Indian Oil Corporation Limited Tender
If you want to inquire about any e-tender the Haryana government has posted, Bidassist gives a one-stop solution i.e. being a registered bidder you will find every eprocurement Haryana tender on BidAssist.There is no need to enter all the details on the website of etender.up.nic.in as BidAssist helps you find the specific Haryana etender you're looking for. Read further to learn how to search and bid for etender Haryana.
Costs
EMD
0Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_PR_178744_1Bid Award Id
ViewTender No
9065C24E81Tender Authority
Indian Oil Corporation Limited ViewPurchaser Address
-Website
http://https://www.iocl.com/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
Bidders_help_Document_for_Preferencial_ Bidding_20230207_v1
Special_Instructions_to_the_Bidders_20230207_version_1a
BOQ Items
The job involves carriying out dismantling & relining of refactory brick including micro porous boards lining between bricks and shell inside radiant and transition section of heaters as per scope of work and drawing including the cost of manpower deployment and necessary tools tackles all complete as per tender and instruction of Engineer-In-charge.
120
-
-
API-936 Certified Refractory Inspectors: Deployment of API-936 Certified Refractory Inspectors during shutdwon of all process units of Refineries and providing the services as below, but not limited to, such as : *Inspection of installed refractory and provide recommendations. *To ensure that material and applicator qualification test results are line with job requirement and are fully documented *To inspect and physically verify that installation of hex-mesh, V-Bar S-Bars or other anchors has been carried out as per the design / drawing of refractory lining job. *To carry out physical verification of refractory materials before installation and ensure the same are in line with the engineering drawings/ datasheet. *To check and verify that accurate refractory installation procedures *To monitor, guide and assist owner and contractor to ensure desired progress of work *To assist owner and contractor in maintaining safety procedure / conditions *To check and verify accuracy of refractory Dry-out procedures *To inspect and test installed linings before Dry-out and after Dry-ou *To notify the owner and the contractor of any work deficiencies or potential deficiencies *To record all non-conformances and / or potential problems *To intimate conflicts, if any, between the specified execution plan and the actual installation procedures or installed refractory quality results *To prepare inspection report at suitable intervals *To certify that all the anchoring systems and refractory lining jobs including selection of all materials, installation, and Dry-out procedures have been carried out as per design / drawing / OEM / Manufacturer’s recommendation and direction of Engineer-in-Charge. with all manpower, material, tools and tackles, equiments, comsumables etc as per the direction of Engineer-in-Charge. Travel expenses: The rates are inclusive of To and Fro Travel expenses of the Refractory Inspectors prior to and after completion of deployment at the Refinery location. However, To and Fro transport facility from Stay accommodation to Refinery shall be arranged by the Owner Free of Cost during the period of deployment. "Accommodation expenses: The rates are exclusive of Hotel accommodation charges during the period of deployment. Stay accommodation for the Refractory Inspectors shall be provided by the Owner free of cost in their Guest House / Transit Accommodation / Nominated Hotel located near the Refinery. In case of non-availability of Owner’s accommodation, actual expenses towards Hotel accommodation for both the Refractory Inspectors in a single room (on double occupancy basis) in a Three-star or equivalent hotel from evening of one day prior to start of deployment up to next morning of last day of deployment shall be reimbursed on submission of valid documents. Note: EA stands for working for 12 Hours shift in Day or Night Separate Refractory Inspectors shall be deployed for Day and Night Shifts.
80
-
-
Replacement of Muffle Blocks assembly and associated refractory lining required for replacement of Muffle Blocks (Burner Tiles) assembly in NCU Heaters with all tools / tackles, machinery and lifting arrangement system as per drawing, detail specification and as per instruction of Engineer-in-charge (EIC)
-
-
-
Removal of old muffle blocks (Burner Tiles) assembly from heater radiant section including lifting and pulling with all tools, tackles, lifting arrangement, refractory bricks supporting arrangement etc. all complete. EA shall mean complete set of burner tiles for one burner.
10
-
-
Lowering and shifting of muffle blocks (Burner Tiles) assembly from site position and disposal at scrap yard or other location within Plant. EA shall mean complete set of burner tiles for one burner.
10
-
-
Transportation of new muffle blocks (Burner Tiles) assembly from IOCL store to work site with necessary safety to avoid any damage during shifting EA shall mean complete set of burner tiles for one burner.
10
-
-
Lifting and installation of new muffle blocks (Burner Tiles) assembly properly and safely in NCU Heater including required refractory repair if any with tools, tackles, lifting arrangement etc. all complete. (Supply of Muffle block assembly and refractory material will be in IOCL Scope) EA shall mean complete set of burner tiles for one burner.
10
-
-
Installation of pyro-block "M" type/"Z" Type/T-bar/ any other type of ceramic module of all sizes and shapes over the 25mm thick back up lining of ceramic fibre blankets in heaters/boilers including gap filling, removal of damaged module, ceramic linings etc. as per drawings and direction of Site Engineer/Site In-charge. Scope of job includes supply of all labours, supply of necessary tools & tackles, marking of lugs position, sealing the gaps, carriage of modules from nearest store to location of fixing, removal of debris from working platform to place of disposal within Plant as per direction of EIC. Ceramic modules, lugs, U-pins, ceramic blanket and scaffolding shall be in owner’s scope.