Sand Filter Tenders

Offizielle Bezeichnung Stadt Frankfurt Am Main, Gr Nfl Chenamt Tender

Others
Germany
Description: Public tender Vob/a landscaping work / playground construction The playground in the green area of the residential development on Hugo-kallenbach-str. is to be redesigned as part of a children's participation project. It is planned to ... More landscaping work / playground construction The playground in the green area of the residential development on Hugo-kallenbach-str. is to be redesigned as part of a children's participation project. It is planned to carry out three hands-on construction activities during the construction phase. During the first construction activity, the wooden parts of the play equipment are to be colored. The concrete snake is to be covered with colored tiles in the second construction activity. During the third construction activity, some of the wood chips are to be installed under the play equipment using a bucket chain as fall protection. The construction activities are to be led by the construction management and employees of the AN and supported by the Ag. Three AN employees are to lead groups of children for each construction activity. The employees are instructed beforehand in how to deal with the children. The Fraunhofer Children's Office's code of conduct for projects must be followed. Electricity, water, sewage, and toilets must be provided by the project manager, and all coordination is to be made independently by the project manager. Mass compilation: 13 tree guards, 1720 sqm of lawn stripped 3.5 cm, 27 m sandpit edging removed and disposed of, 27 cubic meters of play sand removed, 55 sqm concrete slabs removed and disposed of, 3 benches moved, 3 wastebaskets removed and disposed of, 1 volleyball net removed and disposed of, 1 bollard removed and reinstalled, 2 spring rockers removed and disposed of, 1 "ark" post removed and reinstalled, 12.5 cubic meters of foundation concrete demolished, 2 tons of municipal waste removed and disposed of, 9 tons of construction rubble removed and disposed of, 76 cubic meters of soil with turf removed and disposed of, 129 cubic meters of soil removed and disposed of, 51 cubic meters of topsoil removed and reinstalled, 0.07 m of topsoil removed and reinstalled, 138 cubic meters of subsoil loosened 0.10-0.50 m, installation 15 m³ loosening of soil with suction excavator 24.70 m³ loosening of soil for individual foundations 57 m³ of existing soil installed as a mound 5.5 m concrete palisades 47 m flow barrier planting 15 m³ frost protection layer 0/32, thickness 0.15 m 31 m³ gravel base layer 0/32, thickness 0.20 m 34 m³ drainage layer 0/32, thickness 0.10 m 178 m single-row paving strip as edging Paved area 130 m² concrete paving, 11 stone formats 50 m² wet-cut concrete paving 9 m paving ramp to the sandpit, 6-row in concrete 30 m² concrete slabs in 0.05 m mortar sandpit floor 20 m² wet-cut concrete slabs 165 m single-row paving strip, edging Fall protection and sand 303 m² filter fleece 150g/m² under wood chips 6 septic tanks with 16/32 and fleece coating 11.5 m² play sand 122 m² wood chips 16/40 delivered 122 m² wood chips installed 84 m² single-grain concrete 0.10 m filter layer synthetic fall protection 57 m² synthetic fall protection for fall heights up to 1.60 m 37 m² synthetic fall protection for fall heights up to 1.40 m 50 m edge wedge synthetic. Fall protection 1 Psch security service 2 nights 1 pc table/bench seating combination custom-made 4 pc posts supply and install for waste bins 10 m sandstone seating block arched for seating arena 1 pc crocodile spring rocker 1 pc blank mosaic snake: head/5 middle sections/tail 10 sqm tiles and adhesive for mosaic snake supply 1 Psch flexible mortar for grouting for 10 sqm 3 pc sand tables made from tree trunks 11 pc balancing sticks made from standing tree sections 1 pc balancing tree 1.30 m lying down 1 pc balancing tree 3.30 m lying down 1 pc balancing tree with fork 3.30 m lying down 2 pc teepees made from wooden poles 1 pc toddler swing, simple 1 pc toddler play combination with slide 1 pc climbing frame robinia/oak 1 pc wooden 2-way swing 1 pc nest swing 1 pc lounge board/sandal table 51 cbm of existing topsoil to be installed 119 cbm of topsoil to be delivered and installed 5 solitary trees to be planted 2.50 m 17 shrubs to be planted 1.50 m 19 shrubs to be planted 0.40 m 80 m² of vegetation to be planted 1053 m² of vegetation to be planted turf 580 m² of reseeding lawn areas 1 pc of material for hands-on construction project: paint 1 pc of tools for hands-on construction project: mosaic 1 pc of tools for construction project: wood chip installation 1 year of completion care 1 year of development care Special attention is drawn to the existing tree population that is to be preserved. The earthworks in the eaves area (= root area) may only be carried out with the utmost care and, if necessary, by hand. Play equipment must be ordered immediately after the contract has been awarded to avoid delays in the construction process due to long delivery times. An on-site inspection is urgently recommended so that the costs of transporting and collecting materials and installation items, and any interim storage facilities, etc. can be taken into account in the calculation. When submitting a bid, a child protection concept (30% award criterion) with the following content and appropriate documents/proof must be submitted with regard to the advertised hands-on construction activities: -principles of action/code of conduct to prevent transgressive behavior. This subgroup is valued at 20%. -procedure in the event of injuries to children/young people. This subgroup is valued at 20%. -advanced training/additional qualification within the framework of the child protection concept. This subgroup is valued at 60%. In addition, a certificate of good conduct will be required from employees who will be leading the hands-on construction activities with children before construction begins.
Closing Date10 Apr 2025
Tender AmountRefer Documents 

Offizielle Bezeichnung Stadt Frankfurt Am Main, Gr Nfl Chenamt Tender

Others
Germany
Description: Public tender Vob/a landscaping work / playground construction The playground in the green area of the residential development on Hugo-kallenbach-str. is to be redesigned as part of a children's participation project. It is planned to carry out three hands-on construction projects during the construction phase. During the first construction project, the wood of the play equipment is to be colored. The concrete snake is to be covered with colored tiles in the second construction project. During the third construction project, some of the wood chips are to be installed under the play equipment using a bucket chain as fall protection. The construction projects are led by the construction management and employees of the An and supported by the Ag. Three employees of the An are to instruct groups of children for each construction project. The employees are instructed beforehand in how to deal with the children. The code of conduct for projects of the Fraunhofer Children's Office must be followed. Electricity, water, sewage and toilets must be provided from the beginning and all coordination must be made independently from the beginning. Mass composition: 13 pieces of tree protection 1720 sqm of lawn peeled off 3.5 cm 27 m of sandpit edging removed and disposed of 27 cubic metres of play sand removed 55 sqm of concrete slabs removed and disposed of 3 pieces of benches moved 3 pieces of wastepaper baskets removed and disposed of 1 piece of volleyball net removed and disposed of 1 piece of bollard removed and reinstalled 2 pieces of spring rockers removed and disposed of 1 piece of "arch" post removed and reinstalled 12.5 cubic metres of foundation concrete demolished 2 tons of municipal waste removed and disposed of 9 tons of building rubble removed and disposed of 76 cubic metres of soil with turf removed and disposed of 129 cubic metres of soil removed and disposed of 51 cubic metres of topsoil 0.07 m removed and reinstalled 138 cubic metres of subsoil loosened 0.10-0.50 m, installation 15 cubic metres of soil loosened with suction excavator 24.70 cubic metres of soil loosened for individual foundations 57 cubic metres of existing soil installed as a hill 5.5 m of concrete palisades 47 m of flow barrier planting 15 cubic metres of frost protection layer 0/32, thickness 0.15 m 31 cubic metres of gravel base layer 0/32, thickness 0.20 m 34 cubic metres of drainage layer 0/32, thickness 0.10 m 178 m of single-row paving strip as edging Paved area 130 m² of concrete paving, 11 stone formats 50 m of wet-cut concrete paving 9 m of paving ramp to the sandpit, 6-row in concrete 30 m² of concrete slabs in 0.05 m mortar Sandpit floor 20 m of wet-cut concrete slabs 165 m of single-row paving strip, edging Fall protection and sand 303 m² filter fleece 150g/m² under wood chips 6 soakaways with 16/32 and fleece coating 11.5 m² play sand 122 m² wood chips 16/40 delivered 122 m² wood chips installed 84 m² single-grain concrete 0.10 m filter layer synthetic fall protection 57 m² synthetic fall protection for fall heights up to 1.60 m 37 m² synthetic fall protection for fall heights up to 1.40 m 50 m edge wedge synthetic. Fall protection 1 Psch security service 2 nights 1 pc table/bench seating combination custom-made 4 pcs posts supply and install for waste bin 10 m sandstone seating block arched for seating arena 1 pc crocodile spring rocker 1 pc mosaic snake blank: head/5 middle parts/tail 10 sqm tiles and adhesive for mosaic snake supply 1 Psch flexible mortar for grouting for 10 sqm 3 pcs sand tables made from tree trunks 11 pcs balancing sticks made from standing tree sections 1 pc balancing tree 1.30 m lying down 1 pc balancing tree 3.30 m lying down 1 pc balancing tree with fork 3.30 lying down 2 pcs tepee made from wooden poles 1 pc toddler swing, simple 1 pc toddler play combination with slide 1 pc robinia/oak climbing frame 1 pc wooden 2-way swing 1 pc nest swing 1 pc lounge board/sandal table 51 Cbm of existing topsoil installed 119 Cbm of topsoil delivered and installed 5 pieces of solitary trees planted 2.50 m 17 pieces of shrubs planted 1.50 m 19 pieces of shrubs planted 0.40 m 80 sqm of vegetation areas created planting 1053 sqm of vegetation areas created lawn 580 sqm of lawn reseeding areas created 1 psch of material for hands-on construction project paint 1 psch of tools for hands-on construction project mosaic 1 psch of tools for construction project wood chip installation 1 year of completion care 1 year of development care Special attention is drawn to the existing trees that are to be preserved. The earthworks in the eaves area (= root area) may only be carried out with the utmost care and, if necessary, by hand. Play equipment must be ordered immediately after the order has been placed to avoid delays in the construction process due to long delivery times. An on-site inspection is strongly recommended so that the costs of transporting materials and installation items to and from the site, as well as any interim storage facilities, can be taken into account in the calculation. When submitting a bid, a child protection concept (30% award criterion) with the following content and appropriate documents/evidence must be submitted for the advertised hands-on construction activities: -principle of action/code of conduct to prevent transgressive behavior Rating of this subgroup 20% -procedure in the event of injuries to children/young people Rating of this subgroup 20% -advanced training/additional qualification as part of the child protection concept Rating of this subgroup 60% In addition, a certificate of good conduct will be required from employees who will be leading the hands-on construction activities with children before construction begins.
Closing Date3 Apr 2025
Tender AmountRefer Documents 

UNITED STATES AGENCY FOR GLOBAL MEDIA Tender

Civil And Construction...+2Others, Civil Works Others
Corrigendum : Closing Date Modified
United States
Details: Amendment 00002 at This Time, Usagm Is Not Performing Any Mission-related Activities While It Rescopes Its Functions In Accordance With Executive Order 14328, “continuing The Reduction Of The Federal Bureaucracy”. As A Result, Rfp # 951700-25-r-0012 Is Hereby Suspended Until Further Notice. ****************************************************************************************************************************************************************************** amendment 00001 usagm Hereby Extends The Due Date For Proposal Submission From:4/2/2025 To: 4/11/2025. See Attached Amendment 00001 For Details **************************************************************************************************************************************************************************** background this Is A Contract (hereinafter "contract") Between The U.s. Agency For Global Media (hereinafter Referred To As The "usagm"), An Entity Of The Government Of The United States Of America, With Its Headquarters Located At 330 Independence Avenue, Sw, Washington, Dc, 20237, U.s.a. And (tbd) (hereinafter "contractor"). statement Of Work the Requirement Of This Contract Is To Provide Facilities Maintenance Support At The Usagm Philippines Transmitting Station Located In Tinang, Concepcion, Tarlac. the Contractor Shall Provide A Broad Range Of Maintenance Services To Support The Ongoing Operations Of The Facility. The Statement Of Work Is As Follows: electrician Services – Regular Inspection, Maintenance, Troubleshooting, And Repair Of The Facility's Electrical Systems, Ensuring Safety, Efficiency, And Compliance With Electrical Codes And Standards. air Conditioning (hvac) Maintenance And Repair – Scheduled Preventive Maintenance And Corrective Repair Of Air Conditioning Systems, Including Split-type Units, Chillers, Cassette Multi-zoned Hvac Systems, And Ventilation Equipment To Maintain Optimal Indoor Air Quality And Temperature Control. real Property Maintenance & Repair – General Upkeep And Repair Of All Physical Infrastructure, Including Building Exteriors, Roofing, Walls, Flooring, Ceilings, Windows, And Doors. Work Shall Also Include Minor Renovations, Carpentry, Painting, And Masonry As Required. household Equipment & Appliances Maintenance – Periodic Inspection And Servicing Of Facility-owned Household Appliances, Including But Not Limited To Refrigerators, Ovens, Washing Machines, Dryers, And Kitchen Equipment. plumbing Services – Maintenance And Repair Of All Plumbing Systems And Fixtures, Ensuring The Proper Operation Of Water Supply And Drainage Systems. The Facility Contains Approximately 95 Plumbing Fixtures Across Multiple Buildings, Requiring Routine Inspections, Leak Detection, Unclogging, Replacement Of Damaged Components, And Compliance With Water Efficiency Standards. warehouse Support – Inventory Management, Logistics Assistance, And Maintenance Of Storage Areas, Ensuring Proper Organization And Safekeeping Of Equipment, Tools, And Materials Essential For Facility Operations. maintenance & Repair Of Government-owned Vehicles (govs), Heavy Equipment, Utility Vehicles (utvs), And Gasoline/ Diesel-powered Tools – Routine Servicing, Preventive Maintenance, And Necessary Repairs To Ensure Operational Readiness And Safety Compliance Of Government-owned Vehicles And Equipment. temporary Additional Maintenance Services – On An As-needed Basis, The Contractor May Be Required To Provide Supplemental Maintenance Services Beyond The Standard Scope Outlined Above. These Services Will Be Determined By Operational Requirements And Facility Needs. emergency Maintenance Services – The Contractor Shall Provide Additional Maintenance Services As Required By The Facility. These Services Will Be Project-specific And May Include Emergency Repairs, Short-term Labor Support, Or Other Operational Needs Outside Of The Regular Maintenance Schedule. the Contractor Is Expected To Have Qualified Personnel, Tools, And Resources Necessary To Execute These Services Efficiently While Adhering To Industry Best Practices, Safety Standards, And Government Regulations. this Facility Includes The Buildings Shown In The Following Chart, The Contractor Will Be Required To Maintain The Rooms As Identified In Attachment 6. all Services Shall Be Performed In Accordance With The Statement Of Work, Terms And Conditions, And Attachments Included In This Contract And All Applicable Far Clauses, Regulations, Standards, Attachments And Other Documents Referenced Herein. purpose: The Maintenance Of The Building Is Essential For Ensuring Its Long-term Functionality, Safety, And Efficiency. A Well- Maintained Facility Not Only Preserves Its Structural Integrity But Also Enhances The Overall Operational Effectiveness Of The Organization It Serves. The Key Objectives Of Building Maintenance Include: ensuring Safety And Usability – Proper Maintenance Ensures That All Building Systems, Including Electrical, Plumbing, Hvac, And Structural Components, Remain In Safe Working Condition. Regular Inspections And Repairs Help Prevent Potential Hazards Such As Electrical Failures, Leaks, Water Damage, Or Structural Deterioration, Safeguarding The Well-being Of Employees, And Visitors. extending The Longevity Of Assets – Consistent Upkeep Of Critical Infrastructure, Equipment, And Building Components Reduces Wear And Tear, Ultimately Prolonging The Lifespan Of Assets. Preventative Maintenance Strategies, Such As Routine Servicing, Calibration, And Condition Monitoring, Prevent Premature Degradation And Extend The Operational Life Of Essential Systems. optimizing Asset Performance – A Well-maintained Facility Enables All Mechanical, Electrical, And Structural Components To Operate At Their Highest Efficiency Levels. Properly Functioning Hvac Systems, Lighting, And Plumbing Improve Indoor Air Quality, Energy Efficiency, And Overall Workplace Productivity. avoiding Unscheduled Downtime – Proactive Maintenance Minimizes The Likelihood Of Sudden Equipment Failures, System Breakdowns, Or Emergency Repairs That Could Disrupt Daily Operations. This Ensures Continuous Service Availability, Especially In Mission-critical Facilities Where Downtime Can Lead To Operational Setbacks And Financial Losses. minimizing Operational Costs – Routine Maintenance Is Cost-effective Compared To Reactive Repairs Or Emergency Replacements. Preventing Small Issues From Escalating Into Major Failures Reduces Repair Expenses, Conserves Resources, And Minimizes Disruptions That Could Impact Productivity. Proper Asset Management Also Helps In Energy Conservation, Reducing Long-term Utility Costs. enhancing Compliance With Regulations – Regular Maintenance Ensures That The Building Meets Local, National, And International Building Codes, Safety Standards, And Environmental Regulations. Compliance With Fire Safety Protocols, Electrical Standards, And Occupational Health Regulations Reduces Legal Liabilities And Improves Workplace Safety. preserving Property Value – Maintaining The Building’s Physical Structure, Aesthetics, And Functionality Enhances Its Market Value And Ensures That It Remains A Valuable Asset For The Organization. Neglected Properties Suffer From Depreciation, Costly Repairs, And Reduced Efficiency Over Time. supporting Sustainability Initiatives – Proper Maintenance Contributes To Environmental Sustainability By Reducing Energy Consumption, Water Wastage, And Material Waste. Efficient Use Of Resources Through Maintenance Practices Such As Led Lighting Upgrades, Hvac Optimizations, And Smart Building Management Systems Aligns With Green Building Initiatives And Corporate Sustainability Goals. in Conclusion, A Well-maintained Building Is More Than Just An Operational Necessity—it Is A Strategic Investment. By Implementing A Robust Maintenance Program, The Facility Remains Safe, Functional, Cost-efficient, And Sustainable, Ultimately Contributing To The Success Of The Organization And The Well-being Of Its Occupants And Equipment. objectives the Objectives Of This Contract Include: providing Facilities Maintenance Support Services On A Routine Basis To Maintain The Operational Integrity Of The Facility. ensuring All Scheduled And Unscheduled Maintenance Tasks Are Documented And Completed Within Established Timelines. Maintaining Compliance With All Applicable Safety, Regulatory, And Operational Standards. providing Effective Supervision And Management Of Contractor Personnel To Ensure High-quality Performance And Adherence To Contract Requirements. contract Type this Is A Firm-fixed-price (ffp)/hybrid Contract For Facility Maintenance Services For The Usagm Philippines Transmitting Station. All Standard Services Are Firm-fixed-price, Temporary Additional Services And Emergency Maintenance Services Are Not To Exceed (nte) Contract Line Items (clins) Based On Fixed Price Hourly Rates. acquisition Authority this Acquisition Is Conducted Under The Authority Of The Federal Acquisition Regulation (far) Part 13-simplified Acquisition Procedures; Far Subpart 13.5-simplified Procedures For Certain Commercial Items; Far Part 12-acquisition Of Commercial Items. The Solicitation Document And Incorporated Provisions And Clauses Are Those In Effect Through Federal Acquisition Circular 2025-02; Dated 01/03/2025. To View The Latest Federal Acquisition Circulars (fac) Go To Https://www.regulations.gov. section Ii – Technical Services/specific Work Requirements this Is A Firm-fixed-price (ffp)/hybrid Contract For Facilities Maintenance Support Services At The U.s. Agency For Global Media, Located At Tinang, Concepcion, Tarlac, Philippines. the Contractor Shall Perform The Following Technical Services/work Requirements: standard Services the Contractor Shall Provide Facilities Maintenance Support Services. The Contractor Shall Include All Planning, Administration, And Management, And Perform All Related Support Functions Such As Supply, Subcontracting, Quality Control, And Maintenance Of Complete Records And Files Necessary To Assure That All Services Comply With This Contract And Are Comport With All Applicable Laws And Regulations. unscheduled Services: Maintenance That Is Planned But Is Not Scheduled For Specific Time And Has Not Been Assigned To A Technician. All Other Maintenance And Repair Actions Shall Be Documented On The Work Order Form Provided In Attachment 3. These Assignments Shall Be Issued To Address And Track Unforseen Work Identified During Routine Scheduled Maintenance Or Resulting From System Failures Outside The Contractor’s Normal Workday. The Contractor Shall Document All Failures Or Anomalies Discovered During Inspections Or Observed By Contractor Personnel On A Work Order And Submit It To The Cor. electrician Services the Contractor Shall Provide Building Electrical Maintenance, Modify Or Install Power Distribution Transformers And Maintenance Of Electrical Circuits And Services As Per Directed By The Station. Many, But Not All, Daily Assignments Will Have Electricians Working alongside Station Employees To Complete Work Assignments. Services Includes Electro-mechanical Work, Shall Involve Daily Inspections And Logging Of Equipment Condition, As Well As Repair Of Such Equipment. The Contractor’s Electrical Service Personnel Shall Perform Maintenance Of low Voltage Load And Power Panels, Emergency And Exit Lights, Electrical Manholes And Hand Holes. The Contractor’s Personnel Shall Also Be Required To Replace And Repair Street And Perimeter Lighting, Which Includes Replacement Of Wiring, Conduits, Grounding, Etc. General Cleaning Of Electrical Equipment And Auxiliaries, And Spot Painting Of The Same Shall Be Accomplished On An As-needed Basis. daily Work Assignments. Routine Daily Work Assignments Typically Revolve Around Routine Maintenance And Repair Of Items Such As Lighting Fixtures; Switch Panels; Electrical Outlets, Wiring And Conduits; Circuit Breakers And Fuses; Motors; And Other Items In The Station's Low Voltage Electrical System. Daily Work Assignments Typically Revolve Around Routine Maintenance And Repair Of Items. quarterly Work Assignments. Quarterly Maintenance Assignments Shall Include, But Are Not Limited To, The Following (refer To Attachment 7 For Sample Quarterly Maintenance Checklist): cleaning Of All The Exterior Lighting Fixtures On All Buildings, Along The Perimeter Fence Line - At Inner Compound, Tt2 Area, Power Plant Compound, And At Antenna Field Structures (fixtures Include But Are Not Limited To Emergency Lights, Exit Lights, Streetlights, Pylon Lights, Flood Lights And May Need To Be Replaced Or New Fixtures Installed) cleaning Of The Station's Exterior Electrical Outlets On Buildings And On Antenna Field Shelters. cleaning Of The Electrical Panels, Motor Control Center And Lighting Controllers. cleaning Of Low Voltage Transformers. electrical Equipment Shall Be Tested And Repaired Or Replaced, As Necessary. ​​​​​​​​​​​​​​preventive Maintenance: In Addition To Scheduled Maintenance, The Contractor Will Be Called During The Normal Workday As Required By Varying Weather And Environmental Conditions Throughout The Year To Provide Direct Support To The Station's Electrical Unit. these Jobs Include, But Are Not Limited To, The Following cleaning Of Electrical Manholes And Hand Holes. cleaning Of Generator Cooling Towers, Cooling Radiators, Air Filters, And Air Compressors. cleaning Of Substation Equipment And Distribution Switchgears During Annual Preventive Maintenance. assist With The Installation Of Electrical Provisions And Relocation Of Electrical Equipment During Building Renovations And Building Construction. perform Periodic Cleaning Of Electrical Equipment And Auxiliaries. perform Periodic Painting Of Electrical Equipment. air Conditioning (ac) Maintenance And Repair- Quarterly ac Work Shall Include Periodic Inspections, Repair, Preventive Maintenance, Installation And Repair Or Replacement Of Component Parts, Recovery Of The Refrigerants (refer To Attachment 8 For List Of Hvac Units), And Other Ac Activities Directed By The Station. quarterly Maintenance. Besides General Maintenance And Repair Activities, The Contractor Shall Perform The Following Scheduled Maintenance (refer To Attachment 9 For Sample Quarterly Maintenance Checklist For Ac Units): preventive Maintenance/scheduled Maintenance. schedule Maintenance Is Planned For A Specific Time And Scenario. Preventive Maintenance Or Pm Is Regular, Planned Maintenance Scheduled According To Usage Or Time-based Triggers. cleaning Of Air Conditioning Units In The Buildings And At The Antenna Field Shelters. cleaning Of Air Ventilation Units And Air Filters On Buildings. cleaning Of Air Compressor Units. cleaning Of The 2-unit Air Cooled Water Chiller And 2 Air Handling Units. Assist With Troubleshooting Air Conditioning Unit Water Chiller. assist With Troubleshooting And Repair Of Air Conditioning Systems In The Station Vehicles. assist With Installation And Replacement Of All The Air Conditioning Units At The Station. real Property Inspection. The Contractor Shall Provide Real Property Inspection. Any Maintenance Or Repair Required As A Result Of Inspection Findings, Will Be Ordered In Accordance With The Procedures Outlined In Section 2. Standard Services. daily Inspections. The Contractor Shall Assist Locally Employed Staff (les) Electrical Equipment Technicians In Performing Daily Inspections To Identify Required Maintenance And Repair Work (refer To Attachment 13- Real Property Inspection). The Intent Of This Requirement Is That Daily Inspections Will Cover All Work Areas Identified In Attachment 13 From Week To Week. Required Work Shall Be Reported To The Cor For Scheduling. During Inspections Performed By The Locally Employes Staff And Contractor Personnel, All Maintenance And Repair Work Found Will Be Documented By Completing And Submitting A Work Order To The Cor For Approval. the Areas To Be Inspected Are As Follows: walls/roofing. Damaged Or Deteriorated Wall Areas Shall Be Repaired/replaced To Restore To A Serviceable, Structurally Sound, And Watertight Condition. This Includes, But Is Not Limited To, Replacing Damaged Masonry Units, Tuck-pointing Loose Or Eroded Mortar Joints, Sealing Penetrations In Wall Openings, Building Roof Tops, Replacing Damaged Or Deteriorated Structural Members, Siding, Underlay, And Exterior Trim, Replacing Miscellaneous Hardware Items And Repairing Any Water Penetration Of Station Roofs. concrete Works. Contractor Shall Patch Cracked, Broken Or Chipped Concrete Floors, Walkways And Drives With A Non-shrinking Cement Mortar. Working Areas Shall Be Cleaned, And All Loose Concrete Removed. Underlay Surfaces Shall Be Chipped To Ensure Bond With The Patch. Shallow Chip Areas Shall Be Chipped To Provide Space For An Adequate Patch Thickness. The Patch Shall Be Finished Even With The Adjacent Surfaces And Finished To Match Existing Texture. Contractor Shall Install Concrete Forms, Construct Concrete Foundation Or Slabs And Concrete Post As Required. Damaged Septic Tanks Shall Be Replaced Or Repaired, And Electrical Concrete Post Foundations Constructed As Directed By The Cor. building Exterior. Exterior Trim, Including All Exterior Moldings, Millwork, Shutters, And Cornice Shall Be Repaired Or Replaced As Required. Surfaces For All Installations Shall Be Thoroughly Cleaned Of Sealant And Paint Build-up Prior To Installation Of Trim. Damaged Or Deteriorated Insulation Board Or Underlay Shall Be Replaced With Material Of The Same Type, Thickness And Quality. gutters. Broken, Damaged, Misaligned, Or Leaking Gutters And Downspouts Shall Be Repaired Or Replaced With New Material To Match Original As To Gauge, Type Of Material And Finish, And Loose Hangers And Fasteners Shall Be Tightened. Missing Wire Guards, Hangers And Fasteners For Gutters And Downspouts, And Splash Blocks Shall Be Replaced. Splash Blocks Shall Be Properly Positioned To Receive The Impact Of Drainage Water. tiles. Tile On Floors, Kitchen Countertop, Lavatories, Walls, And Window Stools/sills And Marble Saddles That Are Broken, Missing, Cracked Or Discolored Shall Be Replaced As Required. Wall And Floor Tiles Shall Be Re-grouted As Required To Provide A Waterproof Seal. Damaged Or Deteriorated Tiles Shall Be Replaced With Matching Tiles Of The Same Thickness As Original. Damaged Tiles Or Tiles To Be Replaced Shall Be Removed Without Affecting Adjacent Tiles And The Affected Area Shall Be Cleared Of All Debris And Moisture To Provide A Clean, Uniform Dry Surface For The Installation Of New Tile. If Tile Is Replaced Adjacent To A Wall, Vinyl Baseboard Shall Be Replaced Or Repaired As Necessary. Damaged Caulking Around Sinks, Shower Stalls, Tiles And Accessories Shall Be Chiseled Out And Replaced With A Silicone Base Sealant As Necessary. doors And Windows. The Contractor Shall Perform Minor Repairs On Doors And Windows Throughout The Station Facilities. Repairs Will Include But Are Not Limited To Lose, Damaged, Inoperable, Or Missing Hardware Such As Hinges, Striker Plates, Latches, Keepers, Window Mechanisms, Door Closures, Springs, Etc. Though Temporary Repair Work May Be Completed In Emergency Circumstances To Shield Security Doors And Windows, Routine And Longer-term Preventive Maintenance And Repair Of Hardened Security Doors And Windows Are Performed By The Embassy Regional Security Office And Is Not Part Of This Contract. painting. Painting Shall Include Complete Repainting Or Touch Up Painting On Both Interior And Exterior Surfaces To Match Existing Conditions And Is Considered An Integral Part Of Most Of The Work Pertaining To This Requirement. All Replacement Parts And Materials Will Be Provided By The Government As Government Furnished Material (gfm). All Painting, Whether Interior Or Exterior, Partial Or Complete, Shall Include All Work Necessary For A Finished Job Including Windows, Doors Frames, Trim, Molding, Closets, And Shelves. This Includes All Surface Preparation, Caulking, Required Spot Priming, Moving/protection Of Furniture In Occupied Areas, And Cleanup After The Job Is Complete. The Contractor Shall Perform Touch Up Painting To All Rusted Field Equipment, Tractors, Zero Turn Mowers, Skid Loader, And The Excavator. plastering. The Contractor Shall Provide Light Masonry Services Such As Plastering Of Old And New Surfaces Due To Alteration Or Modification, Laying Of Concrete Masonry Walls, Repair And Replacement Of Tiles, Fabrication Of Concrete Posts And Concrete Blocks, Repair Of Drainage Structures Such As Pipe Culvert Or Box Culvert, Road Protection Such As Repair Of Curbs, Retaining Walls And Stone Masonry Or Riprap. carpentry. The Contractor Shall Perform The Following Carpentry Related Services: Fabrication Of Boxes And Shipping Crates, Forms For Concrete Placement, Barricade Signs, Preparation And Installation Of Wall Partitions, Storage And Office Shelving, Kitchen Cabinets, Restroom Lavatories And Countertops, Fabrication And Installation Of Kitchen Countertops And Sinks, Wood Sanding/finishing Work In Preparation For Painting/varnishing Services, And Other Such Items Requiring Wood Working And Fabrication. Repair And Installation Of Damage Perimeter Post And Chain Link. asphalt Road Patch Maintenance Work. The Contractor Shall Perform Minor Asphalt Road Maintenance Work. crack Asphalt Surface And Pothole Shall Be Excavated To A Proper Depth. Excavation Shall Be Square Or Rectangular In Shape, Cut And Side Portion Straight. remove All Loose Dirt And Apply A Prime Coat Of Mc-70 Cutback. This Prime Coat Should Penetrate The Base About ¼”, Filling The Voids. The Primed Area Should Be Adequately Cured Before The Surface Course Is Laid And Should Be Barricaded To Prevent Traffic From Carrying Dust Or Mud Onto The Surface And After Priming. apply The Bitumen (85/100 Cutback) At Temperature Of 200-265f. The Quantity Of The Bitumen Required Is Based On The Average Particle Size Of The Cover Surface. The Aggregate Must Not Be Completely Submerged In The Bitumen. The Aggregate Must Be Spread Immediately After The Bitumen While The Bitumen Is Still Fluid. Since 85/100 Cutback Asphalt Cools To The Temperature Of The Surface To Which Is Applied In 1-1/2 Minutes, The Aggregate Must Be Placed Within 1 Minute. rolling Should Be Done Immediately After Sufficient Aggregate Is Spread To Prevent Pick-up Of The Bituminous Materials. Rolling Should Be Parallel To The Centerline Of The Roadway To Reduce The Number Of Times The Roller Must Change Direction. to Assure Complete Coverage, Succeeding Passes Should Overlap By One –half The Wheel Width Of The Roller. To Assure That The Aggregate Is Well Embedded In The Bitumen, Rolling Should Be Completed Before The Bitumen Hardens. To Maintain Surface Crown And To Prevent Feathering At The Edges, Succeeding Passes Should Be Made From The Low Side To The High Side Of The Surface. household Equipment & Appliances Maintenance: (all Equipment And Appliances Are Located In The Station Compound.) routine Maintenance. The Contractor Shall Provide Household Equipment And Appliances Maintenance Services, As Follows: maintenance And Repair Of Government Owned Household Equipment And Appliances, Including Free Standing Ranges, Refrigerators, Range Hoods, Dishwasher, Water Heaters. Smoke Detectors, Ceiling Fans, Electric Ranges, Freezer, Microwave Oven, Washing Machine, Clothes Dryer, Drinking Fountain, Water Dispenser, Air Curtain, Air Purifier And Shredder Machine. maintenance On All Types Of Fans Located In Offices And Shops. Services Shall Consist Of Replacing Defective Wirings, Plugs Etc. And Oiling Of Motors. movement And Handling Of All Appliances And Equipment, Including Movements Between The Appliance Pool, The Government’s Delivery Point And The Use Location. preventive Maintenance. The Contractor Shall Perform Preventive Maintenance On All Appliances And Household Equipment Held In The Appliance Pool To Keep Standby Appliances And Equipment In Ready Status To Be Installed To Replace Failed In-service Equipment. plumbing Maintenance Services. Plumbing Work Shall Include Maintenance And Repair Of All Plumbing Systems And Fixtures. There Are Approximately 95 Fixtures Located In Different Building Location In The Usagm’s Facilities. When Repaired, Plumbing Systems And Fixtures Shall Be Free Flowing, In Good And Safe Operating Condition, Free Of Leaks And Drips. Note That Work Orders Are Required To Track Plumbing Maintenance Activities. preventive Maintenance. The Contractor Shall Provide Plumbing Maintenance Services As Follows: Preventive Maintenance Is Regular, Planned Maintenance Scheduled According To Usage Or Time-based Triggers. the Contractor Shall Mop, Vacuum, Or Otherwise Remove Water Resulting From Overflowing Fixtures, Leaks, Clogged Drains Or Disposal, Etc. As Part Of The Repair. Walls, Ceilings, And Other Structures, Which Are Damaged By And/or Removed To Gain Access To Leaks, Clogs Or Other Defects Shall Be Restored By The Contractor To Original Condition. the Contractor Shall Assist Electrical Equipment Unit (eeu) Unit To Operate, Maintain And Repair Station Water Systems Including Servicing, Repair Or Replacement Of Bathroom Fixtures, Kitchen Fixtures, Water Hydrants, Water Distribution Lines, De-ionized Water Treatment Systems, Well Pumps, Pressure Control Systems, Sump Pumps, Float Switches, Potable Water, Water Treatment Facilities And Firefighting Equipment. The Contractor Shall Clean And Maintain Two 20,000-gallon Water Reservoir Tanks And A 3,000-gallon Hydro Pneumatic Tank. contractor Shall Assist The Eeu Unit To Operate, Clean, Maintain And Repair The Facilities Wastewater System, To Include Repair And/or Replacement Of Water Drains, Sewer Lines, Septic Tanks, Manholes, And Hand Holes. contractor Shall Assist The Eeu Unit To Operate, Repair And Maintain The Station Water Treatment Plant Including But Not Limited To The Chlorinating System Equipment, Water Softener, Brine Tank, Sand And Carbon Filters, Booster Pumps And Deep Well Pump Motors. the Contractor Shall Assist The Eeu Unit To Check And Clean Regularly All Station Eyewash/portable Eye Wash. Replace/refill With Potable Water Bi-monthly. monthly Task - Fire Hydrants Shall Be Tested To Ensure Proper Operation. annual Task Schedule – The Contractor Shall Assist Les Electrical Technicians With The Following Work: a) Manually Clean Two 20,000-gallons Capacity Water Reservoir Tanks, 3,000- Gallons Hydro-pneumatic Tank, And Station Septic Tank. This Includes Of Cleaning Of Water Filters (sand And Carbon Filters) And Auxiliary Equipment Such As Booster Pumps Motors, Motor Controls And Air Compressors. (saturday And Sunday Only). ​​​​​​​warehouse Support the Contractor Shall Provide General Warehouse Support Services For Two Warehouses (transmitter Plant And Facilities Plant). Both Provide Similar Services; However, The Facilities Warehouse Generally Handles A Higher Volume And Higher Weight Items. Work Performed Includes But Is Not Limited To Loading/unloading Of Large Shipments, Stock Placement And Removal From Warehouse Shelving/ Bins, Movement Of Office And Residential Furnishings Between The Warehouse And Various Onsite Buildings, Packing And Crating Services, And Supporting Other General Warehouse Functions (refer To Attachment 14) For Sample Of Daily/monthly/quarterly And Yearly Tasks). ​​​​​​​packing & Crating. the Contractor Shall Perform All Packing And Crating Functions For Shipment Of Sensitive Electronic Equipment, Furnishings, And Other Outgoing Property Shipments. Contractor Personnel Shall Be Familiar With The Use Of Crate Banding Devices And Must Be Capable Of Handling Tools- Of-the-trade (i.e. - Band Cutters, Hammers, Screw Drivers, Crowbars, J-bars, Etc.). ​​​​​​​loading/unloading Services. the Contractor Shall Perform All Loading And Unloading Of Shipping Containers, Delivery Vehicles, Flatbeds, Air Freight Vans, Shipping Crates, And Other Large Wooden Or Cardboard Boxes. The Contractor Shall Ensure All Personnel Providing Services Are Proficient With Using Hand Trucks And Pallet Jacks To Transport Heavy Crates, Boxes And Equipment. The Contractor Shall Ensure At Least One Person Is Qualified To Operate Forklifts 3-tons And Up, As Well As A 3-ton Truck Crane. ​​​​​​​inventory & Housekeeping. the Contractor Shall Assist Government Personnel Conducting Inventories, Warehouse Reorganizations, And Issuing/receiving Activities. The Contractor Shall Maintain The Orderliness Of Items Within The Warehouse, To Include Maintaining Orderly Shelves, Loose Property Bins, Clear Walkways, And Access To Fire Extinguishers And Fire Escapes. ​​​​​​​movement Of Government Property the Contractor Shall Facilitate Movement Of Materials And Equipment In Other Functional Areas Throughout The Station. Contractor Personnel Shall Periodically Accompany Station Drivers To Assist With Loading, Transport, And Unloading Of Government Property And Supplies To/from Off-site Locations. Off-site Locations Include, But Are Not Limited To, The U.s. Embassy Manila, Foreign Service Officer Residences, International Airports / Ports, And Other Regional Locations In Support Of Shipping, Procurement And Disposal Actions. ​​​​​​​switchboard Operation & Related Services the Contractor Shall Provide Switchboard Operator Services Throughout The Normal Working Day. Services Shall Include Answering Telephones, Re-routing Calls, Onsite Paging Of Government Employees, Placing Outgoing Calls, And Otherwise Operating The Station Centralized Telephone Switchboard Equipment. incoming Calls. The Contractor Shall Answer All Incoming Telephone Calls, Which Currently Number Approximately 150 Calls Per Day, Through The Centralized Telephone Switchboard Equipment. Calls Are Generally From The U.s. Embassy, Other U.s. Agencies, Other Usagm Transmitting Stations Overseas, Station Vendors, Washington Headquarters, And Other Entities Inside And Outside The Country. The Receptionist Shall Maintain A Log Of Incoming Calls That Includes The Following Information: name Of Caller. time Call Was Received. name Of Person/office Called outgoing Calls. The Contractor Shall Place Outgoing Calls, Which Currently Number Approximately 50 Per Day, For Usagm Personnel. Calls Are To Both Local And International Destinations. The Receptionist Shall Maintain A Log Of Outgoing Calls That Includes The Following Information: name Of Caller. time Call Was Received. name Of Person/office Called. telephone Line Used. telephone Number Dialed. type Of Call: Personal Or Official ​​​​​​​telephonic Bomb Threat. In The Event The Receptionist Receives A Bomb Threat Over The Telephone, He/she Shall Be Prepared To Follow The Attached Telephonic Bomb Threat Form. Refer To Attachment 15. system Faults. Faulty Telephone Lines, Equipment Malfunctions, Or System Irregularities Shall Be Reported To The Cor Immediately. ​​​​​​​maintenance & Repair Of Government Owned Vehicles (govs), Heavy Equipment, Utility Vehicles (utvs), And Gasoline/diesel Powered Tools. the Contractor Shall Provide Scheduled Maintenance And Routine Repair Services For Government Vehicles, Heavy Equipment And Gasoline Powered Tools And Equipment. The Station Vehicle Fleet Consists Of A Wide Variety Of Vehicles From Sport Utility Vehicles (suvs), Light And Medium Pickup Trucks, Passenger Vans And Heavy Cargo Vehicles, And Fire Fighting Vehicles. Serviced Equipment Includes Tractors, Forklifts, Utility Vehicles (utvs), Lawn Mowers, And Smaller Fuel Powered Tools And Equipment. The Government Shall Provide All Tools And Materials For Work Performed In This Section. See Attachment 23 For A List Of Government Owned Vehicles. ​​​​​​​vehicle Maintenance & Repair. The Contractor Shall Initiate Troubleshooting For Station Vehicles And Provide A Detailed Diagnosis Of Problems Found. The Report Shall Include A List Of Parts And Procedures Needed To Repair The Vehicle. Only Routine Repairs Such As Replacing/changing Belts, Filters, Batteries, Lights/lamps, Pumps, Spark Plugs, Alternators, Brake Pads, Tires, Oils And Fluids Will Be Performed Under This Contract. The Station Shall Utilize Commercial Service Centers For More Extensive Repair Jobs That Require Specialized Tools And Equipment Not Included In The Gfm/gfe. preventive Maintenance. The Contractor Shall Perform Scheduled Maintenance On All Govs (attachment 23), As Well As All Heavy Equipment, Utility Vehicles (utvs), And Gasoline/diesel Powered Tools, Provided As Government Furnished Equipment (gfe) (attachment 1) And Record All Maintenance Performed Utilizing Attachments 17 And 18, Respectively. For Those Preventive Maintenance Tasks That Are Done At Off-site Locations, The Contractor Shall Assist The Cor. Motor Pool Supervisor, And Warehouse Supervisor With Record Keeping And Scheduling Of Preventive Maintenance As Required. vehicle Cleaning. The Contractor Shall Provide Routine And Detailed Cleaning (included Under The Carriage) For Govs On A Bi- Weekly Basis, But More Frequently If Required. Refer To Attachment 19 For Vehicle Cleaning Instructions. equipment Cleaning. The Contractor Shall Clean/wash Heavy Equipment And Gasoline/diesel Powered Tools After Each Daily Use. Utv's Shall Be Thoroughly Washed And Cleaned Weekly, But More Frequently If Required. roadside Assistance. The Contractor Shall Provide Roadside Assistance For Gov Breakdowns In The Greater Tarlac Region (within 1.5-hour's Drive From The Station). ​​​​​​​temporary Additional Maintenance Services temporary Additional Services Are Defined As Maintenance Services Described Under 2.0 Through 2.7.5 Standard Services But Are Required At Times Outside Of The Normal Workday As Well Emergency Services That May Occur And Be Required At Any Time. These Services Shall Support System Failures, Special Events, Or Emergencies At The Station. The Contractor Shall Provide These Services In Addition To Services Specified In Paragraphs 2.0 Through 2.7.5 Of This Contract. The Cor Shall Order These Services As Needed. This Work Shall Be Performed By Trained Personnel Of The Contractor And Shall Not Be Subcontracted. The Cor May Require The Contractor To Provide Temporary Additional Services With 24-hour Advance Notice. These Personnel Cannot Be The Same Personnel Performing Standard Services, Unless Work Is Performed During Weekends. assignments As Directed. In Addition To Scheduled Maintenance, The Contractor Will Be Called Outside Of The Normal Workday As Required By Varying Weather And Environmental Conditions Throughout The Year To Provide Direct Support To The Station's Electrical Unit. These Jobs Include, But Are Not Limited To, The Following: cleaning Of Electrical Manholes And Hand Holes. cleaning Of Generator Cooling Towers, Cooling Radiators, Air Filters, And Air Compressors. cleaning Of Substation Equipment And Distribution Switchgears During Annual Preventive Maintenance. assist With The Installation Of Electrical Provisions And Relocation Of Electrical Equipment During Building Renovations And Building Construction. perform Periodic Cleaning Of Electrical Equipment And Auxiliaries. perform Periodic Painting Of Electrical Equipment. ​​​​​​​emergency Maintenance Services emergency Services Are Defined As Maintenance Services That May Occur And Be Required At Any Time. These Services Shall Support System Failures, Special Events, Or Emergencies At The Station. While The Contractor Is Expected To Service Multiple Requirements Simultaneously, The Contractor Shall Be Prepared To Provide Services On A More Frequent Or Urgent Basis Following Heavy Storms/ Typhoons. While It Is Typical For Two Or More Of Such Activities To Be Ongoing (simultaneously), The Typical Pattern Is To Complete Temporary Or Patchwork Repairs Of Perimeter And Antenna Roads During The Rainy Season Followed By Long Term Or More Permanent Repairs During The Dry Season. The Contractor Shall Provide These Services In Addition To Services Specified In Paragraphs 2.0 Through 2.8 Of This Contract. The Cor Shall Order These Services As Needed. This Work Shall Be Performed By Trained Personnel Of The Contractor. The Cor May Require The Contractor To Provide Temporary Additional Services With 24-hour Advance Notice. These Personnel Cannot Be The Same Personnel Performing Standard Services, Unless The Emergency Work Is Performed During Weekends. assignments As Directed. In Addition To Scheduled Maintenance, The Contractor Will Be Called Outside Of The Normal Workday As Required By Varying Weather And Environmental Conditions Throughout The Year To Provide Direct Support To The Station's Electrical Unit. These Jobs Include, But Are Not Limited To, The Following: cleaning Of Electrical Manholes And Hand Holes. cleaning Of Generator Cooling Towers, Cooling Radiators, Air Filters, And Air Compressors. cleaning Of Substation Equipment And Distribution Switchgears During Annual Preventive Maintenance. assist With The Installation Of Electrical Provisions And Relocation Of Electrical Equipment During Building Renovations And Building Construction. perform Periodic Cleaning Of Electrical Equipment And Auxiliaries. perform Periodic Painting Of Electrical Equipment. section Iii- Special Requirements management And Supervision supervision. The Contractor Shall Designate A Project Manager Who Shall Always Be Responsible For On-site Supervision Of The Contractor’s Workforce. This Project Manager Shall Be The Focal Point For The Contractor And Shall Be The Primary Point Of Contact With U.s. Government Personnel. The Project Manager Shall Have Sufficient English Language Skills To Be Able To Communicate With Members Of The U.s. Government Staff. work Orders. The Contract Requires That All Maintenance And Repair Services, Whether Completed As A Standard Service, Temporary Additional Service, Or Emergency Maintenance Service Are Documented On A Work Order (see Attachment 3). scheduled Services. For Scheduled Services, "work Orders" Refer To Established Preventive Maintenance Procedures. The Contractor Shall Perform Preventive Maintenance As Described In This Contract And Submit A Weekly Preventive Maintenance Report To The Cor. This Report Shall Document Completed Procedures As Well As Any Items Incomplete Or Deferred, Providing Explanations Or Justifications For Any Uncompleted Work And Proposing A Schedule To Address These Items. normal Work Schedules. The Contractor Shall Maintain Work Schedules For Their Employees. All Work Shall Be Performed From Monday Through Friday, Between The Hours Of 8:00 Am And 4:30 Pm, Except For The U.s. Embassy Manila Approved American And Philippine Holidays. Other Hours May Be Approved By The Cor. The Contractor Must Provide At Least 24-hour Advance Notice To The Cor Who Will Consider Any Deviation From The Hours Identified Above. ​​​​​​​potential Offerors Should Carefully Review The Attached Request For Proposals And Price Table Before Responding To This Synopsis/solicitation.
Closing Date11 Apr 2025
Tender AmountRefer Documents 

Municipality Of Carmen, Bohol Tender

Civil And Construction...+1Water Storage And Supply
Philippines
Details: Description I. Project Description The Project Involves The Design And Build Of A 3 Mld Water Treatment Facility, Inclusive Of A 3 Mld Water Treatment Plant (wtp), Raw Water Abstraction Facility, Raw Water Pipeline, Raw Water Impounding Lagoon, Product Pumping Station, 3 Phase Power Transmission Line And Product Water Transmission And Distribution Pipelines To Barangays Poblacion Norte And Poblacion Sur. It Also Includes One (1) Month Proving Period With Performance Guarantees On Specific Usages Of Power And Chemicals For The Production Of Potable Water That Meets The Philippine National Standards For Drinking Water. Ii. Conceptual Design The Project Concept Is To Construct A 3 Mld Water Treatment Facility Using Socon River As Raw Water Source. The Raw Water Will Undergo Series Of Processes To Remove Sediments, Microbes And Other Impurities To Ensure That The Water Reaching To The Consumers Complies With The Quality Set Forth In The Philippine National Standards For Drinking Water, Pnsdw. The Product Will Be Distributed To Barangays Poblacion Norte And Poblacion Sur. Iii. Proposed Project Components: 1. Raw Water Abstraction (intake) Facility 2. Raw Water Transmission Line 3. Impounding (raw Water) Lagoon 4. Lagoon Pumping Station 5. 3 Mld Water Treatment Plant 6. Residual Management Facility (sludge Lagoon) 7. Product Water Pumping Station 8. Power Supply 9. Product Water Transmission Line 10. Product Water Distribution Lines, Valves, Fittings And Other Appurtenances 11. Site Development • General Earthworks • Fence Below Are The Coordinates Of The Proposed Locations Of The Facilities: Table 1. Location Of The Proposed Facility Facilities Location Proposed Location Of The Facility 9°49’40” N, 124°12’43” E Iv. General Map Showing The Location Of The Proposed Water Treatment Facility V. Conceptual Design Of A 3 Mld Water Treatment Facility Vi. Approved Budget Of Contract The Total Capital Expenditure (capex) Requirement For This Project Is Php 115,000,000.00. The Project Is Financed Through A Term Loan Agreement With The Development Bank Of The Philippines. Progress Payments To The Contractor Shall Be Governed By The Terms And Conditions Set Forth In The Omnibus Term Loan Agreement And The Deed Of Undertaking, Duly Executed Between The Development Bank Of The Philippines And The Municipality Of Carmen, Bohol. Furthermore, These Payments Shall Adhere To The Pertinent Provisions Of The Implementing Rules And Regulations Of Republic Act No. 9184, The Relevant Coa Rules And Regulations, And Any Other Applicable Laws. These Terms And Conditions Are Hereby Formally Communicated To All Prospective Bidders Through This Provision. Table Below Summarizes The Component Cost Of The Capex. Capex Summary Component Cost, Php Site Development And Fencing Raw Water Abstraction Facility Raw Water Transmission Pipeline Raw Water Impounding Lagooon 3 Mld Water Treatment Plant Residual Management Facility Product Pumping Station Power Supply Product Water Transmission Pipeline Product Water Distribution Lines, Valves, Fittings And Other Appurtenances Engineering & Design Commissioning & Proving Period Temporary Facility Total Project Cost Php 115,000,000.00 Vii. Proposed Design & Construction Schedule The Project Must Be Completed Within One (1) Year From Receipt Of Notice To Proceed. Viii. Contractor’s Track Record And Performance Guarantee The Contractor Must Show Proof That It Has Previously Installed A Water Treatment Plant (“wtp”) With A Proven Capacity Of No Less Than 3.0 Mld Capable Of Treating River Water At Turbidity Level Up To 5,000 Ntu. The Said Wtp Should Demonstrate A Low Energy Consumption Not Exceeding 0.15 Kwh/m3 Within The Wtp Battery Limit. The Contractor Must Be Able To Successfully Demonstrate During The 7-day Performance Test That The Wtp Has Continuously Operated At A Production Rate Of No Less Than 3.0 Mld, Energy Consumption Not Exceeding 0.15 Kwh/m3 And Product Water Quality That Meets The Specifications Of The Philippine National Standard For Drinking Water. The Contractor Must Incorporate In The Design Of Its Wtp A Feature That Will Allow 100% Water Recovery And Zero Effluent Discharge. Ix. General Scope Of Works Of The Contractor The Contractor Is Required To Perform The Following Scope Of Works: 1. Review Of Existing Information Review The Basic Design Parameters And Detailed Scope Of Works. The Contractor Shall Ensure That It Has First-hand Information On The Site Development Plan, Construction Data, Geo-hazard Maps, Elevation And Other Gis Maps And Other Documents That Are Readily Available From The Project Owner. Such Will Be Used To Define Project Design Criteria And Serve As Basis For Any Changed Conditions And Establish Project Cost Estimates. Should Any Of These Data And Other Pertinent Data Be Unavailable, The Contractor Shall Carry Out The Needed Testing/investigation To Complete The Needed Design Data. 2. Field Survey And Site Inspection The Contractor Shall Conduct The Appropriate Site Survey Including Staking, Establishing Of Horizontal And Vertical Control Points, Benchmarks, Traverse And Profile Survey, And Stream Flow. 3. The Contractor Shall Have Inspected The Site And Its Surroundings And Orient Himself With The Following: A. Location And Nature Of Work; B. Climatic Conditions; C. Nature And Condition Of The Terrain; D. Geologic Conditions At The Site; E. Transportation And Communication Facilities; F. Availability Of Construction Materials, Labor, Water Services, Electric And Power Supply; G. Location And Extent Of Aggregate Sources; And H. Other Factors That May Affect The Cost, Duration And Execution Of The Work. 4. Pipeline And Structural Analysis The Contractor Shall Prepare The Necessary Structural Analyses, Calculations And Design Of Structural Members In Accordance With The National Building Code Of The Philippines, National Structural Code Of The Philippines And Other Relevant Codes. The Design Of The Main Structure And Its Appurtenances Shall Take Into Account Prevailing Conditions Of The Area To Attain The Optimum Safety Of The Whole Structure. The Contractor Shall Prepare The Pipeline Design On The Basis Of Data Obtained From Site Investigations And Survey Of The Proposed Water Source, Site For Water Treatment Plant, And The Location Of Pipelines, Materials And Other Investigations Necessary In Standard Engineering Practice To Ensure High Efficiency Of The Proposed Water System. 5. Hydraulic Analysis The Contractor Shall Make A Hydraulic Analysis That Form Part Of The Technical Documents To Be Submitted To Ascertain That The Water System Could Provide The Required Flow And Pressure Based On The Designed Population And Planning Period. At The End Of The Design Stage, The Contractor Is Expected To Produce The Appropriate Design And Construction Plans. 6. Permits And Licenses The Contractor Shall Be Responsible For The Application Of Necessary Permits, Clearances And Licenses From Local And National Agencies Having Jurisdiction Over The Project. No Commencement Of The Project Without First Securing The Said Documents. 7. Construction Works The Contractor Shall Perform The Following Construction Activities But Is Not Limited To The Following: A. Mobilization/demolition The Contractor Shall Mobilize And Bring Out Into Work, All Personnel, Plant And Equipment, In Accordance With His Approved Construction Program, Equipment Moving And Utilization Schedule And Manpower Schedule, From Its Regular Place Of Business To The Site To Undertake The Contract. Mobilization Shall Include The Obtaining And Transporting To Jobsite Of Equipment, Materials, Tools, Personnel, Constructional Plant And All Necessary Items For The Execution And Completion Of The Work And Shall Also Include The Setting Up And Verification Of All Equipment And Instruments Until It Is Rendered Operable. Demobilization Shall Include Dismantlement And Removal From The Site Of The Contractor’s Materials And Equipment And All Temporary Facilities. It Shall Also Include A Clean-up Of The Site After Completion Of The Contract As Well As Transportation From The Site Of The Contractor’s Personnel. B. Site Clearing And Proper Waste Disposal General Site Clearing Operations Include The Removal Of Demolished Materials And Objectionable Matter, Protection And Clearing To Allow For New Construction. The Contractor Is Obliged To Provide Barricades, Coverings, Or Other Types Of Protection Necessary To Prevent Damages. Likewise, He/she Is To Dispose Of Materials, Trash And Debris In A Safe And Acceptable Manner In Accordance With Applicable Laws And Ordinances. Burying And Burning Of Trash And Debris At The Site Will Not Be Permitted. Trash And Debris Shall Be Removed From The Site At Regular Intervals To Prevent These From Accumulating And Ultimately Delaying The Course Of The Work. Site Works B.1. Excavation, Foundations, Anchorage The Design And Quality Of Structural Materials To Be Used Shall Be In Conformity To The Governing Laws And To The Acceptable Engineering Practices. Footings, Foundation Elements And/or Anchorage Systems Shall Be Of The Appropriate Type, Of Adequate Size/s And Capacity In Order To Safely Sustain The Superimposed Loads Under Seismic Forces, Lateral Earth Pressure Or Any Condition Of External Forces That May Affect The Stability Of The Structure. Excavated Soil Shall Be Coordinated With The Lgu-carmen For Proper Disposal. C. Conduct Of Potability Test After Project Completion And Commissioning, The Contractor Should Conduct Water Potability Test With The Presence Of The Representative Of The End-user. X. Specifications & Parameters A. Scope Of Design And Build Of The Water Treatment Facility And Related Works The Necessary Works For The Design And Build Of The Water Treatment Plant Including Raw Water Abstraction Facility And Pipeline, Product Pumping Station, Potable Water Transmission Pipeline, Power Supply, Metering House And Interconnection At The Delivery Points Shall Include But Not Be Limited To The Following: 1. Design And Construct A 3 Mld Raw Water Abstraction Facility And Raw Water Transmission Pipeline. 2. Design And Construct A 30,000 Cubic Meter Raw Water Impounding Lagoon. 3. Design And Construct A Water Treatment Plant (wtp) That Can Treat Raw Water With A Turbidity Of Up To 5,000 Ntu With 100% Water Recovery And Zero Effluent Discharge. 4. Design And Install A Product Pumping System That Will Pump The Potable Water To The Target Areas. 5. Design And Construct The Power Supply System Needed To Run The Water Treatment Facilities Inclusive Of 3-phase Power Transmission Line, Transformers And Standby Generator Set. 6. Design And Install Product Water Transmission Line And Distribution Line For The Target Service Areas. 7. The Product Pumping And Pipe Sizing Must Be Designed That There Will Be At Least 10 Psi During Peak Hours. 8. Conduct Soil Investigation And Topographic Survey Of The Wtp Site. 9. Design And Construct Associated Civil Works Including Site Development For The Water Treatment Facilities, Site Utilities, Water Supply, Sewer And Drainage System. The Civil Works Shall Include But Not Be Limited To Foundation Works, Formworks, Concreting, Painting And Fencing. 10. Design, Supply And Install All Mechanical And Electrical Components Including Lightning Protection System For The Water Treatment Facilities, Instrumentation And Control Equipment And Accessories That May Be Deemed Necessary For The Efficient And Ease Of Operation Of The Water Treatment Facilities. 11. Provide Appropriate Electromagnetic (if Applicable) Flow Metering Devices For Inflow And Outflow Measurements. 12. Design And Construct Support Facilities Such As Chemical Storage & Control Room, Fence, Road Network, Etc. 13. Supervise Commissioning And Performance Testing Of The Wtp For One (1) Month Upon Issuance Of Mechanical Completion. 14. All Other Works Which May Be Reasonably Implied Or Nor Explicitly Described But Are Needed To Have A Complete And Efficiently Functioning Plant Shall Be Implemented/constructed By The Contractor At No Additional Cost To The Procuring Entity. B. Performance Specifications Of The Water Treatment Facilities And Related Works 1. Design Flowrates The Water Treatment Facilities Shall Be Designed For A Capacity Of 3 Mld. 2. Required Treatment Facilities And Performance Efficiency A. The Treatment Plant Shall Produce Treated Water Effluent Conforming To The 2017 Philippine National Standards For Drinking Water (pnsdw) As Shown In Table Below. The Wtp, Intake And Related Facilities Shall Be Designed With Expected Life Of 25 Years. Table 1. 2017 Philippine National Standards For Drinking Water Parameter Unit Analysis Taste Unobjectionable Odor Unobjectionable Color Apparent Tcu 10 True Tcu 5 Turbidity Ntu 5 Aluminum Mg/l 0.20 Chloride Mg/l 250 Copper Mg/l 1.0 Hardness Mg/l 300 As Caco3 Hydrogen Sulfide Mg/l 0.05 Iron Mg/l 1.0 Manganese Mg/l 0.4 Ph 6.5-8.5 Sodium Mg/l 200 Sulfate Mg/l 250 Total Dissolve Solids Mg/l 600 Zinc Mg/l 5 Arsenic Mg/l 0.01 Boron Mg/l 0.5 Cadmium Mg/l 0.003 Lead Mg/l 0.01 Benzene Mg/l 0.01 E. Coli Or Thermo Tolerant (fecal) Coliform Bacteria No./100 Ml Nil B. Design And Operate The Plant Free From Any Discernable Odor And Noise Louder Than 55 Decibels At The Site Boundary. C. The Contractor Must Incorporate In The Design Of Its Wtp A Feature That Will Allow 100% Water Recovery And Zero Effluent Discharge D. The Annual Average Chemical Usage Should Not Exceed Php 1.00/m3 E. The Power Unit Usage Within The Proposed Wtp Battery Limit (excluding Intake And Product Pumping) Should Not Be More Than 0.15 Kwh/m3. F. The Raw Water Pipeline And Product Water Pipelines Must Withstand A Pressure Of At Least 100 Psi. 3. Minimum Design Requirement The Water Treatment Facilities Must Be Designed To Prevent Total Plant Shutdown When Undergoing Pump Maintenance Works. As Such, There Should Be At Least One Duty And One Stand-by Item Of Equipment To Allow The Plant To Operate At Any Given Time With A Full Process Flow Capacity At The Desired Efficiency During Equipment Replacement/repair Or Maintenance Servicing Or Cleaning. Equipment Upon Which The Plant Is Dependent For Full Operation Must Also Be Provided With Standby. A. Design All Plant Structures To Withstand Pressures And Seismic Loading In Accordance With The National Structural Code Of The Philippines. However, For Structural Concrete, The 28-day Compressive Strength Shall Not Be Less Than 21 Mpa. B. The Minimum Design Requirement For All Buildings Shall Be Concrete Foundations And Floors, Concrete Structural Elements, Galvanized Steel Trusses And Roof Frame, Reinforced And Filled Concrete Block Walls With Rendering And Painting, Bonded-color Steel Roofing System, Suspended Ceilings, Tiled Floors For Office Areas, Ceramic Tiling For Showers, Toilets And Similar Areas, Concealed And Under-floor Service Conduits And Pipelines And Air Conditioning For Office Areas. C. Electrical Power Supply And Control System And Requirements I. The Electrical Power Supply And Control System Shall Include But Not Limited To The Main And Branch Circuit Overcurrent Protective Devices, Motor Controllers Including All Protective And Monitoring Relay Systems Required For The Complete Operation Of The Plant And All Necessary Wiring, Conduits And Grounding Systems. Electrical Power And Control System Shall Be Wired So That The Various Items Of Plant Equipment Can Be Operated Either Manual Or Automatic To Achieve The Intended Sequence Of Operation. Process Control Shall Be Situated At The Motor Control Centers (mcc). Ii. Factory Wired Plant Components Shall Be Interconnected So As To Be An Integral Part Of The Plant. Iii. Provide Surge Protection To Prevent Damage To Electric Motors And All Other Electrical And Electronic Components During Fluctuation Of Voltage, During Resumption Of Power Supply After A Power Interruption And From The Effects Of Lightning. 4. Facilities Description And Specifications All Processes And Facilities Shall Be Designed To Meet The Performance Requirements For The Proposed Project. The Inter-connectivity Between Various Plant, Support Services And Structures Must Be An Integrated Approach To Meet Operational Performance, Flexibility, Maintenance And Reliability Criteria. The Power Unit Usage Within The Battery Limit Of The Proposed Wtp Shall Not Be More Than 0.07 Kwh/m3. The Water Treatment Plant May Include But Not Be Limited To The Following Main Process System, Support Systems And Relevant Facilities: A. Raw Water Abstraction Facility The Raw Water Abstraction Facility And Pipeline Shall Have A Capacity Of 3 Mld. The Natural Flow Of The River Shall Not Be Obstructed Or Changed By Constructing A Dam, Weir, Or A Similar Structure That Could Result To Flooding Of The Nearby Properties. The Abstraction Facility Shall Consist Of The Following: • Intake Weir, Water Collection Channel And Water Collection Well • 2 Units Submersible Non Clog Pump (1 Running And 1 Spare) With Motors And Variable Frequency Drive • Pipe Lay-out • Electrical Systems And Controls B. Raw Water Pipeline The Raw Water Pipeline Must Be Made Of Spiral Welded Steel Pipe. Pipes To Be Used Must Pass The Required Test Set By The Appropriate Authority. Pipes Shall Be Laid At A Minimum Depth Of 60 Cm. Pipe Sizing Should Be In Conformance To The Hydraulic Analysis C. Raw Water Impounding Lagoon The Impounding Lagoon Have A Capacity Of A Least 30,000 M3 And Will Be Lined With Hdpe Geosynthetic Lining The Lagoon Will Also Be Installed With The Pumping System That Will Pump Water From The Lagoon To The Water Treatment Plant. The Lagoon Pumping Station Will Comprise Of 2 Units (1 Pump Running And 1 Pump Spare) Submersible, Non-clog Pumps, With A Capacity Of 3mld And A Head Of 15 Meters. D. Water Treatment Plant The 3mld Water Treatment Plant (wtp) Must Be Able To Handle And Process Incoming Raw Water With Turbidity Levels Up To 5,000 Ntu. The Wtp Shall Include But Not Limited To Receiving Well, Mixing Channel, Flocculation Basin, Sedimentation Basin, Rapid Sand Filters, Chlorination, Chemical Dosing Equipment, Clear Water Tank And Sludge Management. The Wtp Shall Be Able To Produce An Effluent That Meets The Parameters Prescribed In The 2017 Philippine National Standards For Drinking Water (pnsdw). The Wtp Should Make Use Of Gravity Flow To The Extent Possible Which Minimizes The Use Of Energy For Pumping Resulting In Low Operation Costs. It Shall Incorporate A Zero Effluent Discharge Design And Will Make Use Of An Activated Filter Media System. • Receiving Well Provide A Receiving Well At The Proposed Wtp (with A Flow Measurement Or Device) To Receive Raw Water From The Intake Facilities. Pre-chlorination And Coagulant Dosing Shall Be Done At The Receiving Well • Rapid Mix-flocculation-sedimentation Provide A 2-stage Flocculation Chamber With Agitators For Proper Dispersion And Formation Of Flocs And A Sedimentation Basin For The Separation Of The Flocs By Gravity Settling. It Shall Have Provision For Removal Of Sludge. It Should Minimize Hydraulic Head Losses Between Units To Allow Future Changes In Processes Without The Need For Re-pumping. Rapid Mix The Rapid Mix Shall Mean The Rapid Dispersion Of Chemical Through The Water To Be Treated, Using Violent Agitation. The Tanks Should Be Made Of Concrete, Equipped With Devices Capable Of Adequate Mixing For All Process Treatment Flowrates. The Retention Time Should Not Be More Than 10 Seconds. The Rapid Mix Shall Be Designed In Close Proximity With The Flocculation Tanks. Flocculation Flocculation Shall Mean The Agitation Of Water At Low Velocities For Long Periods Of Time. Inlet And Outlet Of The Tanks Shall Be Designed That It Will Minimize Short-circuiting And Destruction Of Flocs. The Tanks Shall Be Made Of Concrete And Waterproof From Wall To Wall. Drain Or Pump Shall Be Provided To Handle Dewatering And Sludge Removal In A Short Period Of Time, When Necessary. The Inlet And Outlet Velocity Should Be Between 0.15 M/s, And 0.45 M/s With A Detention Time For Flocs Formation Of At Least 20 Minutes. Sedimentation Sedimentation Shall Follow Flocculation. The Following Criteria Shall Apply To Conventional Sedimentation Units: - The Sedimentation Tank Shall Complete With Inlet And Outlet Structures, Sludge Collection And Removal Mechanism, Isolation Valves And Gates, Drainage And Safety Ladder, Catwalks And Manholes. - The Surface Overflow Or Settling Rate Should Not Be More Than 2.0 M/h. - Inlet Shall Be Designed To Distribute The Water Equally And Uniformly. The Inlet Velocity To The Sedimentation Tanks Should Not Be More Than 0.3 M/s. - Basins Should Be Provided With Sludge Collection And Removal Mechanism. Valves Shall Be Provided To Isolate For Maintenance Purposes. It Shall Be Designed To Eliminate Or Minimize Clogging. Cleaning Or Removal Of Sludge Through The Use Of Sludge Disposal Pump Shall Be Designed In Such A Way That It Could Be Facilitated/completed In A Short Period Of Time. The Sludge Shall Be Conveyed To The Sludge Lagoon Through The Drainage Facilities. • Filtration System The Filtration System Shall Serve As The Final Stage Of Treatment To Remove Suspended Solids And Colloids. It Shall Compose Of The Activate Media Filter System. The Proposed Filter Shall Also Include The Following: A Minimum Of 8 Units Of Filters With Capability To Meet Plant Capacity Even If One (1) Filter Is Taken Out For Service Or Backwashing; An Automatic Backwashing System Complete With Controls And Motorized Gates And Valves; Wash Water Collection System And An Underdrain System That Efficiently Collect The Filtered Water. Filter Run Time Should Be Between 24 And 72 Hours. Each Filter Bed Shall Be Designed For A Filtration Hydraulic Loading Rate Of Not More Than 12 M3/m2-hr When One Filter Is Out Of Service. The Multimedia Filter Shall Operate 24 Hours Per Day Whole Year Round At The Design Capacity Of 3 Mld Regardless Of The Quality Of The Raw Water. The Filter System Shall Be Designed Such That No Power Is Required During Normal Operation And During Backwash Time. The Production Capacity Of The Filtration System Should Not Be Affected And Remains The Same At 3 Mld Even When One Cell Is Undergoing Backwash Operation. - The Filtration System Shall Be Structurally Designed Sound And Safe, Made Of Reinforced Concrete, Complete With Vertical Walls Within The Filter With No Protrusion Of The Filter Walls Within The Filter Media; Head Room To Permit Normal Inspection And Operation; Walkways, Ladder Rungs And Manhole Covers Shall Be Provided As Necessary For Easy Access And Maintenance. Walkways Shall Be Provided With Stainless Steel Safely Handrails. - Appurtenances The Following Shall Be Provided For Each Filter Cell: Water Inflow Control, Backwashing Pipes And Valves, Underdrain That Will Allow Filtered Water To Flow By Gravity At Wtp Capacity And Reverse Flow During Backwashing By Gravity To Remove Accumulated Sludge. • Disinfection Facility The Disinfection Facility Shall Cover The Pre Chlorination And Post Chlorination Requirement Of The Water Treatment Plant. Provide A Disinfection System That Will Be Used To Kill Pathogenic Microorganisms. There Should Be Sufficient Excess Of Chlorine For Disinfection Including A Free Residual Chlorine Concentration Of 0.5 – 0.7 Mg/l. The Disinfection System Shall Include All Equipment Such As Chlorine Dosing Pump And Other Miscellaneous Items Necessary For Disinfection Using Granular Chlorine. The Chemical Dosing System Shall Be Located Near The Receiving Well. A Storage Area Of Capable Of Handling At Least 30 Days Of Chemical Shall Be Provided. The Disinfection Facility Shall Be Capable Of Applying The Following Dosages At The Plant’s Design Flow Rate: Minimum Dose 0.30 Ppm Average Dose 1.00 Ppm Maximum Dose 5.00 Ppm • Chemical Feeding System Provide Complete Chemical Feeding System For Dissolving And Injecting Various Chemicals To Support The Rapid Mix And Coagulation Process. Include Batch Tanks, Storage Tanks, Mechanical Mixers, Metering Screws, Pipe Work, Valves, Fittings And Associated Equipment. The Feeding Systems Shall Be Located Inside The Chemical Building. The System Shall Be Arranged To Accept Chemical Supply In Both Liquid And Powder Forms. Equip The System With Ladders, Walkways, Platforms, Handrails And Cages To Allow Safe Access To The Equipment For Operations Staff. Locate Standpipes And Hoses Near The Equipment For Maintenance. E. Sludge Lagoon The Sludge Lagoon, Or The Residual Management Facility Must Have A Capacity Of At Least 500 M3. This Must Be Designed That There Is 100% Water Recovery And Zero Effluent Discharge. F. Product Pumping Station The Treated Potable Water Will Be Pumped To The Target Service Areas With A Residual Pressure Of No Less Than 10 Psi During Peak Hours. Two Units Of Centrifugal Pump Should Be Installed (1 Running And 1 Spare) Capable Of Delivering The Requirement 3 Mld. G. Power Supply Power Supply Facility Is Inclusive But Not Limited To The Following: • 3- Phase Line With Primary Voltage Recloser (depending On Electric Cooperative Requirement) • Distribution Transformer • Stand By Generator Set With Automatic Transfer Switch The Specifications Of The Transformers And Generator Set Must Be Based On The Calculations On The Total Load Of The Whole Water Treatment Facility. H. Product Water Transmission Pipeline The Potable Water Pipeline Must Be Made Of Hdpe Pipe. Pipes To Be Used Must Pass The Required Test Set By The Appropriate Authority. Pipes Shall Be Laid At A Minimum Depth Of 60 Cm. Pipe Sizing Should Be In Conformance To The Hydraulic Analysis. Quality Assurance For Buttfuse Works Must Be Performed To Ensure That There Will Be No Leaking During Operation. The Pipes Must Be Able To Withstand A Pressure Of No Less Than 100 Psi. Estimated Length Are As Follows: Description Length 10” Mm Ø 2,058 Meters 8” Mm Ø 1,254 Meters 6” Mm Ø 3,882 Meters 4” Mm Ø 464 Meters I. Product Water Distribution Lines, Valves, Fittings And Other Appurtenances The Potable Water Pipeline Must Be Made Of Hdpe Pipe. Pipes To Be Used Must Pass The Required Test Set By The Appropriate Authority. Pipes Shall Be Laid At A Minimum Depth Of 60 Cm. Pipe Sizing Should Be In Conformance To The Hydraulic Analysis. Quality Assurance For Buttfuse Works Must Be Performed To Ensure That There Will Be No Leaking During Operation. The Pipes Must Be Able To Withstand A Pressure Of No Less Than 100 Psi. Corresponding Valves And Fittings Ang Interconnection To The Main Transmission Line Must Be Installed. Estimated Length Are As Follows: Description Length 3” Mm Ø 3,756 Meters 2” Mm Ø 6,900 Meters J. Auxiliary Facilities I. Chemical Storage The Storage Area Should Be Able To Handle Various Chemicals For 30 Days Plant Operation At Full Capacity. The Building Should Satisfy And Follow All The Necessary Safety Requirements In The Operation Of The Chemical Building. Ii. Fence Provide Inter-link Fence Around Entire Parameter Of The Plant Site. Locate Fence To The Correct Boundary And Provide Certified Survey Of Fence After Installation. Include Vehicular Gate At Entrance Roadway And An Adjacent Personnel Gate With Gate Restraints, Chains And Locks. Perimeter Lighting Shall Also Be Provided. Iii. Road Provide Paved Road Network Servicing All Areas Of The Plant And Incorporating Geometric Design And Traffic Management Features To Ensure A Free Flow Of Vehicles. Iv. Support Systems Potable Water Supply System Provide A Complete Potable Water Supply System For Drinking Water, Staff Amenities, Chemical Dilution, Cleaning, Toilets, Lavatories, Essential Process Requirements, Fire Lighting And All Other Applications. Water Shall Come From The Product Water Tank. Drainage System Provide Complete Drainage System (to Flow By Gravity) For All The Buildings, Road Networks, Water Treatment Perimeter, And Essential Area. A Separate Drainage System Shall Be Provided To Convey (by Gravity) The Sludge From The Sedimentation Basin And The Backwash Water From The Rapid Sand Filler And Other Waste Water From The Proposed Wtp Into The Sludge Lagoon Located At The Nearby Existing Wtp. Electrical Power And Control System Provide A Complete Electrical And Control System For The Plant Including The Site. Fire Control & Alarm System Provide A Complete Fire Protection Such As Smoke Detector And Alarm System In All Buildings, Control Room, Laboratory And Related Facilities And Shall Be Complying With The National Building Code Of The Philippines. Provide Fire Extinguishers At Strategic Location Inside The Plant And Support Structures. The Alarm System Shall Be Designed Audible To A Minimum Distance Of 30 Meters. Lightning Protection And Grounding System V. Miscellaneous Items That Are Deemed Necessary Provide All Necessary Items/works To Have A Complete And Efficiently Functioning Plant. 5. Process Performance Test And Guarantee, Proving And Warrantees A. After The Issuance Of The Certificate Of Completion, The Contractor Shall Supervise The Performance Testing Of The Wtp And Training Of The Procuring Entity Personnel Within A Period Of One (1) Month. The Procuring Entity Shall Supply The Operation And Maintenance Manpower And All Materials, Utilities Including Power, Fuel, Lubricants, Chemicals, Facilities, Services And Other Items Needed To Operate And Maintain The Plant. The Contractor Shall Be Responsible For The Cost Of Parts Or The Facility That May Have To Be Replaced During The Proving Period. B. The Contractor Shall For Thirty (30) Consecutive Day Demonstrate That The Completed Wtp Shall Operate In Accordance To Stated Performance Specifications And Parameters. C. The Contractor Shall Be Responsible For Making All Remedial Measures To Bring The Plant Performance And Efficiency To The Specified Level. Failure Of The Contractor To Complete All Remedial Measures Shall Authorize The Procuring Entity To Confiscate The Performance Security Or The Performance Guarantee Bond As The Case May Be And To Retain All Monies Due To The Contractor Without Prejudice To Procuring Entity's Right To File A Damage Suit. D. The Power Unit Cost Per Cubic Meter Of Treated Water At The Proposed Wtp Battery Limit Should Not Be More Than 0.15 Kwh/m3 E. The Annual Average Chemical Usage Should Not Exceed Php 1.00/m3 F. The Contractor Shall Provide One (1) Year Mechanical Warranty. G. The Contractor Shall Provide Lifetime Technical Advisory Service To The Procuring Entity. Xi. Bid Proposal Inclusions In The Preparation Of The Proposal, The Bidder Should Ensure That The Following Are Included In The Submission: 1. Technical Drawings A) Process Flow Diagram And P&id B) Site Development Plan C) Key Components Lay-out Plan D) Electrical Sld And Estimated Energy Requirement E) Conceptual Drawings And 3d Rendition Of The Water Treatment Plant And Other Facilities 2. Schedules A) Pert/cpm Network And Bar Chart/s-curve Schedule (design Stage And Construction Stage Should Be Well Defined In The Schedule. B) Manpower And Equipment Schedule C) Financial Periodic Cash Requirement 3. Capital Expenditures Proposal The Bid Should Have A Detailed Cost Breakdown Of The Components Of The Project: A) Detailed Engineering Design B) Water Treatment Plant C) Support Facilities D) Wastewater And Sludge Management Facility E) Utility Power Supply Including Transformers And Transformer Pad. F) Site Development (fencing, Road Network, Lightings, Drainage, Etc.) G) Commissioning And Testing H) Proving Period Cost Of The Inclusions Such As Hydrological And Geotechnical Studies, Site Surveys, And Insurances, May Be Individually Included In The Cost Breakdown Of The Components Where It Will Be Used. Proposal Should Also Include The Cost Of One (1) Month Of Testing And Commissioning. Cost Of Electricity And Chemicals To Be Used During The One-month Period Of Proof Of System Operations And De-bugging Must Be Become By The Bidder 4. Operations Expenditures Breakdown A Detailed Breakdown Of The Operations Expense Should Be Submitted With The Following Specifications: A) Power: • Include The Estimated Electric Consumption Starting From The Intake And The Wtp Process – Including Wastewater And Sludge Management Facility; • Electric Consumption Should Be Stated In Kwh Per Cubic Meter; • Electric Consumption Should Also Be Stated As A Philippine Peso Value Per Cubic Meter Using Php 9.00 Per Kwh As The Electric Cost. B) Chemicals: • Breakdown Of Chemical Consumption Per Cubic Meter Should Be Presented; • Chemical Consumption Per Cubic Meter Should Be Stated In Philippine Peso Value; Xii. Ded Submittal 1. Design Report, Construction And Shop Drawings A. The Design Report Shall Contain All Engineering Design Details Related To The Project Including Electrical And Mechanical Design, Structural Design And Bill Of Materials. All Design Calculations Shall Be Orderly Compiled And Submitted To The Procuring Entity As An Integral Part Of The Design Report. B. The Technical Specifications Of The Major Equipment Should Be Submitted C. The Drawings Shall Show The Complete Assembly Of The Plant With All The Equipment And Appurtenant Components. The Layout Shall Indicate The Relative Location Of The Plant With Respect To The Boundary Of The Lot. D. The Drawings Shall Show Complete Construction Details For Each Component, Piece Of Equipment, Support Structure And Access Facilities. 2. Drawings A. Drawings For Approval Drawings To Be Submitted By The Winning Bidder For Approval Shall Be Of Size A3. 3. Operation & Maintenance Manuals And List Of Spare Parts Prepare And Submit Draft Operation And Maintenance Manual With Lists Of Spare Parts For The Plant Including All Equipment, Thirty (30) Calendar Days Before The Intended Completion Date. Submit The Completed Operation And Maintenance Manual Within Two Weeks Of Receiving Review Comments In The Form Of Two Digital Copies On Cd And Four Hard Copies Using The Latest Versions Of Word And Autocad With Supplementary Drawing And Image Files In Pdf Format. Manuals Shall Be In Metric, A4 In Size With Three Ring Binders With Durable Hard Covers. Drawings Shall Be In Metric, A3 Size Covers And Held Together Using Three Removable Brass Male/female Screws. All Drawings Shall Be In A3 Size. The Operation And Maintenance Manuals Shall: I. Cover All Aspects Of The Works Ii. Provide 'general Principles Of Operation' For The Plant. The General Principles Of Operation Shall Be Prepared By The Designers And Should Include The Necessary Information For Operators To Effectively Operate And Maintain The Works. Iii. Incorporate Safety, Environmental And Quality Issues. Iv. Have Detailed Indexes And Cross Referencing. V. The Operations Manual And The Maintenance Manual Shall Be Bounded Separately. A. Operation Manual A Single Operation Manual Shall Be Provided For The Operation Of The Plant. The Manual Shall Include But Not Be Limited To: I. Title Page: Project, Procuring Entity's And Contractor’s Name, Address And Telephone Number And Contract Number. Ii. Index: Include A Comprehensive Index Iii. General Description • Location • Site Layout, Process And Instrumentation Diagrams, Hydraulic Profile • Description Of Process And Effluent Criteria • Design Criteria Iv. Safety Management V. Environmental Management Vi. Detail Operation (for Each Process Unit) • Describe Each Process Unit Including Size And Number Of Mechanical/ Electrical Units • Mode Of Operation (start, Shutdown, Manual And Auto Control) • Performance Criteria For Each Process Unit/facility • Sampling Points • Troubleshooting • Record Keeping Requirements • Duty Statements (for Operators) • Operating Procedures (covering Safely And Environmental Procedures) • Environmental And Emergency Response • Sampling And Monitoring Requirements - Include Performance Criteria For Each Process Unit - Monitoring Of The Receiving Environment (waterways, Noise And Odors) • Cross Reference To Maintenance Manuals - Provide Maintenance Manuals To Support This Operations Manual For All Mechanical And Electrical Equipment. B. Maintenance Manual Prepare Maintenance Manuals For All Individual Items Of Equipment. The Manuals Shall Include But Not Be Limited To: I. Title Page: Project, Procuring Entity's Name, Address And Telephone Number, Contractor's Name, Address And Telephone Number And Contract Number. Ii. Index: Include A Comprehensive Index. Iii. Description: A Full Description Of The Equipment With A Tabulation Of Dimensions And Performance Ratings. Iv. Principles Of Operation: Basic Working Description, Including Novel Features And Any Automatic Control. V. Operating Instructions: A Step-by-step Procedure Organized In Sections Containing The Following: • Pre-start Check-up • Starting • Continuous Operation • Stopping • Emergency Stopping • Abnormal Operation (as Applicable) Vi. Installation And Commissioning Instructions: Details Of Standards And Procedures For Transporting And Installing The Equipment. Including A Step-by-step Procedure For Mounting Or Erecting, Wiring And Lubricating The Equipment. Alignment Tolerances And Check Requirements Shall Be Stated. Vii. The Commissioning Instructions Shall Include Step By Step Procedures Before And During Start-up, After Starting And Operational Tests During Continuous Operation. Viii. Routine Maintenance - Step By Step Procedure For Preventive Maintenance Work Carried Out At Intervals Of 2 Weeks Or Less. Ix. Periodic Maintenance: Step By Step Procedure For Fault Correction And Preventive Maintenance Carried Out At Intervals In Excess Of Two Weeks, Involving Replacement Of Spare Parts And Consumables. A List Of Special Tools Shall Be Included. X. Test Data And Troubleshooting: Instructions To Qualified Tradesmen For Assessing The Operational Performance Of The Equipment. Xi. Spare Parts List: Illustrations And Schedules For Identification And Specifications Of All Items In The Equipment. Exploded Diagrams Are Required. The Recommended Spare Parts Stock For One Year Shall Be Indicated. Xiii. Personnel & Equipment Requirement The Bidder Must Demonstrate That It Has Designed And Constructed Similar Water Treatment Facilities And Has The Personnel For The Key Positions That Meet The Following Requirements: Item Position Total Work Experience (years) Similar Work Experience (years) 1 Project Manager 10 5 Design 2 Water Treatment Specialist (chemical Engineer) 5 3 3 Sanitary Engineer 5 2 4 Professional Mechanical Engineer 5 3 5 Professional Electrical Engineer 5 3 6 Structural Engineer 5 2 Build 7 Project Engineer 5 3 8 Civil Engineer 5 3 9 Mechanical Engineer 5 3 10 Electrical Engineer 5 3 11 Safety Officer 5 2 The Contractor Shall Provide Details Of The Proposed Personnel And Their Experience Records. C. Equipment The Contractor Must Demonstrate That It Will Have Access To The Key Equipment Listed Hereafter: Item Equipment Type And Characteristics Quantity 1 Dump Truck 1 2 Backhoe 1 3 Roller Compactor 1 4 Concrete Vibrator 1 5 Bagger Mixer 2 6 Bar Cutter 1 7 Welding Machine 1 8 Boom Truck 1
Closing Date17 Mar 2025
Tender AmountPHP 115 Million (USD 2 Million)

City Of Koronadal Water District Tender

Civil And Construction...+1Excavation
Philippines
Details: Description A. General A. Technical Definitions The Following Definitions Shall Apply: 1. Borehole - Means Any Drilled Section Of Boring Before Completion As Defined In Well Below. 2. Casing - Means Unslotted Or Non-perforated Lining Tubes. 3. Development Equipment - Means High Velocity Jetting Tool, Airlift Equipment, Surge Plunger And All Other Equipment Needed To Develop The Well. 4. Diameters - Means Nominal Diameters Unless Otherwise Stated. 5. Drilling Rig - Means The Drilling Equipment And The Auxiliary Equipment For Its Operation. 6. Drilling Unit - As Defined In Section B.b. 7. Final Well Design - Means The Drawing And Description Prepared By The Engineer Upon Completion Of Drilling Specifying The Final Well Construction. 8. Lining Materials - Means Any Casing, Screen, Slotted Lining Or Perforated Lining Tube Whether Permanently Or Temporarily Installed In The Borehole. 9. Pumping Unit - As Defined In Section H.g. 10. Screens - Means Continuous Wirewound Stainless Or Low Carbon Steel Screens, Or Slotted Or Perforated Lining Tube. 11. Preliminary/tentative Well Design - Means The Contract Drawing Showing The Estimated Quantities Of The Work. 12. Well - Means Any Completed Hole In Which All Lining Material Has Been Set, All Grouting Completed And All Temporary Lining Removed. B. Technical Standards All Materials Or Workmanship Shall Comply With The Specifications. Other Standards Equal Or Superior To Those Enumerated In This Specification, Shall Be Acceptable, Subject To The Approval Of The Engineer. The Opinion Of The Engineer Must Be Obtained Prior To Utilizing Such Materials Or Workmanship On Or Off The Site. C. Water Supply And Illumination In The Absence Of Adequate Quantities Of Water Or Illumination Required For Drilling At The Drilling Site, The Contractor Shall Make Such Arrangements Including The Provision For Mobile Tanks Or Fixed Tanks As May Be Necessary To Ensure A Supply Of Water And Illumination Sufficient For Drilling Operations. D. Electrical Power Supply 1. The Contractor Will Make Arrangements As May Be Necessary For The Connection Of Or Supply Of Power To The Site. 2. Payment For The Provision Of Electrical Power Supplies As Specified In Section A.d.1. Shall Be Deemed To Be Included In The Rates Entered In The Bid Form For Setting Up Equipment At The Site, Drilling Rates And Rates Entered For Operation Of Pumping Unit. E. Storage Of Inflammables The Contractor Shall Comply With All Local Authority Regulations Applicable To The Use And Storage Of Diesel Oils, Petrol, Paraffin And Other Inflammable Fuels Used By Him/her On The Site, And Shall Ensure That Adequate Precautions Are Taken Against Fire. F. Boundaries Of Work The Owner Shall Provide Land Or Rights-of-way For The Work Specified In This Contract And Make Suitable Provisions For Ingress And Egress, And The Contractor Shall Not Enter Or Occupy With Men, Tools, Equipment Or Material, Any Ground Outside The Property Of The Owner Without The Written Consent Of The Owner Of Such Property. Other Contractors And Employees Or Agents Of Ckwd And/or The Owner May, For All Necessary Purposes, Enter Upon The Work And Premises Used By The Contractor, And The Contractor Shall Conduct His/her Work So As Not To Impede Unnecessarily Any Work Being Done By Others On Or Adjacent To The Site. G. Access Roads Construction Or Improvement Of Access Roads To The Wells Shall, Unless Otherwise Agreed, Be Done By The Contractor At His/her Own Cost, Which Is Deemed To Be Included In The Contract Sum. The Access Road Shall Be Kept In Proper Condition During The Entire Construction Period. H. Protection Of Site 1. Except As Otherwise Provided Herein, The Contractor Shall Protect All Structures, Walks, Pipelines, Trees, Shrubberies, Lawns, Etc., During The Progress Of His/her Work, Shall Remove From The Site All Drill Cuttings, Debris, And Unused Materials, And Shall Upon The Completion Of The Work Restore The Site As Nearly As Possible To Its Original Condition, Including Removal Of Access Tracks And The Replacement, At The Contractor's Sole Expense, Of Any Facility Or Landscaping Which Has Been Damaged Beyond Restoration To Its Original Condition, All To The Satisfaction Of The Engineer. 2. Water Pumped From The Well Shall Be Conducted To A Place Approved By The Engineer Where It Will Be Possible To Dispose The Water Without Damage To Property Or Creation Of A Nuisance. I. Site To Be Kept Tidy The Contractor Shall, At All Times, Keep The Site And All Working Areas In A Tidy And Workmanship Condition And Free From Rubbish And Waste Materials. J. Temporary Buildings For Use By Contractor The Contractor Shall Provide At The Site Of The Works Such Temporary Buildings, Tanks, Workshops, Etc. As May Be Necessary And Proper For His/her General Use In Connection With The Works, And For The Use Of Persons Employed By Him/her. The Nature Of The Buildings, Tanks, Etc. And The Positioning Of Them Shall Be Subject To The Prior Approval Of The Engineer And The Relevant Authorities. K. Shop Drawings 1. The Contractor Shall If Requested By The Engineer Prior To Start Of Each Operation, Produce For The Engineer's Approval Shop Drawings Showing Details Of Technical Operations Such As Test Of Plumbness And Alignment, The Method Of The Slotted Casing Production, If So Required, The Methods Of Placement Of Formation Stabilizer And/or Cement Grout, The Arrangement For Well Testing, The Method For Well Development And All Other Drawings Pertinent To The Well Drilling, Well Construction Operations And Well Development As Requested By The Engineer. 2. Shop Drawings Shall Be Completed With Respect To Dimensions, Design Criteria, Materials, Methods Of Constructions And The Like To Enable The Engineer To Review The Information As Required. L. Well Head Protection 1. At All Times During The Progress Of The Work, The Contractor Shall Protect The Well In Such Manner As To Effectively Prevent Either Tampering With The Well Or The Entrance Of Foreign Matter Into It, And Upon Its Completion He Shall Provide And Install A Well Head Cap Satisfactory To The Engineer. 2. In The Event That The Well Becomes Contaminated Or That Water Having Undesirable Physical Or Chemical Characteristics Has Entered The Well Due To The Negligence Of The Contractor, He/she Shall At His/her Own Expense Perform Such Work Or Supply Casings, Seals, Sterilizing Agents Or Other Materials As May Be Necessary To Eliminate The Contamination Or To Exclude Any Undesirable Water In The Well. M. Transport Of Personnel And Equipment 1. The Contractor Shall Supply And Operate All Transport Required For Transporting His/her Employees, Materials And Equipment. 2. The Cost Of Movement Of Personnel, Materials And Equipment Shall Be Included In The Rates Given For Drilling, Development And Pump Operation. N. Site Preparation And Reinstatement 1. The Contractor Shall Prepare The Site, Provide All Necessary Tanks And Pits And Make All Necessary Arrangements For Erecting And Dismantling The Drilling Unit And Shall Reinstate The Site On Completion Of Such Phase Of Work To The Satisfaction Of The Engineer. 2. Payment Shall Be Deemed To Be Included In The Items Entered In The Bid Form For Erection And Dismantling Of Drilling Rigs. O. Standing Time Standing Time Will Be Paid Only When Drilling Is Suspended On The Written Instruction Of The Engineer Beyond Ten (10) Days Cumulative And For Reasons Not Attributable To The Contractor. B. Well Drilling A. Scope 1. The Contractor Shall Provide And Operate Three Or More Mobile Rotary Drilling Units Required To Complete The Works Within The Ninety (90) Calendar Day Contract Period. 2. The Contractor Shall Provide All Auxiliary Equipment, Lubricants, Fuels And Spares Necessary To Keep The Drilling Rig(s) In Continuous Operation. B. Equipment 1. The Drilling Rig(s) Together With All Auxiliary Equipment And Personnel Shall Be Defined As The Drilling Unit(s). 2. The Drilling Rig(s) Together With All Auxiliary Equipment Must Be In Good Working Condition And The Rig Mast Should Have A Vertical Height Of At Least Ten (10) Meters. 3. All Rigs Shall Have Sufficient Capacity To Drill The Specified Borehole(s) In The Diameters Specified In The Tentative Well Design(s) To A Depth Which Is Min. 25% Higher Than Indicated In The Contract Drawings. 4. Payment For Drilling Will Be By The Linear Meter Of Borehole As Measured After Removal Of Drill String. The Rates Set Against Drilling Items In The Bid Form Shall Be Deemed To Include All Equipment, Personnel, Fuels And Lubricants And The Accessories Required For Operation Of The Drilling Unit. 5. When The Drilling Unit Is Being Used For A Purpose Other Than Drilling, Then The Rates For That Purpose Entered In The Bid Form Shall Be Deemed To Include The Running Costs Of The Drilling Unit. C. Drilling Method 1. All Drilling Shall, Unless Otherwise Specified In The Special Conditions Of The Contract, Be Performed With The Rotary Drilling Method. 2. The Contractor Shall Drill The Hole To Such Depth And With Such A Diameter Which Shall Enable An Easy Installation Of Casing And Screen And Placement Of Gravel Envelope With A Uniform Thickness As Specified, If Required. During Drilling Of The Hole, The Contractor Shall Ensure That The Natural Permeability Of The Yielding Strata Near The Well Bore Is Not Irreversibly Reduced Due To The Drilling Method Employed. D. Strata Sampling 1. Strata Samples Shall Be Taken At 1 Meter Intervals Or More Frequent If The Formation Penetrated Changes. Samples Shall Be Placed In Plastic Or Other Appropriate Bags On Which Or In Which The Sampling Depth And The Date Of Sampling Is Written In Such A Manner That It Is Permanently Readable. 2. The Sampling Procedure Must Provide That All The Fractions Of The Penetrated Strata Are Present In The Sample. 3. Each Sample Shall Be Placed In A Wooden Box With Space For Storage Of One Sample And The Sampling Depth Shall Be Written On The Box. 4. A Record Of Samples Taken With The Details Described Above, Shall Be Submitted To The Engineer Everyday. 5. Payment For Sampling Shall Be Deemed To Be Included In The Rates Entered For Drilling In The Bid Form. 6. The Failure On The Part Of The Contractor To Obtain, Preserve And Deliver Samples Or Records, Satisfactory To The Engineer, Shall Be Considered As Actual Damage To The Owner. In The Event That, In The Opinion Of The Engineer, The Failure Of The Contractor To Take And Preserve The Samples May Affect The Proper Design Of The Well, The Contractor May Be Required To Perform Such Work As The Engineer Deems Necessary To Remedy Such Failure At No Cost To The Owner. E. Drilling Mud 1. Biodegradable Mud (revert® Or Similar) Should Be Used And Shall Be The Basis For The Priced Offer. The Contractor Is To Specify The Kind And Make Of The Additive And Its Properties In Section Vi Of The Bidding Documents. 2. Bentonite, If Used, Shall Be Of Premium Quality In Accordance With Api Standard 13a With 150 Kg/cum Of Make-up Water Yielding A Mud With A Viscosity Of Between 35 And 40 Seconds Using A Marsh Funnel And A Mud Weight Of Less Than 1.10 Kg/l (9.2 Lb/us Gal.). 3. Make-up Water Shall Be Treated With Caustic Soda (soda Ash) To Maintain The Ph Between 8.0 And 9.0 Prior To Mixing Mud. 4. During Drilling With Mud The Contractor Shall Perform Hourly Or Per Meter (as Directed By The Engineer) Measurements Of The Following Mud Characteristics: - Ph Value - Specific Gravity - Sand Content - Filtration Loss - Filter Cake Thickness - Funnel Viscosity The Recorded Mud Characteristics Shall Not Exceed The Following Values, Without The Prior Approval Of The Engineer: - Specific Gravity : 9.5 Lb/gal. (1142 Kg/m3) - Sand Content : 4% - Filtration Loss : 10 Ml - Filter Cake : 1.5 Mm F. Working Hours All Work From Start Of Drilling Of The Borehole Until Completion Of Well Development Shall, If The Rotary Drilling Method Is Applied, Be On A Round The Clock Basis. C. Geophysical Logging A. Scope The Contractor Shall, If Specified In The Special Conditions Of The Contract, Perform Geophysical Logging As Specified In The Special Conditions Of The Contract. B. Equipment 1. The Geophysical Logs May Be Recorded Either By Automatic Recording On A Chart Strip Or By Manual Reading Of Recorded Values. In Case The Logs Are Recorded By The Manual Method, Readings Shall Be Taken Per Min. 0.33 M Of Borehole Length. 2. The Recorded Logs Shall Be Submitted To The Engineer Immediately Upon Completion Of Logging As Plots Of Recorded Characteristics Versus Depth For His/her Approval. In Case Of Disapproval By The Engineer, The Logs Shall Be Repeated Immediately. C. Logs Geophysical Logging Shall, Unless Otherwise Specified In The Special Conditions Of The Contract, Comprise The Following Logs: Caliper Log Resistivity Log (16" And 64") Gamma Ray Log Self-potential Log (sp) D. Well Casing A. Scope The Contractor Shall Provide And Install The Well Casing Specified In The Contract Drawings And Any Temporary Casing Required During The Work, Unless Otherwise Specified In The Special Conditions Of The Contract. B. Casing Material 1. The Contractor Shall, Before Commencement Of Work, Submit For The Approval Of The Engineer The Following Details Of All Casing: A. Type Of Material B. Internal And External Diameters C. Wall Thickness D. Method Of Jointing E. Name Of Manufacturer F. Standard The Pipe Is Manufactured To 2. All Permanent Casing Material Shall Be Spiral Welded And Of New Stock Unless Otherwise Specified In These Documents. 3. The Contractor Shall Assume Responsibility For Any Casing Failure And Shall Correct, As Approved By The Engineer, Any Casing Failure At No Cost To The Owner. In The Event That The Contractor Cannot Correct A Casing Failure, The Contractor Shall Replace The Casing With Material Complying With The Specifications, Or If Necessary, Better Casing As Approved By The Engineer At No Extra Cost For Ckwd. C. Temporary Casing The Contractor Shall Provide Such Temporary Casing As May Be Necessary To Prevent The Collapse Of Any Formation During The Drilling Operation To Allow The Well To Be Sunk To The Specified Depth And To Allow The Insertion Of Permanent Lining Material As Required. The Contractor Shall Remove The Temporary Casing Before Completing The Well, Unless Otherwise Specified In These Documents. D. Lining Installation 1. Lining Material Shall Be Assembled And Located In The Well At The Required Depth In A Continuous Operation. The Lining Material Shall Be Set Concentric Within The Borehole By Centralizing Bars Unless Otherwise Agreed With The Engineer. 2. If The Lining Jams Or Is Lost Before It Is Set To The Specified Depth, The Contractor Shall Endeavor To Remove The Lining Material From The Well Or, If Unable To Effect Removal, Shall Redrill The Well And Replace The Lining Material At His/her Own Expense. E. Lining Material Accessories 1. The Contractor Shall Provide As Necessary The Following Accessories To Set The Lining Material To The Required Depth: A. Centralizers To Be Affixed To The Lining Material At Intervals Of 12 M To Locate The Lining Material In The Center Of The Drill Hole; B. Supporting Clamps, Equipment And Tools; C. Reducing Cones And Connecting Pieces; D. Casing Hangers E. All Other Necessary Equipment. 2. Except Where Expressly Provided, All Accessories Shall Be Deemed To Be Included In The Bid Form For The Provision And Insertion Of Lining Material. F. Testing For Plumbness And Alignment 1. All Boreholes Shall Be Constructed, Plumb And True To Line As Defined Herein. To Demonstrate The Compliance Of His/her Work With This Requirement, The Contractor Shall Furnish All Labor, Tools And Equipment And Shall Provide The Detailed Drawings And The Description Of The Tests To The Satisfaction Of The Engineer. 2. Tests For Plumbness And Alignment Must Be Made After The Complete Construction Of The Well And Before Its Acceptance. Additional Tests, However, May Be Made By The Contractor During The Performance Of The Work. No Specific Payments Shall Be Made For Making These Tests. 3. Should The Results Of The Tests For Plumbness And Alignment Show That The Plumb Bob Or Dummy Fails To Move Freely Throughout The Length Of The Lining Or Borehole To A Depth Of The Lowest Anticipated Pump Setting And Should The Well Vary From The Vertical In Excess Of Two-thirds Of The Smallest Inside Diameter Of That Part Of The Well Being Tested Or Beyond The Limitations Of This Test, The Plumbness And Alignment Of The Well Shall Be Corrected By The Contractor At His/her Own Expense. Should The Contractor Fail To Correct Such Faulty Alignment Or Plumbness, The Engineer May Refuse To Accept The Well And The Contractor Shall Drill A New Well Without Charge To Ckwd And/or The Owner. E. Well Screens A. Scope The Contractor Shall Provide And Install The Well Screens Specified In The Contract Drawings, Unless Otherwise Specified In The Special Technical Conditions. B. Type Of Screens 1. The Type Of Screens Shall Be As Specified In The Contract Drawings And The Special Technical Conditions. 2. Slotted Screens, If Specified For Installation, Shall Be So Fabricated As To Ensure The Maximum Yield Of The Well And To Prevent Clogging And Encrustation And Shall Be Free From Jagged Edges And Irregularities That May Accelerate Clogging Or Corrosion. C. Responsibility For Malfunction 1. The Contractor Shall Assume Full Responsibility For Any Malfunction Of The Screen Caused By Inadequate Installation Procedure And Shall Undertake Any Correction As Approved By The Engineer At No Extra Cost To The Owner. 2. The Screen Must Have No Change Of Alignment At Any Of Its Joints After Installation. If Requested By The Engineer, The Contractor Shall Submit For Approval By The Engineer The Design And Method Of Construction And Installation Of The Screen. 3. In The Event That The Contractor Cannot Correct A Screen Failure, The Contractor Shall Replace The Screen With Material Complying With The Specifications Of This Contract At No Extra Cost To The Owner. D. Screen Strength The Screens Shall Have Adequate Strength To Resist The External Forces That May Be Applied During And After Installation. E. Screen Accessories All Fittings, Packers, Couplings, Joints, Plugs And Seals Used During Installation Of Well Screen Together With The Installation Procedure, Shall Be To The Approval Of The Engineer. F. Formation Stabilizer/gravel Pack A. Scope The Contractor Shall Provide And Install Formation Stabilizer, Or Gravel Pack If Specified In The Contract Drawings And The Special Technical Conditions. B. Material 1. The Formation Stabilizer/gravel Pack Material Shall Consist Of Well Rounded, Water-worn Siliceous Grains. Angular Chipping Or Road Stone Must Under No Circumstances Be Used As Formation Stabilizer/gravel Pack Material. 2. The Contractor Shall, During The Mobilization Period, Submit To The Engineer For His/her Approval, Samples Of The Formation Stabilizer He/she Proposes To Use, Stating The Source Of The Formation Stabilizer, Quantities Available, Rate Of Delivery And Any Other Information Requested By The Engineer. C. Method Of Installation 1. The Method Of Placing The Formation Stabilizer/ Gravel Pack In The Annulus Shall Be Such That Separation Of The Gravel And Bridging Is Avoided. 2. The Formation Stabilizer/gravel Pack Shall Immediately Upon Completion Of Lining Installation, Be Placed In The Annulus Between The Borehole And The Lining, In The Screened Section(s) Of The Lining, As Specified In The Final Well Design. 3. If The Borehole Was Drilled By The Rotary Method, Installation Of Formation Stabilizer/ Gravel Pack Shall Be Done By Circulation Of The Drilling Mud. G. Well Development A. Scope 1. The Contractor Shall Furnish Compressors, Surge Plungers, Jetting Tools, Electric Generators, Chemicals And Any Other Equipment Required For Satisfactory Well Development And Shall Undertake The Development As Directed By The Engineer. 2. Development Shall, If The Percussion Drilling Method Is Applied, Comprise Surging With Plunger And Development By Airlifting Unless Otherwise Specified In The Special Technical Conditions. 3. Development Shall, If The Rotary Method Is Applied, Comprise Deflocculation, High Velocity Jetting In Continuous Slot Screens, Surging With Plunger In Slotted Screens And Development By Airlifting, Unless Otherwise Specified In The Special Technical Conditions. B. Surging With Plunger 1. Upon Completion Of Installation Of Lining Or Formation Stabilizer/gravel Pack, The Contractor Shall Develop The Well By Mechanical Surging With A Valve-type Surge Plunger Approved By The Engineer. 2. Before Start Of Surging And With 1 Hour Intervals During The Surging Operation, The Depth To The Well Bottom And To Top Of Gravel Pack Shall Be Recorded. 3. Surging Shall Be Continued Until Accumulation Of Sediments In The Sump Pipe, During A 1 Hour Period Surging Operation, Is Negligible. C. Deflocculation (applicable For Rotary Method Only) 1. Upon Completion Of Installation Of Lining Or Formation Stabilizer/gravel Pack, The Drilling Mud Shall Immediately Be Displaced From The Well By Pumping Clean Water Into The Sump Pipe. 2. Mud Displacement Shall Immediately Be Followed By Injection And/or Jetting Through The Screened Sections With A Mud Thinner To Deflocculate The Mud Cake On The Borehole Wall. The Well Shall Then Be Left For 12-24 Hours Before Developing Is Continued, To Allow The Mud Thinner To React. D. High Velocity Jetting 1. After The Deflocculation Material Has Been Allowed To Work For 12-24 Hours All Sections Screened With Continuous Slot Screens Shall Be Developed By High Velocity Jetting 2. The Jetting Tool Shall Be Equipped With Two Or Four Nozzles. The Nozzle Design Shall Be Such That It Produces A Concentrated Jetting Action. The Tool Shall Be Presented To The Engineer For Approval Before Start Of Drilling Operation. 3. The Jetting Tool Shall Be Supplied With Water Through A High-pressure Pump Capable Of Producing A Nozzle Velocity Of 50-70 M Per Second. The Pump Shall Be Equipped With A Suitable Pressure Gauge On The Discharge Side To Facilitate Monitoring Of Nozzle Velocity. 4. The Development Shall Be Carried Out By Slowly Rotating The Jetting Tool And Gradually Lowering It In Order To Cover The Entire Surface Of The Screen. 5. At The Same Time As The High Velocity Jetting Is Performed, The Well Shall Be Discharged With A Discharge Rate Slightly Higher Than The Discharge Rate From The Jetting Tool. 6. Each Section Of The Screen Shall Be Jetted Until The Return Water Is Free From Drilling Mud, But No Section Shall Be Jetted Less Than 20 Minutes Per Meter Of Screen. E. Development By Airlifting 1. Upon Completion Of High-velocity Jetting, And/or Surging With Plunger, The Well Shall Be Discharged By The Airlifting Method. 2. The Compressor Used For Pumping By Airlifting Shall Be Capable Of Developing A Minimum Pressure Of Not Less Than 250 Psi. The Delivery Shall Be No Less Than 21.25 Cum Air Per Minute. 3. The Quantity Of Water Discharged From The Well And The Drawdown In The Well At The Commencement Of The Development Shall Be Limited And Shall Be Gradually Increased Only As The Water Clears. From Time To Time The Air Flow Shall Be Stopped To Facilitate Loosening Of Trapped Sand Grains. The Well May Also Be Backwashed By Pumping Clean Water Into The Well. 4. During The Airlifting Operation, Position Of Air Pipe And Conductor Pipe, Drawdown In Well, Approximate Yield And Time For Each Change In Position Shall Be Recorded By The Contractor. 5. The Development Shall Be Completed With A Conductor Pipe Not More Than 0.5 M Above The Bottom Of The Well To Ensure That All Sand Has Been Cleaned Out Of The Sump Pipe. F. Well Cleaning Upon Completion Of The Development Operations, The Contractor Shall Demonstrate To The Satisfaction Of The Engineer That The Bottom Of The Well Is Clear Of All Sand, Mud And Other Foreign Materials. G. Freedom From Sand 1. The Contractor Shall Develop The Well By The Methods Specified Until The Water Pumped From The Well Is Substantially Free From Sand And Until The Turbidity Is Less Than 5 On The Silica Scale Described In Standard Methods Of Water Analysis (latest Edition As Published By Awwa, Apha And Wpct). 2. The Water Pumped From The Well Shall Not Contain An Amount Of Fine Material In Excess Of 1.0 Mg Per Liter When The Well Is Pumped At Its Maximum Expected Yield. The Equipment For Measurement Of The Sand Content Shall Be Furnished By The Contractor. H. Acceptance Of Development 1. The Development By The Specified Methods Shall Be Repeated And Continued Until The Well Is Thoroughly Developed In Accordance With The Criteria Specified In Section G.h. 2. If The Well Yield After The Well Has Been Confirmed Sand-free Is Still Below The Yield, Which Is Considered Acceptable For The Penetrated Aquifer, Then The Engineer May Instruct The Contractor To Perform Further Development. H. Well Testing A. Scope The Contractor Shall, Unless Otherwise Specified In The Special Technical Conditions, Provide And Operate A Pumping Unit For The Following Purposes: 1. Step-drawdown Pumping Tests On The Completed Well 2. Continuous Constant Discharge Pumping Test On The Completed Well. B. Equipment Capacity 1. The Contractor Shall Provide And Operate Pumping Machinery Capable Of Carrying Out The Specified Pumping And Shall Provide Adequate Controls To Allow Discharge Rates To Be Kept Constant At Varying Pumping Water Levels And To Permit Pumping With A Variation Of Not More Than 5% Of The Designated Discharge Rate During Any Period Of Yield Or Aquifer Testing. 2. The Pumping Unit Set Shall Be Able To Deliver A Discharge Rate, Which Is Min. 50% Higher Than The Expected Yield Of The Well And A Minimum Discharge, Which Is Maximum 15% Of The Expected Yield Of The Well When Suitably Throttled By Use Of A Gate Valve. 3. Suitable Pumping Machinery Will Be Deemed To Be: I. Submersible Electric Pump Unit Together With Generator And Such Accessories Needed To Run The Pump. Ii. Line-shaft Pump And Internal Combustion Prime Mover Together With All Accessories Needed To Run The Pump. C. Equipment Operation 1. The Contractor Shall Supply And Operate All Equipment And Accessories Necessary For Installation And Removal Of Pumps. 2. The Contractor Shall Maintain On Site Sufficient Fuels, Lubricants, Spares And Other Accessories Needed To Run The Pumping Unit For Whatever Period May Be Specified By The Engineer. 3. The Contractor Shall Provide Sufficient Competent Personnel Including A Qualified Fitter And Electrician, As May Be Necessary To Install And Operate The Pumping Unit. D. Control Of Discharge Rate The Contractor Shall, During The Pumping Tests, Provide A Suitable Gate Valve On The Discharge Pipeline, To Facilitate Easy Control Of The Discharge Rate. Discharge Shall Be Controlled With A Valve Fitted Behind The Elbow And Measured With A Water Meter, Fitted At A Distance Of Not Less Than 1 M Behind The Valve. An Additional Measuring Device (e.g. Oil Drum And Stopwatch) Shall Be Provided For Back Up And Checking. Drawdown And Recovery Of The Water Level Is To Be Monitored With A Water Level Indicator Through The Piezometer Pipe At Intervals As Specified By The Engineer On The Site. The Engineer May Demand Water Quality Measurements. He Will Provide The Monitoring Forms. E. Water Level Sounding Pipe 1. The Contractor Shall, If Instructed By The Engineer, Provide And Install A Temporary Tube Of At Least 1 Inch Diameter From The Top Of The Well To 2 Meters Above The Pump Bowl Assembly To Facilitate Easy Measurements Of Water Level. The Tube Shall Be Open Only At The Bottom And Top. 2. Payment For Providing, Installing And Removing The Tube Shall Be Deemed To Be Included In The Rates Given For Pumping Tests. F. Discharge Rate Monitoring Discharge Rates Up To 10 L/s (36 Cum/hr) May Be Measured By Drum Filling. Discharge Rates In Excess Of 10 1ps Shall Be Recorded With A Water Meter Or By A V-notch Weir Or With Orifice Discharge Pipe. All Items Are Subject To The Engineer's Approval Before Start Of Drilling. G. Definition Of "pumping Unit" The Equipment Specified In Section H.b – H.f Is Referred To As The Pumping Unit. H. Pumping Procedure The Engineer Will Determine The Pumping Procedure Necessary To Obtain The Objectives Of This Contract. I. Suspension Of Pumping If The Engineer Finds The Condition Of Any Equipment, Personnel, Fuel, Lubricants Or Accessories Will Prejudice The Quality Of Data Obtained From Any Pumping Test, He May Suspend The Work In Accordance With The Provisions Of The Conditions Of The Contract. J. Equipment Breakdown During Pumping 1. The Pumping Must Be Continuous And At A Constant Rate During The Pumping Tests. The Engineer Will Instruct The Contractor As To The Expected Maximum Duration Of Each Pumping Test Before Start Of Each Test. 2. If Pumping Is Interrupted Or The Discharge Rate Fluctuates By More Than 5% Of The Designated Discharge Rate, The Test May Be Repeated After A Period Of Recovery Determined By The Engineer. 3. If Any Pumping Test Is Interrupted Because Of Equipment Breakdown Or Inadequate Supervision Or Discharge Control, No Payment Will Be Made For Any Pumping Period Before Commencing The Test. K. Duration Of Tests 1. The Step-drawdown Pumping Tests Shall Be Performed On 5 Steps With A Duration Of 1 Hour Each. 2. The Continuous Constant Discharge Pumping Tests Shall Be Performed For A Period Of 3-5 Days, Unless Otherwise Specified In The Special Conditions Of The Contract Or Unless Otherwise Instructed By The Engineer. L. Temporary Pipeline 1. The Contractor Shall Provide A Temporary Pipeline As Directed By The Engineer For The Discharge From Pumping Tests And For Clearance To A Suitable Watercourse Or Drain. 2. Under Certain Circumstances When Re-infiltration Cannot Be Avoided Or It Is Costly To Provide For This Condition, The Engineer Shall Decide To What Distance From The Well, Water May Be Discharged On The Ground. I. Cement Grouting A. Scope The Contractor Shall, Unless Otherwise Specified In The Special Conditions Of The Contract, Provide The Cement And Mixing Equipment Required For The Mixing Of The Grouting Indicated In The Tentative Well Design And Shall Place The Cement Grout As Specified. B. Grouting Material 1. Cement Grout Shall Consist Of A Mixture Of 95% Portland Cement, 5% Bentonite And Clean Water, Mixed In The Proportion Of 52.5 Kg Of Portland Cement/bentonite To Max. 30 Liters Of Water. 2. All Cement Shall, Unless Otherwise Specified In The Contract Documents, Conform To The "specifications For Portland Cement" (astm C150-latest Revision). C. Method Of Placing Grout Material 1. The Method And Equipment For Placing The Grout Shall Be To The Approval Of The Engineer. No Method Will Be Approved That Does Not Provide For The Forcing Of Grout From The Bottom Of The Casing/hole/annulus To Be Grouted, To The Surface. Flushing Of The Annular Space With Fluid To Assure The Space Is Open And To Remove Loose Material Will Be Required To The Contractor Before Grouting Is Commenced. 2. Any Grouting Operation Shall Be Continuous And Before Starting, Sufficient Grout Shall Be Mixed To Complete The Whole Operation. During The Grouting Operation, The Mixed Grout Shall Be Continuously Stirred. The Contractor Shall Provide Such Tanks, Hoppers And Other Equipment As May Be Necessary To Meet These Requirements. D. Setting Time No Work Will Be Allowed On The Well Within A Period Of 72 Hours After Completion Of Grouting Unless Quick Setting Cement Is Used. In Such Case, The Idle Period May Be Reduced To 24 Hours Subject To The Engineer's Prior Approval. J. Well Completion A. Scope The Contractor Shall Provide And Operate All Equipment Necessary To Restore The Site As Near As Possible To Its Condition Before Commencement Of Drilling And Shall Furnish And Install A Well Head Cap As Specified In The Contract Drawings. B. Site Restoration The Site Shall Be Restored To A Condition As Nearly Possible To That Which Existed Before The Well Drilling And Testing Activities Commenced. This Work Shall Include, But Not Be Limited To, Restoration Of Fences And Structures, Removal Of Drill Cuttings, Leveling Of The Disturbed Ground Surfaces And Replacement Or Compensation For The Destroyed Plants And Landscaping. C. Well Head Capping The Well Head Shall Be Completed With A Well Head Assembly Fully Welded To The Upper Casing As Well As A Water Level Sounding Tube With Screw Cap In Order To Prevent Any Unauthorized Tampering Of The Well.
Closing Date19 May 2025
Tender AmountPHP 2.3 Million (USD 42.7 K)
211-220 of 215 archived Tenders