface to remove all loose powdered materials, including cost and conveyance of all materials, including cost and conveyance of all materials, cost of brushes, water to site, etc., sales & other taxes, all operational, incidental and labour charges such as scaffolding charges, lift charges, curing etc., complete for finished item of work in all floors for Walls.(APSS No. 911) in All Floors

107.17

-

16654

... More
Chennur;Providing High Yield Strength Deformed (HYSD) steel bars (Fe 500 grade as per IS 1786-1985) of 8mm to 40mm diameters, cutting, bending, to required sizes and shapes placing in position with cover blocks of approved size and binding wire of 20SWG, forming grills for reinforcement work as per approved designs and drawings including cost and conveyance of bars from approved sources to site of work, including cost and conveyance of binding wire, cover blocks, chairs, overlaps, spacers, dowels, wastage etc., and all operational, incidental, and labour charges such as cutting, bending, placing in position, tying etc., and sales & other taxes,on cost of all materials complete for finished item of work (APSS No.126)

4.3

-

363138

... More
Chennur;Painting to New Iron work with two coats of ready mixed Synthetic Enamel paints in all shades Grade - I having VOC (Volatile Organic Compound ) content less than 50 grams/ liter over an existing steel primer including cost and conveyance of all materials to site, sales & other taxes, incidental, operational and all labour charges etc., complete for finished item of work. (APSS No. 1201, 1207 & 1212).in All Floors

6

-

609

... More
Chennur;Supplying and fixing 580 mm x 440 mm long Orissa pan white glazed Water Closet 1st qualityISI marked confirming to IS:2556-Part-3-1981 with "P" or "S" trap Hindware / Parryware / Neycer with brick masonry seat, P trap or S trap of Indian W.C. shall be encased on CC (1:2:4) 150mm alround well above the joint to stop leakage at the joint etc., complete including cost and conveyance of all materials to site, cost of CC bed, labour charges and seigniorage charges etc., complete for finished item of work.

8

-

15952

... More
Chennur;Supply, fixing of approved make floor mounted single piece EWC suit Ceramic material with range of size 510-695x295-385x520-795mm with 'S' trap for ground floor and 'P' trap with dual flush cistern , ultra solid seat cover of approved make with rubber buffer and cap 15 mm angle stop cock 450 mm long PVC inter connection pipe wall flanges all of approved make etc. complete for finished item of work in all respects:White Colour

2

-

17000

... More
Chennur;Supplying and fixing Indian make Flat Back Wash Hand Basin (Cera make ) 1st quality conforming to IS:2556-Part-4:1972 of size 550mm x 400mm with waste fittings like rubber plug, chain, 32 mm nominal size C.P. Fitting with parallel pipe thread conforming to IS:2963-1979 and fitted with 15 mm nominal bore Chromium Plated Pillar Tap of 1st quality Indian make 400 grams Seiko/ Esso or equivalent complete with standard CI brackets including wooden block ,1 No.12.70mm PVC connection with brass union nuts CP coated , 1 No.12.70mm NP bib tap 300 gms Seiko or equivalent including cost and conveyance of all materials to site, labour charges etc. complete for finished item of work

9

-

28029

... More
Chennur;Supplying and fixing NP bib taps of size 12.70mm dia of Indian make Cera including cost and conveyance of all materials, labour charges etc., complete for finished item of work in all floors. 300 Grams

10

-

4159

... More
Chennur;Supply & fixing Ashirvad/Astral flow guard for equivalent CPVC Pipes with fittings in ground or on wall including cost of tees, elbows, bends, reducers, couplings, running joints, union flanges, unions etc. with necessary excavation in all types of soils except rock requiring blasting, refilling, chiselling masonry walls and making good the walls & floors to the original surface and fixing MS clamps on TW blocks on walls including cost and conveyance of all materials and labour charges complete for finished item of work 41.30 mm dia CPVC SDR 13.50

16.4

-

5199

... More
Chennur;Supply & fixing Ashirvad/Astral flow guard for equivalent CPVC Pipes with fittings in ground or on wall including cost of tees, elbows, bends, reducers, couplings, running joints, union flanges, unions etc. with necessary excavation in all types of soils except rock requiring blasting, refilling, chiselling masonry walls and making good the walls & floors to the original surface and fixing MS clamps on TW blocks on walls including cost and conveyance of all materials and labour charges complete for finished item of work 22.20 mm dia CPVC SDR 13.50.

23.85

-

2412

... More
Chennur;Supply & fixing Ashirvad/Astral flow guard for equivalent CPVC Pipes with fittings in ground or on wall including cost of tees, elbows, bends, reducers, couplings, running joints, union flanges, unions etc. with necessary excavation in all types of soils except rock requiring blasting, refilling, chiselling masonry walls and making good the walls & floors to the original surface and fixing MS clamps on TW blocks on walls including cost and conveyance of all materials and labour charges complete for finished item of work 28.60 mm dia CPVC SDR 13.50.

50

-

7330

... More
Chennur;Constructing 457.2mm x 457.2mm (1'-6" x 1'-6") brick in CM (1:6) prop. Masonry inspection chamber upto 914.4mm (3'-0") and fitted with light weight 457.2mm x 457.2mm (1'-6" x 1"-6") frame and cover of 20kg., including cost and convenyance of all materials to site, all labour charges, sales and otehr taxes on all materials etc., complete for finished item of work

10

-

38550

... More
Chennur;Supply and fixing of SWR/ PVC pipes (as per ISI standards) 4 Kg/Sq.cm. Prince/sudhakar or any ISI brand and fixing all special such as plain bends, off sets, door bends, single junctions, double junctions as per site requirement, fixing with PVC clamps if necessary with required number of Bombay nails including cost and conveyance of all materials to site, labour charges etc.complete for finished item of work at all floor levels. (APSS No. 1302 1319 & 1326) 110mm dia

38.95

-

6285

... More
Chennur;Supply and fixing of SWR/ PVC pipes (as per ISI standards) 4 Kg/Sq.cm. Prince/sudhakar or any ISI brand and fixing all special such as plain bends, off sets, door bends, single junctions, double junctions as per site requirement, fixing with PVC clamps if necessary with required number of Bombay nails including cost and conveyance of all materials to site, labour charges etc.complete for finished item of work at all floor levels. (APSS No. 1302 1319 & 1326) 90mm dia

15.15

-

2048

... More
Chennur;Supply and Fixing of 25mm outer dia heavy 2.20mm thickness grade, FRLS with IS:9537 part 3 regid PVC pipe (ISI mark) concealed in wall with all required accessories including masonary work for light, fan , common and separate plug point including all labour charges etc., complete.

18.1

-

1497

... More
Chennur;Wiring with 2 runs of 14/0.3mm (1.0 Sqmm) FRLS / HFFR PVC insulated 1100V grade as per IS:694/1990 specification for Copper cable in existing pipe with 6A / 10A 1 Way 1 Module Modular Switch control with 6 Module Hot Dip Galvanized modular type Metal Box covered with 6 Modular Cover Frame, 3 Plate Jumbo Ceiling Rose including all labour charges etc., complete for light, bell, fan and exhaust fan points in Non-Residential Buildings.

14

-

10193

... More
Chennur;Supply and fixing of 6A 3/2 Pin 2 Module Modular Socket with shutter with 6A 1 Way 1 Module Modular Switch control on a Common switch board with with 3 Module Hot Dip Galvanized Modular Metal Box covered with 3 Modular Cover Frame with earth continuity including wire leads, earth connections along with all labour charges etc., complete.

2

-

523

... More
Chennur;Supply and Fixing of batten holder/angle holder on existing block with 13W CFL lamp and all labour charges etc., complete. In lieu of ceiling rose.

10

-

1386

... More
Chennur;Supply and run of 1 of 22 /0.3mm (1.5 Sq.mm) FRLS P.V.C. insulated flexible copper cable in existing pipe for earth continuity including all labour charges etc., complete. Makes of Wires : Polycab / Havells / SunCab / Fortune Art / Paragon / HPL / L&T / Power flex / RPG / Anchor / Bonton

100

-

3010

... More
Chennur;Supply and run of 2 of 2.5 sq.mm FRLS PVC insulated flexible copper cable in existing PVC/ MS conduit pipe for circuit mains including labour charges (phase neutral and earth) etc., complete as required for switch board circuit mains.

95

-

8013

... More
Chennur;Supply, Fixing and Transportation of 20W/24W, not less than 1100mm length LED batten light with extruded alluminium housing and polycarbonate cover, input voltage AC 220 - 260 Volts with PF>0.9, Surge protection: 2KV,THD<15%, with inbuilt driver and frosted cover CCT: 3000K - 5700K, minimum CRI>70, .etc., complete. with Fixing of 18W/20W LED luminaire on wall / Ceiling with / TW round blocks with all accessories including giving connections and all labour charges etc., complete.

3

-

2989

... More
Chennur;.Supply and fixing of 8 Way SPN DB with IP 43 Protection as per IS:13032 and suitable for singile phase 8 Nos S.P out goings and for 1No Incommer including internal connection and labour charges for flush mounting etc., complete. Incommer: 40A DP Isolator-1No. Outgoing: 10kA-6-32A SP MCBs - 10 Nos DB Makes : Legrand / Schneider.Isolator Make: Legrand-DX3 / Schneider-Acti9. MCB Make:Legrand-DX3 / Schneider-Acti9.

1

-

4639

... More
Chennur;Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 3m in Loamy & Clayey Soils like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) including all operational incidental labour charges such as shoring, strutting, sheeting, planking and dewatering including cost of hire charges of T & P, labour charges etc., complete for finished item of work including seignerage charges excluding dewatering charges etc., complete for Foundation of Building.(APSS No. 308)

1.51

-

306

... More
Chennur;Plain Cement Concrete corresponding to M7.5 grade as per IS 456 equivalent to (1:4:8) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm size Hard Blasted Granite (IS383, 1970) metal from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental, and labour charges such as mixing, laying and ramming concrete in layers in position not exceeding 15cm, finishing top surface, curing concrete, etc., complete for finished item of work for Foundations and Flooring Bed (APSS No. 402)

0.76

-

2981

... More
Chennur;Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to (1:5:10) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm size Hard Blasted Granite (IS383, 1970) metal from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. complete for finished item of work for Foundations and Flooring Bed (APSS No. 402)

1.11

-

4227

... More
Chennur;Filling with Sand in trenches, with initial lead in layers not exceeding 15cm thick, consolidating each deposited layer by watering and ramming including cost and conveyence of water to work site and all operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310)

4.44

-

4092

... More
Chennur;Brick Masonry in superstructure with CM (1:6) prop: using Fly ASH Bricks of size 290x225x140mm with compressive of 50 Kgs / Sqcm from approved source including cost and conveyance of all materials like cement, sand, fly ash bricks, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc., complete for finished item of work. for basement (APSS No. 501 & 504).

5.97

-

34456

... More
Chennur;Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc., to site, sales & other taxes on all materials,all operational, incidental and labour charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary as directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall for finished item of work. (APSS 901,903 & 904)

2.18

-

850

... More
Chennur;Dadooing to walls with white glazed tiles 1st. quality of any size of brand as approved by Engineer - in - charge and set over a base coat of CM (1:5), 12mm thick and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with white cement paste mixed with pigment of matching shade including cost and conveyance of all materials like cement, sand, water, tiles, etc. to site, seigniorage charges, sales and other taxes on all materials, C921 such as mixing of cement mortar, laying in position, curing, lift charges etc., complete for finished item of work (APSS No.701 & 707)

18.31

-

9401

... More
Chennur;Flooring with Ceramic non skid Tiles of 7.3mm thick 1st. quality of any shade as approved by Engineer - in - charge set over a base coat of CM (1:8), 12mm thick laid over flooring bed / V.R.C.C. slab, with neat grey cement slurry of honey like consistency spread at the rate of 3.3 Kgs of cement per Sq.m and jointed with neat white cement paste mixed with pigment of matching shade including cost and conveyance of all materials like cement, sand, water, ceramic tiles etc. to site, seigniorage charges, sales and other taxes on all materials, all operational, incidental and labour charges such as mixing of cement mortar, laying, curing, lift charges etc., complete for finished item of work.(APSS No.701 & 707).

13.49

-

11479

... More
Chennur;Supply & fixing Ashirvad/Astral flow guard for equivalent CPVC Pipes with fittings in ground or on wall including cost of tees, elbows, bends, reducers, couplings, running joints, union flanges, unions etc. with necessary excavation in all types of soils except rock requiring blasting, refilling, chiselling masonry walls and making good the walls & floors to the original surface and fixing MS clamps on TW blocks on walls including cost and conveyance of all materials and labour charges complete for finished item of work [28.60 mm dia CPVC SDR 13.50].

50

-

7330

... More
Chennur;Supplying and fixing 12.70mm dia Fancy type Long body Bib cock including cost and conveyance of all materials, labour charges etc., complete for finished item of work in all floors.

9

-

3743



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.