BidAssist is a very user-friendly website which helps in finding the specific Assam e-tender that one is looking for. For getting any information or detail about any e-tender the Assam government must have posted, BidAssist is designed in such a manner so as to provide information on all government tenders in one place without any inconvenience.

Public Works Roads Department - PWRD Tender

Works
Civil And Construction
Bridge Construction
Eprocure
Opening Date15 Jun 2024
Closing Date5 Jul 2024
Tender Amount₹ 3,87,51,000 
Notes
Download

Costs

Summary

Construction Of Bridge In Dibrugarh District I) Br. No. 1/1 Lekai Mohmari Road

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
b) Routine Load Test of 2x160x2.50 2 Nos. test for piles upto 50 Nos.

800

-

-

... More
Pile integrity test of piles by using pile driving analyser or equivalent as approved by the E-IN-C and detail specification . Test to be carried out by an approved reputed agency including all incidental works.

8

-

-

... More
Cement concrete for reinforcement concrete in pile cap complete as per drawing and technical specifications. D. RCC grade M - 35 i) Using concrete mixer

252.91

-

-

... More
Levelling course for Pile cap Providing and lying of PCC M - 15 levelling course 100 mm thick below the pile cap. as per drawing and technical specifications.

14.15

-

-

... More
Supplying, fitting and placing uncoated TMT Bar reinforcement in foundation complete as per drawing and Technical Specifications. (a) TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/ SAIL/ Esser Steel/ Jindal panther steel/ Shyam steel or equivalent)

82.56

-

-

... More
Plain/ Reinforced Cement Concrete in substructure complete as per Drawing and Technical Specifications. (N) Without plasticiser H) a) RCC Grade M 35 a) Height up to 5.0 m Case-I : Using Concrete Mixer

190.26

-

-

... More
Supplying, fitting and placing TMT bars reinforcement in substructure complete as per drawing and Technical Specifications. b) (a) TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/ SAIL/ Esser Steel/ Jindal panther steel/ Shyam steel or equivalent)

28.02

-

-

... More
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specification.

42

-

-

... More
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification

153.75

-

-

... More
Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surfaces behind the abutement, wing wall and return wall to the full height compacted to firm condition complete as per drawing and technical specification.

63.62

-

-

... More
Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of a metal piston supported by a disc or unreinforced elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE surface sliding against stainlesssteel matting surfaces, complete assembly to be of cast steel/fabricated structural steel, meatal and elastomer elements to be as per IRC:83 part-I &II respectively and parts conforming to BS:5400, complete as per drawing and approved technical specification.

2340

-

-

... More
Furnishing and placing reinforcement / prestressed cement concrete in super structure as per drawing and technical specifications. (N) Without Plasticiser D. RCC/ PSC grade M - 35 Case I : Using concrete mixer For T beam and slab, 1) Height up to 5.0 m

259.47

-

-

... More
E. RCC Grade M-40, For T beam and slab 1) Height up to 5.0 m

29.81

-

-

... More
Supplying , fitting and placing TMT bar reinforcement complete as per drawing and technical specifications. (a) TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/ SAIL/ Esser Steel/ Jindal panther steel/ Shyam steel or equivalent)

53.44

-

-

... More
Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per drawing and Technical Specifications

34.29

-

-

... More
Providing Drainage Spouts complete as per approved drawing and technical specifications.

20

-

-

... More
PCC M15 Grade leveling course below approach slab complete as per drawing and Technical specification

8.05

-

-

... More
Reinforced cement concrete approach slab including reinforcement and formwork complete as per drawing and Technical specification (a) TMT Corrosion Resistant Steel (CRS) reinforcement bar of Fe-500 N/mm2

15.65

-

-

... More
Providing Strip Seal Expansion Joint to cater movement of +70mm as per drawing.

25.35

-

-

... More
Span Load Test - Load testing of one or more spans of bridges as selected by the Engineer as per approved load test procedure following relevant IS/IRC/Railway codes with contractor's labour, deflection measuring instruments, loading materials, recording and analyzing the load testing results including all leads and lifts etc. complete as required. The rates are all inclusive and will be paid after load test is finished and girder is cleared of the kentledges/loading materials etc. The load shall be 1.25 times the stipulated design load based on Design load & not span ( Extra for every increase of 100.00 mt or part there for in the span load capacity up to 800.00 mt.

1

-

-

... More
Non-Destructive testing with Ultrasonic Pulse Velocity Meter with data storage facility for detection of cracks, voids and other imperfections in Reinforced concrete structures and furnishing the findings thereof in proper comprehensible format, complete as directed by the department

18

-

-

... More
Non-destructive testing with rebound hammer for detection of damage zones in Reinforced concrete structures and furnishing the findings thereof in proper comprehensible format

40

-

-

... More
Providing and laying of boulder apron laid in wire crates with 4 mm dia GI wire conforming to IS:280 and IS:4826 in 100 mm x 100 mm mesh (woven diagonally) including 10 per cent extra for laps and joints laid with stone boulders weighing not less than 25 kg each as per drawing and technical specifications.

382.43

-

-

... More
Providing and laying pitching on slopes laid over prepared filter media as per drawing and technical specifications. Stone/Boulder

315.77

-

-

... More
Providing and laying filter material underneath pitching in slopes complete as per drawing and technical specifications.

105.26

-

-

... More
Earthwork in excavation for foundation of structures as per drawings and technical specifications , including setting out, construction of shoring and bracing, including dewatering and using machinery, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material . I) In Ordinary Soil B. Mechanical means. i) Depth up to 3.00 m (with dewatering)

245.01

-

-

... More
Plain/Reinforced cement concrete, in open foundation complete as per drawing and technical specification including steel shuttering formwork. I. Without plasticiser A. PCC Grade M15

17.09

-

-

... More
G RCC Grade M30 (i) Using Concrete Mixer

85.26

-

-

... More
Supplying, fitting and placing uncoated TMT Bar reinforcement in foundation complete as per drawing and Technical Specifications. (a) TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/ SAIL/ Esser Steel/ Jindal panther steel/ Shyam steel or equivalent)

4.75

-

-

... More
Plain/ Reinforced Cement Concrete in substructure complete as per Drawing and Technical Specifications. H) a) RCC Grade M 35 I) Height up to 5.0 m Case-I : Using Concrete Mixer

74.45

-

-

... More
Supplying, fitting and placing TMT bars reinforcement in substructure complete as per drawing and Technical Specifications b) (i) TMT-IS 1786 ( Fe-500 D) Primary Producer (TATA/ SAIL/ Esser Steel/ Jindal panther steel/ Shyam steel or equivalent)

12.13

-

-

... More
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specification.

84

-

-

... More
Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surfaces behind the abutement, wing wall and return wall to the full height compacted to firm condition complete as per drawing and technical specification.

60.9

-

-

... More
Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification.

10050.72

-

-

... More
Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification.

1285.74

-

-

... More
Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification. A)By Mix in Place Method

222.08

-

-

... More
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening/binding materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density grading 2 as per Technical Specification. Manual means WBM Grading 2 Using stone screening Type-B 11.2 mm for Gr.II

104.06

-

-

... More
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification. By Manual Means WBM Grading 3 Using stone screening Type-B 11.2 mm for Gr.III

104.06

-

-

... More
Providing and laying interlocking concrete block pavement with M40 grade grade of concrete blocks having thickness 80mm as per technical specification complete including carriage. Including Edge block/ Edge restraints

1390.05

-

-

... More
Furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or other locations shown on the drawing or as directed by the Engineer including preparation of ground, fetching of sods and watering as per Technical Specification.

2683.28

-

-

... More
Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of encapsulated lens type reflective sheeting fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per drawings and Technical Specification. 600mm equilateral triangle

4

-

-

... More
800mm x 600mm rectangular

8

-

-

... More
600mm circular

4

-

-

... More
Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a "W" metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2m center to center, 1.8 m high, 1.1m below ground/road level, all steel parts and fitments to be galvanized by hot dip process, all fitting to conform to IS:1367 and IS:1364, metal beam rail to be fixedon the vertical post with a spacer of channel section 150mmX75mmX5mm, 330mm long complete as per clause 810.)

80

-

-

... More
Planting of Trees and their Maintenance for three Year (Planting of trees by the road side (Avenue trees) in 0.60 m dia holes, 1 m deep dug in the ground, mixing the soil with decayed farm yard/sludge mannure, planting the saplings, backfilling the trenches, watering , fixing the tree guatrd and maintaining the plants for three year.

25

-

-

... More
Construction of cold weather Bamboo bridge overall width of 3.70m and clear road way 3m with jungle wood post 20cm to 25cm dia 5nos. In each rows and rows being 2.1m. apart except for the navigable span which should be 3m. Post to be driven at least 180cm. or more below ground level including providing 20cm to 25cm center to center and placed over 20 cm dia, jungle wood dham, 15cm dia. jungle wood bracing collar fixed by bolts and nuts, straps etc. mature bholuka Bamboo cross groth all closely packed and tied 75cm wide track way made from 38mm thick 1st class local plank fixed on 75mmx100mm first class local wood battens 120cm apart and 3 lines of jati bamboo horizantal railing fixed in bholuka bamboo post placed at 210cm apart and white washed including all necessary nuts and bolts, coir ropes, struts, nails etc. complete with a layer of brushwood to exposed portion out-side trackway with earth topping complete as per direction of the department

50

-

-

... More
Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification.

200

-

-

... More
Implementation of Enviromental and Social Management Plan Air quality monitoring at 3 locations for 2 seasons for 2 consecutive years (Construction Stage)

12

-

-

... More
Implementation of Enviromental and Social Management Plan Air quality monitoring at 3 locations for 2 seasons for 1 Year (Operation Stage)

6

-

-

... More
Implementation of Enviromental and Social Management Plan Water quality monitoring at 3 locations for 2 seasons for 2 consecutive years (Construction Stage)

12

-

-

... More
Implementation of Enviromental and Social Management Plan Water quality monitoring at 3 locations for 2 seasons for 1 Year (Operation Stage)

6

-

-

... More
Implementation of Enviromental and Social Management Plan Noise quality monitoring at 3 locations for 2 seasons for 2 consecutive years (Construction Stage)

12

-

-

... More
Implementation of Enviromental and Social Management Plan Noise quality monitoring at 3 locations for 2 seasons for 1 Year (Operation Stage)

6

-

-

... More
Implementation of Enviromental and Social Management Plan Soil quality monitoring at 3 locations for 2 seasons for 2 consecutive years (Construction Stage)

12

-

-

... More
Implementation of Enviromental and Social Management Plan Soli quality monitoring at 3 locations for 2 seasons for 1 Year (Operation Stage)

6

-

-

... More
A Provisional sum (fixed amount) for items of tree felling/plantation of Rs. 2,29,813.00 (not to be changed by the Bidder in BOQ)

1

-

-



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.