Rural Development And Panchayati Raj Department Tender
Search from the latest JKtenders and find a business opportunity fitting your SME on the online platform of BidAssist. If you're wondering how to find the latest JK tenders or from where to get all the documents without the hassles, this is what we explain here. Find the best opportunities coming to the surface via the JK government, PSUs and state corporations.
Rural Development And Panchayati Raj Department - RDPR Tender
Civil And Construction
Drainage Work
Eprocure
Opening Date18 Nov 2024
Closing Date25 Nov 2024
Tender Amount₹ 2,48,000
Costs
EMD
₹ 4,960Document Cost
₹ 500Tender Fee
Refer Documents
Summary
Construction Of Lane, Drain With Tile Work From Road To New Colony Kana Near H/o Bashirabibi W.no.1, Pyt. Kc Upper Block Nagrota Under Scheme Capex (pri Component) For The Year 2024-25
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_RDPR_264939_9Tender No
e-NIT No.373 -REWJ of 2024 dated.18-11-2024Tender Authority
Rural Development And Panchayati Raj Department ViewPurchaser Address
-Website
http://http://drdj.nic.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
Providing and laying in position cement concrete (1:3:6) mix of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: including curing but excluding cost of formwork A) 70 % CEMENT CONCRETE
12.08
5733
69261.89
Providing and laying in position cement concrete (1:3:6) mix of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: including curing but excluding cost of formwork B) 30% PLUM CONCRETE
5.18
937
4858.32
Centering and shuttering including strutting, propping etc. and removal of form work for: Foundations, Footings , Bases for Columns
92
286
26344.2
Cement concrete flooring 1:2:4 (1cement: 2 coarse sand: 4 graded stone aggregate) finished with a floating coat of neat cement including cement slurry and curing complete, but excluding the cost of nosing of steps etc. complete. 50mm thick
27.6
562
15515.34
Providing and laying 60 mm thick factory made cement concrete interlocking paver block of M30 grade made by block making machine with strong vibratory compaction and of approved size and design/ shape laid in required colour and pattern over and including 50 mm thick compacted bed of fine sand. filling the joints with coarse sand and etc all complete as per direction of engineer in charge
82.8
816
67577.22
Providing and laying in position specified grade of reinforced cement concrete including curing but excluding the cost of centering, shuttering, finishing and reinforcement. Allworks upto plinth level1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size)
0.32
7788
2492.29
Centering and shuttering including strutting, propping etc. and removal of formforSuspended floors, roofs, landings, balconies and access platforms.
0.72
718
517.1
Steel reinforcement for R.C.C. work including straightening, cutting, bending lacingin position and binding all complete @110kg/cum
35.64
123
4390.85
Carriage of key construction material from source to site of work Sand & Agg.avg. 5.0 km lead by MT
31.13
200
6249.04
Carriage of key construction material from source to site of work Stone avg. 10.0 km lead by MT
5.18
328
1700.8
Add Cost of Sign Board including painting and writting complete job
1
2000
2000